Shell's Australian FLNG Facility Poised for Mid-November Restart

Marwa Rashad and Ron Bousso
Wednesday, October 18, 2023

Shell is expected to complete maintenance at its flagship Prelude liquefied natural gas (LNG) facility off Australia by mid-November, two sources close to the project told Reuters on Wednesday.

The British energy giant started maintenance work at the 3.6-million metric ton a year floating LNG plant in August. A top Shell executive then said in September it was a "major turnaround" work that would last roughly two months.

The maintenance is now expected to be completed by mid-November, slightly longer than initially planned after several new issues were discovered and fixed, one of the sources said.

"The first LNG delivery cargo is now expected by mid-November," the second source said.

The last cargo to have left the facility was on Aug. 19.

"Shell regularly undertakes maintenance at all its facilities as required to ensure they are delivering safe and reliable performance over the long-term. Turnaround at Prelude commenced in August and is expected to take several months," a Shell spokesperson said.

Prelude, whose deck is longer than four soccer fields, was the world's first floating LNG facility to use novel technology and cost over $12 billion, according to estimates.

The facility, some 475 kms (300 miles) off the west coast of Australia, has suffered a string of outages since it started production in June 2019, including a fire that led to a full power loss in December 2021.      

Reuters reported in September that Shell considered shutting Prelude for a year to fix issues that have plagued its operations, but instead opted for a shorter maintenance period.   

(Reuters - Reporting by Marwa Rashad and Ron Bousso; Editing by Emelia Sithole-Matarise)

Categories: Offshore LNG Industry News Activity Gas FLNG Australia/NZ

Related Stories

US Pressure on India Could Propel Russia's Shadow Oil Exports

Eni-Petronas Gas Joint Venture Up for Launch in 2026

Hanwha Ocean Enlists ABB for Singapore’s First Floating LNG Terminal

POSH Set to Tow Nguya FLNG from China to Eni’s Congo Field

TotalEnergies Inks 10-Year LNG Supply Deal with South Korea’s KOGAS

Japan Picks Wood Mackenzie to Assess Trump-Backed Alaska LNG Scheme

CNOOC Brings Online Another Oil and Gas Project in South China Sea

Seatrium Signs FLNG Vessel Upgrade Deal for Golar LNG

Seatrium Engages Axess Group to Clear FPSOs for Brazil Deployment

ADNOC Signs Long-Term LNG Deal with Hindustan Petroleum Corporation

Current News

Pharos Energy Kicks Off Drilling Campaign Offshore Vietnam

Viridien to Shed More Light on Malaysia’s Offshore Oil and Gas Potential

US Pressure on India Could Propel Russia's Shadow Oil Exports

Energy Drilling’s EDrill-2 Rig Starts Ops for PTTEP in Gulf of Thailand

RINA Wins FEED Contract for Petronas’ Flagship CCS Project in Malaysia

ABL Secures Rig Moving Assignment with India's ONGC

Pakistan, Türkiye Deepen Oil and Gas Ties with Offshore Indus-C Block Deal

Eni-Petronas Gas Joint Venture Up for Launch in 2026

Vietsovpetro Brings BK-24 Oil Platform Online Two Months Early

Propane’s Economic Edge for Ports During Trade Uncertainty

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com