Yinson-Built FPSO En Route to Brazil for Work at Petrobras’ Jubarte Field

Thursday, June 20, 2024

The floating production storage and offloading (FPSO) Maria Quitéria, built by Malaysian FPSO supplier Yinson, has left the shipyard in China and is currently on its way to Brazil, to be deployed at Petrobras’ Jubarte field, located in the Campos Basin.

The FPSO Maria Quitéria departed from China in May and is expected to arrive at its location in the third quarter of 2024.

The unit is scheduled to begin operations in the last quarter of the year, thus advancing the timeline from PE 24-28, initially planned to commence operations in 2025.

It will operate in the Jubarte field, located in the Campos Basin's pre-salt layer, off Espírito Santo's coast.

The FPSO Maria Quitéria has a production capacity of 100,000 barrels of oil and can process 5 million cubic meters of gas.

The FPSO is equipped with decarbonization technologies such as a combined cycle power generation system and FGRU (closed flare).

Petrobras chartered the unit from Yinson, which was also responsible for its construction, under the contract agreed in 2022.

The FPSO is destined for the Jubarte field as part of the Parque das Baleias Integrated Project offshore Brazil.

The Parque das Baleias area is formed by the Jubarte, Baleia Anã, Cachalote, Caxaréu, Pirambú and Mangangá fields. The first field, Jubarte, was discovered in 2001.

In 2019, Petrobras and the National Agency of Petroleum, Natural Gas and Biofuels (ANP) entered into an agreement to extend the concession term until 2056 for the new unified Jubarte field, which makes it possible to implement the new production system of the Parque das Baleias Integrated Project, in addition to complementary projects in the area.

Categories: Industry News Activity FPSO South America Asia Oil and Gas

Related Stories

ADES Lands $117M ONGC Drilling Contracts for Two Jack-Ups

Velesto’s Jack-Up Rig Up for Drilling Job with Petronas

TotalEnergies Inks 15-Year LNG Supply Deal with China's Jiangsu Guoxin

Valaris Secures $600M in New Contracts as Backlog Rises to $4.8B

Aramco Targets Hormuz Bypass with East-West Pipeline Expansion

Aramco Third Quarter Profit Up 35% Despite War Disruptions

CNOOC Set to Restore Production at Major South China Sea Gas Field

Big Oil Pockets Near-Record Profits but Spending Restraint Signals Long-Term Doubts

Woodside Exit Sends East Timor Searching for Greater Sunrise Partner

SLB Secures Aramco Well Construction Work for 450 Wells

Current News

VAALCO Advances Côte d'Ivoire Offshore Exploration Ahead of 2028 Drilling

Aramco’s Building in Riyadh Damaged by Houthi Attack

ADES Lands $117M ONGC Drilling Contracts for Two Jack-Ups

Velesto’s Jack-Up Rig Up for Drilling Job with Petronas

Tender-Assist Rigs: Southeast Asia’s Quiet Workhorses Head for Full Utilization

Aker Solutions Lands Major Role in Qatar’s Offshore Oil Field Revamp

TotalEnergies Inks 15-Year LNG Supply Deal with China's Jiangsu Guoxin

Baker Hughes Sets Up Global Network to Bolster Mature Oil and Gas Fields Production

Valaris Secures $600M in New Contracts as Backlog Rises to $4.8B

Production Restart at Australian Offshore Fields Boosts Jadestone's Oil Output

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com