Prelude FLNG Won't Restart in 2020

Sonali Paul
Friday, October 16, 2020

Royal Dutch Shell said on Thursday its Prelude floating liquefied natural gas (FLNG) project off Australia, off line since early February, is working on restarting operations but would not resume full production this year. 

The troubled Prelude FLNG platform was shut down following an electrical trip and Shell has faced a number of issues over the past few months in trying to restart full production and now does not expect to ship any LNG before next year.

Full production is not expected to resume before year-end. Prelude is a multi-decade project, and our focus is on delivering sustained performance over the long term,” Shell said in a statement.

The company hopes to resume shipping LNG from Prelude in the first quarter of 2021, a person familiar with the situation said.

The $17 billion Prelude project, centered around the world’s biggest floating liquefaction vessel, has been plagued with problems. It shipped its first cargo only last year, more than two years behind schedule, and has yet to achieve steady output at its design capacity of 3.6 million tonnes a year of LNG.

The project is jointly owned by Shell, Japan's Inpex Corp, Korea Gas Corp, and a unit of Taiwan's CPC Corp.

(Reporting by Sonali Paul; Editing by Richard Pullin and Christian Schmollinger)

Categories: Offshore Energy LNG Industry News Activity Floating Production FLNG Australia/NZ

Related Stories

SBM Offshore to Sell 45% Stake in Mexico-Bound FSO to NYK

Inpex Faces Threat of Broad LNG Loading Ban as AU Labour Dispute Deepens

Cambodia Starts UN Process to Resolve Maritime Dispute with Thailand

Petronas Signs 20-year Charter Deal with MISC for Five LNG Carrier Newbuilds

Indonesia’s Mako Gas Project on Track for First Gas in 2027

Valeura Charters Shelf Drilling’s Jack-Up Rig for Gulf of Thailand Ops

Jadestone Secures Gas Sales Deal for Fields Offshore Vietnam

Strike Threat Grows at Ichthys LNG after Workers Reject Deal

Pertamina Unit to Operate Indonesia’s Lavender Block under 30-Year PSC

Borr Drilling Expects Higher Activity as Rigs Return to Work

Current News

Oil Slips as Oman Reports Normal Operations at Key Oil Terminal

Petronas Signs Offshore Oil Recovery Collaboration Deal

SBM Offshore to Sell 45% Stake in Mexico-Bound FSO to NYK

Conrad Secures Drilling Rig for Mako Gas Field off Indonesia

Oman’s Block 50 Offshore Drilling Ops Face Further Delays

Aramco Picks McDermott for Energy Projects in Saudi Arabia

Velesto’s Jack-Up Rig Up for Gulf of Thailand Drilling Campaign

Kuwait Sees 70% Oil Output Recovery within Two Months of Hormuz Reopening

Capricorn Energy Grants Third Extension for Potential Takeover Offer

Ichthys LNG Strike Causes Delay to Taiwan-Bound Cargo

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com