Shell's Australian FLNG Facility Poised for Mid-November Restart

Marwa Rashad and Ron Bousso
Wednesday, October 18, 2023

Shell is expected to complete maintenance at its flagship Prelude liquefied natural gas (LNG) facility off Australia by mid-November, two sources close to the project told Reuters on Wednesday.

The British energy giant started maintenance work at the 3.6-million metric ton a year floating LNG plant in August. A top Shell executive then said in September it was a "major turnaround" work that would last roughly two months.

The maintenance is now expected to be completed by mid-November, slightly longer than initially planned after several new issues were discovered and fixed, one of the sources said.

"The first LNG delivery cargo is now expected by mid-November," the second source said.

The last cargo to have left the facility was on Aug. 19.

"Shell regularly undertakes maintenance at all its facilities as required to ensure they are delivering safe and reliable performance over the long-term. Turnaround at Prelude commenced in August and is expected to take several months," a Shell spokesperson said.

Prelude, whose deck is longer than four soccer fields, was the world's first floating LNG facility to use novel technology and cost over $12 billion, according to estimates.

The facility, some 475 kms (300 miles) off the west coast of Australia, has suffered a string of outages since it started production in June 2019, including a fire that led to a full power loss in December 2021.      

Reuters reported in September that Shell considered shutting Prelude for a year to fix issues that have plagued its operations, but instead opted for a shorter maintenance period.   

(Reuters - Reporting by Marwa Rashad and Ron Bousso; Editing by Emelia Sithole-Matarise)

Categories: Offshore LNG Industry News Activity Gas FLNG Australia/NZ

Related Stories

Oil Up 8% as Middle Eastern War Rages

GLO Marine to Invest $7M in New Vessel Retrofit Hub in Romania

MISC, PTSC Extend Ruby II FPSO Operations Offshore Vietnam

Mubadala Hires SLB for Deepwater Drilling Services Offshore Indonesia

Transocean-Valaris Tie-Up to Create $17B Offshore Drilling Major with 73 Rigs

Japan's Mitsui in Advanced Talks for Stake in Qatar’s North Field LNG Project

Inpex Moves to Accelerate Indonesia’s Abadi LNG Project

ADNOC Gas Signs $3B LNG Supply Deal with India’s HPCL

Thailand's Gulf Energy Eyes Long-Term LNG Supply

DOF Bags Two Deals in Asia-Pacific Region

Current News

Petronas Picks OceanSTAR Elite FPSO for Asian Oil and Gas Project

Velesto Inks Five-Year Drilling Deal for Jack-Up Rig with Petronas

Arabian Drilling Reactivates Fleet as GCC Offshore Contract Starts

Qatar LNG Halt Forces Asia to Seek Alternative Supplies

China Looks Best Placed to Weather Iran Energy Shock

Qatar Stops LNG Output, Other O&G Fields Shut as War Rages

Oil Up 8% as Middle Eastern War Rages

QatarEnergy Selects Technip Energies JV for North Field West Expansion Work

Velesto Lands Jack-Up Drilling Deal with Jadestone off Malaysia

Inpex Eyes Mid-Year Bids for $21B Indonesia LNG Project

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com