Australia's First LNG Import Terminal Seen Ready by Late-2023

By Sonali Paul
Tuesday, March 22, 2022

Squadron Energy, the private company building Australia's first LNG import terminal, expects its Port Kembla facility in New South Wales to be ready to take its first gas shipment by the end of 2023, its commercial director said on Tuesday.

Squadron Energy, owned by Australian mining billionaire Andrew Forrest, is vying against four other proposed LNG import projects looking to fill a shortfall in gas supplies expected in southeastern Australia from as early as 2024, and across eastern Australia from 2027.

Earthworks at the Port Kembla site about 90 kilometers (56 miles) south of Sydney have been completed, work on a new wharf has begun and the facility "will be ready for first gas in quarter four next year," Evonne Bennett told a gas conference in Sydney.

Squadron has lined up the Hoegh Galleon floating storage and regasification unit (FSRU) for its terminal, but has not lined up gas supply yet.

In contrast, rival Viva Energy has lined up a tentative deal for Woodside Petroleum to supply gas to a proposed import terminal in Geelong, near Melbourne.

Viva is awaiting state approval for its project and aims to make a final investment decision by the middle of this year, targeting first gas imports by early 2024.

A third project making progess is run by private group Venice Energy, looking to build an import terminal in the outer harbor of Adelaide, which received approval from the South Australian state government in December.

Venice Energy is working on lining up gas customers ahead of a final investment decision and hopes to start construction in the second half of this year with first gas shipment ready to go into South Australia's network by 2024.

(Reporting by Sonali Paul; Editing by Muralikumar Anantharaman and Sherry Jacob-Phillips)

Categories: LNG Coastal/Inland Australia/NZ LNG Carriers LNG Tankers

Related Stories

Murphy Oil Appraisal Well Boosts Resource Outlook at Field off Vietnam

Jereh Group Delivers Oil Separation Systems for Petrobras’ FPSO Units

Offshore Rig Outlook: As 2025 Challenges Fade, Path Ahead Brightens

Following Big Loss in 2025, Oil Steadies

Yinson Production Cuts First Steel for Vietnam-Bound FSO

Japan’s JERA Signs First Long-Term LNG Deal with India’s Torrent Power

CNOOC Puts New South China Sea Development Into Production Mode

MDL Secures Cable Laying Job in Asia Pacific

Hanwha Ocean Enlists ABB for Singapore’s First Floating LNG Terminal

POSH Set to Tow Nguya FLNG from China to Eni’s Congo Field

Current News

Fugro, PTSC G&S Extend Partnership for Vietnam's Offshore Wind Push

Thailand's Gulf Energy Eyes Long-Term LNG Supply

OceanMight Gets Petronas’ Offshore Construction Job in Malaysia

Vantris Energy Lands Petronas Job on Malaysia’s Offshore Fields

Murphy Oil Appraisal Well Boosts Resource Outlook at Field off Vietnam

Viridien Kicks Off Multi-Client Reimaging Program off Malaysia

Petrovietnam Agrees First-Ever LNG Term Deal with Shell

ADNOC Takes FID on SARB Deep Gas Project Offshore Abu Dhabi

Jereh Group Delivers Oil Separation Systems for Petrobras’ FPSO Units

Offshore Rig Outlook: As 2025 Challenges Fade, Path Ahead Brightens

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com