FOW Players Target 132kV Dynamic Cables

Elaine Maslin
Wednesday, October 12, 2022

UK industry players are eying the development of 132kV dynamic array cables to meet the demands of ever larger turbines, but there are calls for standards to be agreed before they invest.

The need for 132kV cables is being driven by the growth is turbine capacity to 15MW and beyond, with 20MW turbines even being discussed. These sizes out a strain on use of even the latest 66kV capacity cables, as it reduces the number of turbines per “string” of cable that can be connected – meaning that vastly more cable has to be used.

Robert Keast, program manager at the Carbon Trust, told the joint RenewableUK and Global Underwater Hub Cables conference today that, with today’s 66kV cables, around ten 8MW turbines can be connected via one string. But that falls to just four to five for upwards of 20MW turbines, meaning a lot more cable has to be used (i.e. separate cables back to a transformer hub for each set of four to five turbines), significantly increasing costs.

With 132kV cables, there could even be the option to remove the need for offshore substations, taking each string directly back to shore, says Keast, saving huge costs. This would only work for projects nearer to shore, 20-50km or so, and could face cable landfall and consenting challenges, he says, but it could be an attractive option for the energy islands proposed in the North Sea.

But, to invest in the technology, stepping up from the current 66kV capacity, there needs to be an agreed standard for 132kV dynamic inter array cables, says Aaron Ellis, technical sales manager at JDR Cables, which produced the first 66kV cables.

“If you don’t step up to 132kV, you can’t use those bigger turbines,” he said. “I believe we need CIGRE or IEC to publish a new standard to drive the industry. For us to develop this cable technology would need huge upfront spending. If we qualify that to the old standard and then a developer is not happy we have to restart all of the qualification work. It’s a big problem we have got.”

Keast says that a program at the Carbon Trust – the High Voltage Array Systems Project – is seeing 10 developers looking at this issue and there is a goal to work together and agree a standard, which would give cable manufacturers something to work on. Then, a formal industry standard, from e.g. CIGRE or IEC, could be worked on. “It’s a chicken and egg,” situation he says, with some work needing to be done on design before a formal standard can be drawn up.
Until then, there are a number of questions, including around the best stepping stones to 132kV, one being when developers will actually want them. If they started now, JDR could deliver 132kV cables by 2025, Ellis says.

In addition, cable manufacturers are having to look at how to insulate cables from water. Currently, lead is used thanks to its low melting temperature meaning it can be extruded over the plastic carrier of the cables, making a hermetic seal. But developers are keen for lead to be removed. It’s a challenge in terms of fatigue, is difficult to deal with in terminations and from a sustainability perspective, says Ellis. It’s also difficult to handle because of it weight. This will be the biggest challenge, says Ellis.

There’s also been a push for aluminium, thanks to its lower cost. But its lower weight makes it suboptimal for dynamic cables and it’s more susceptible to corrosion from any water molecule ingress. Ellis says copper would be better and if a “wet” copper design can be qualified this could be done for static cables and then dynamic. However, it could be that aluminium is still used for “dry” static cables, due to it being a third of the price of copper.

Categories: Subsea Industry News Ocean News Subsea Technology Cables

Related Stories

RINA to Conduct Pre-FEED Study for Petronas’ CCS Project in Malaysia

Sapura Scoops Petrobras Contract for Pan-Malaysia Offshore Services

Beam’s AI-Driven AUV to Hit Offshore Wind Market in 2025

Floating Wind and the Taming of Subsea Spaghetti

CNOOC Starts Production from Deepwater Gas Project in South China Sea

Shelf Drilling Finalizes Baltic Rig Sale

SBM Offshore’s FPSO for ExxonMobil’s Guyana Oil Project Takes Final Shape (Video)

CNOOC Maintains Steady Oil Production as Bebinca Typhoon Crosses East China Sea

Shelf Drilling to Consolidate Jack-Up Fleet and Resolve Funding Gaps via Triangular Merger

CNOOC Ticks Another Milestone in Ultra-Deepwater Gas Exploration

Current News

CNOOC Boosts Dongfang Gas Fields Output with New Platform Coming Online

Petronas to Retain National Authority After Sarawak Gas Deal

Yinson Production Scoops $1B Investment to Upscale FPSO Business

Petronas Greenlights Hidayah Field Development Off Indonesia

Abu Dhabi's NMDC Group Gets $1.1B Subsea Gas Pipeline Job in Taiwan

BP Targets 44% Oil, 89% Gas Increase from India’s Mumbai High Field

US Operator Finds Oil Offshore Vietnam

BP to Help Boost Oil and Gas Output at India’s Largest Producing Field

Europe's Gas Uncertainty Help Drive Asian LNG Spot Prices Higher

CNOOC’s South China Sea Oil Field Goes On Stream

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com