Sasanof-1 Drilling: Rig Preps, Checks Underway ahead of Offshore Mobilization, Western Gas Says

OE Staff
Thursday, May 12, 2022

Valaris' MS-1 semi-submersible drilling rig, currently anchored in the Dampier outer harbor in Australia, is on schedule to start tow to the Western Gas' Sasanof-1 location on Monday, May 16, 2022, the oil and gas company said Thursday.

 "Western Gas’ drilling operations team have been deployed to the field and are now onboard the MS-1 rig undertaking pre-mobilization checks," Western Gas said.

As reported last week, drilling support vessels began logistical operations as scheduled on May 9, 2022, transporting and loading drilling equipment and bulk materials to the MS-1 rig.

Solstad's Far Senator anchor handling support vessel loading at Dampier Wharf - Credit: Western Gas 

"More than 800m of 18-3/4” marine riser for deploying the Blow Out Preventer (BOP) is being transported to the rig in preparation of deployment at the Sasanof-1 location (water depth of 1070m).  Drilling operations are expected to commence as planned on 24 May 2022," Western gas said.

The MS-1 offshore drilling rig is expected to take about four days to reach the Sasanof Prospect, which is located around 200 km northwest of Onslow, Western Australia, following which the rig and support vessels will prepare for drilling the Sasanof-1 exploration well.

The well will be drilled vertically to a total depth of 2500 m in 1070 m of water.

According to Western Gas, the Sasanof Prospect covers an area of up to 400 km2 and is on trend and updip of Western Gas’ liquids rich, low CO2 Mentorc field.

ERCE estimates the Sasanof Prospect to contain a 2U Prospective Resource of 7.2 Tcf gas and 176 Million bbls condensate (P501), with a high case 3U Prospective Resource estimate of 17.8 Tcf gas and 449 Million bbls condensate (P101).

 Western Gas (519P) Pty Ltd is the holding company for Sasanof. It has a 52.5% stake in the offshore license, with partners being Global Oil and Gas  – 25%; Prominence Energy – 12.5%;  Clontarf Energy Plc (AIM: CLON) – 10%.

Marine riser loaded on the Far Senator 

Categories: Drilling Industry News Activity Australia/NZ Drilling Rigs

Related Stories

China's CNOOC Posts Record First-Half Profit

BP Completes Central Azeri Platform Maintenance, Ramps Up Production

Iran-Oman Talks on Hormuz Reopening Drive Down Oil Prices

Vantris Energy Secures Petronas’ Offshore Drilling Work Orders

Velesto Frees Up Drilling Rig After Early Contract Termination off Indonesia

Jadestone Energy Lifts Malaysia Production with Second Online Well

Eni and Petronas JV Extend Ventura Offshore’s Drilling Job in Indonesia

Dolphin Drilling’s Blackford Dolphin Secures More Work for Oil India

Oil Holds Steady After US, Iran Agree to Cease Attacks

Walking Into the Future: ADNOC Drilling Unveils First AI-Powered Island Rig

Current News

China's CNOOC Posts Record First-Half Profit

BP Completes Central Azeri Platform Maintenance, Ramps Up Production

Iran-Oman Talks on Hormuz Reopening Drive Down Oil Prices

Viridien Progresses Hybrid Multi-Client Survey Offshore Malaysia

TGS Extends Work on Indonesia’s Largest Seismic Acquisition Project

Saudi Contractor Enters Oman with Four-Well Drilling Assignment

McDermott Gets ADNOC’s ‘Mega Contract’ to Advance Umm Shaif Field

Iran Tightens Enforcement of Strait of Hormuz Transit Rules

TenneT Completes Drilling, Installation of Protective Conduits for Wind Farms

ConocoPhillips, CNOOC Put Penglai Field off China Into Full Operation

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com