Australia's First LNG Import Terminal Seen Ready by Late-2023

By Sonali Paul
Tuesday, March 22, 2022

Squadron Energy, the private company building Australia's first LNG import terminal, expects its Port Kembla facility in New South Wales to be ready to take its first gas shipment by the end of 2023, its commercial director said on Tuesday.

Squadron Energy, owned by Australian mining billionaire Andrew Forrest, is vying against four other proposed LNG import projects looking to fill a shortfall in gas supplies expected in southeastern Australia from as early as 2024, and across eastern Australia from 2027.

Earthworks at the Port Kembla site about 90 kilometers (56 miles) south of Sydney have been completed, work on a new wharf has begun and the facility "will be ready for first gas in quarter four next year," Evonne Bennett told a gas conference in Sydney.

Squadron has lined up the Hoegh Galleon floating storage and regasification unit (FSRU) for its terminal, but has not lined up gas supply yet.

In contrast, rival Viva Energy has lined up a tentative deal for Woodside Petroleum to supply gas to a proposed import terminal in Geelong, near Melbourne.

Viva is awaiting state approval for its project and aims to make a final investment decision by the middle of this year, targeting first gas imports by early 2024.

A third project making progess is run by private group Venice Energy, looking to build an import terminal in the outer harbor of Adelaide, which received approval from the South Australian state government in December.

Venice Energy is working on lining up gas customers ahead of a final investment decision and hopes to start construction in the second half of this year with first gas shipment ready to go into South Australia's network by 2024.

(Reporting by Sonali Paul; Editing by Muralikumar Anantharaman and Sherry Jacob-Phillips)

Categories: LNG Coastal/Inland Australia/NZ LNG Carriers LNG Tankers

Related Stories

McDermott Gets ADNOC’s ‘Mega Contract’ to Advance Umm Shaif Field

TenneT Completes Drilling, Installation of Protective Conduits for Wind Farms

Mermaid Maritime Expands Into US Offshore Market

Oil Rises as Uncertainty Clouds US-Iran Peace Talks

FPSO for Azule Energy’s Angola Offshore Field Starts Taking Shape in China

Sunda Energy Applies for Exploration Permit Offshore New Zealand

Hormuz Reopening Risks Turning Oil Shortage Into Glut

Oil Holds Steady After US, Iran Agree to Cease Attacks

Qatari LNG Carriers Re-Enter Hormuz as Traffic Through Strait Slumps

Inpex, Unions Reach Deal to End Ichthys LNG Strike

Current News

China's CNOOC Posts Record First-Half Profit

BP Completes Central Azeri Platform Maintenance, Ramps Up Production

Iran-Oman Talks on Hormuz Reopening Drive Down Oil Prices

Viridien Progresses Hybrid Multi-Client Survey Offshore Malaysia

TGS Extends Work on Indonesia’s Largest Seismic Acquisition Project

Saudi Contractor Enters Oman with Four-Well Drilling Assignment

McDermott Gets ADNOC’s ‘Mega Contract’ to Advance Umm Shaif Field

Iran Tightens Enforcement of Strait of Hormuz Transit Rules

TenneT Completes Drilling, Installation of Protective Conduits for Wind Farms

ConocoPhillips, CNOOC Put Penglai Field off China Into Full Operation

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com