Valeura Makes Progress with Multi-Well Drilling Campaign in Gulf of Thailand

Tuesday, July 8, 2025

Canada-based oil and gas company Valeura Energy has advanced its multi-well drilling campaign offshore Thaild, using Borr Drilling’s Mist jack-up rig.

During the second quarter of 2025, Valeura mobilized Borr Drilling’s Mist jack-up drilling rig to Block G11/48, containing the Nong Yao field.

The drilling campaign is progressing as planned toward its objective of approximately 10 new development wells and is expected to be complete in the fourth quarter of 2025, the company said. 

The campaign will entail new development wells drilled from each of the three Nong Yao wellhead facilities, and will therefore include the first ever infill development wells on the Nong Yao C platform, which the company installed in 2024.

“During the second quarter of 2025 we demonstrated another safe quarter of ongoing production and drilling operations and took a positive final investment decision on our major redevelopment project at the Wassana field, which is now moving to the construction phase.

“While production volumes are down quarter-on-quarter, our plan had always assumed that production would be weighted to the second half of the year and we are therefore maintaining our full-year production guidance range of 23.0 – 25.5 mbbls/d.

“From a financial perspective, we continue to prioritise balance sheet strength, and firmly believe this will serve our stakeholders well as we pursue opportunities to add value.  While the headwinds of lower global oil prices during the quarter are apparent in our revenue of $129.3 million, we are continuing to invest while maintaining a strong cash position,” said Sean Guest, President and CEO of Valeura.

Aside from Nong Yao, Valeura took a final investment decision on redevelopment the Wassana field in licence G10/48 in May 2025.

The project will entail deployment of a new central processing platform facility on the field, intended to increase production, reduce costs, and create a hub for eventual tie-in of potential additional satellite wellhead platforms. 

According to the company, the project is on plan, and is currently moving into its construction phase, with the first production targeted for the second quarter of 2027.


Categories: Drilling Industry News Activity Asia Oil and Gas

Related Stories

SBM Offshore Starts Construction of FSO for Trion Oil Field off Mexico

MDL Secures Cable Laying Job in Asia Pacific

Hanwha Ocean Enlists ABB for Singapore’s First Floating LNG Terminal

TotalEnergies Inks 10-Year LNG Supply Deal with South Korea’s KOGAS

Japan Picks Wood Mackenzie to Assess Trump-Backed Alaska LNG Scheme

PTTEP Greenlights $320M Offshore CCS Project at Arthit Gas Field in Thailand

Marco Polo Picks Salt Ship Design for Next-Gen Offshore Energy CSOV

Valeura Energy, PTTEP Partner Up on Gulf of Thailand Blocks

CNOOC Finds Oil and Gas in South China Sea

TPAO, SOCAR and BP to Ink Caspian Sea Oil and Gas Production Deal

Current News

MODEC Ramps Up Hammerhead FPSO Work After ExxonMobil's Go-Ahead

Aesen, DOC JV Targets Subsea Cable Logistics

Timor Gap Boosts Stake in Finder Energy’s Timor-Leste Oil Fields

SBM Offshore Starts Construction of FSO for Trion Oil Field off Mexico

Russia Targets 2028 for Sakhalin-3 Gas Project Start Up

Seatrium Secures ABS Backing for Deepwater FPSO Design

MDL Secures Cable Laying Job in Asia Pacific

Hibiscus Petroleum Starts Drilling at Teal West Field off UK

Yinson Production Nets DNV Approval for New FPSO Hull Design

Hanwha Ocean's Tidal Action Drillship Starts Maiden Job with Petrobras

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com