Jan De Nul Installs Cables, Upgrades Substation for Changhua Offshore Wind Farm

Tuesday, August 4, 2020

Belgium-based offshore installation contractor Jan De Nul has completed the installation of four medium-voltage export cables connecting the TPC Changhua offshore wind farm to the shore in Taiwan. 

The company has also upgraded the onshore substation in Changhua County, which was essential for the connection of the first state-owned wind farm ‘Taiwan Power Company Offshore Windfarm Phase 1 Project – Demonstration’ to the Taiwanese power grid.

Jan De Nul’s Cable-Laying Vessel Willem de Vlamingh successfully installed the four subsea export cables from the offshore wind farm site, 10 km off the coast, to the shore where they were connected at the landfall area near Fangyuan.

For the beach pull-in operations including passing over a shallow water sandbank, Jan De Nul Group teamed up with its Taiwanese partner Hung Hua Construction which provided essential marine equipment, including a jack-up barge.

Due to the presence of a nearshore oyster farm and an important shipping lane for fishermen on the subsea export cables route, the cables had to be pulled through 1km-long underground ducts, which had previously been installed by horizontal directional drilling (HDD) up to 21 meters below the seabed.

"Originally, the HDD’s were stipulated in the contract to be 300 meters long, but Jan De Nul decided to extend them in order to prevent any damage to the sensitive coastal zone and fish farms. As such, we demonstrate once more Jan De Nul’s global care for the environment. Our offshore cable team did an amazing job, as did our onshore civil construction team who worked on the HDD together with Taiwanese companies Hung Hua and Magitech”, says Jan Kop, Project Director at Jan De Nul Group.

Credit: Jan De Nul

After the cable installation, trenching works started. For the nearshore trenching works, Jan De Nul’s Starfish excavators used an in-house developed plow-skid and jet-skid. For the offshore trenching operations, the Cable-Laying Vessel Willem de Vlamingh also acted as a Trenching Support Vessel.

Together with its Taiwanese subcontractor Chung-Hsien Chen, Jan De Nul Group completed the installation and commissioning of new electrical equipment, including high voltage transformers, high-voltage and medium-voltage switchgear, a new SCADA control room and emergency power supply, inside the onshore substation in Da Cheng. This upgrade was essential for the substation to be able to receive power generated by the new offshore wind farm.

After passing a 24-hour energization test, the upgraded substation was successfully connected to the national grid for the first time in this new configuration, Jan De Nul said.

In the meantime, the offshore foundation installation of 84 pin piles and 21 jackets is making steady progress and Jan De Nul Group’s consortium partner Hitachi Ltd. continues preparing the wind turbines in the Taichung marshaling port. The turbine installation campaign, due to start in August, will feature Jan De Nul’s Offshore Jack-Up Installation vessel Taillevent.

 The ‘Taiwan Power Company Offshore Windfarm Phase 1 Project – Demonstration’ was awarded to the Consortium Jan De Nul–Hitachi in February 2018.

Credit: Jan De Nul

Jan De Nul Group is responsible for the full balance of plant, including design, fabrication and installation of the foundations, and the provision of the offshore vessel for the installation of the wind turbines. Also included is significant electrical scope, including the supply and installation of the cables both onshore and offshore, as well as upgrading an electrical substation.

Hitachi Ltd. is in charge of manufacturing, assembly, installation and other works related to the 21 Typhoon certified offshore wind turbines using a downwind rotor, each with a capacity of 5.2MW.

The Jan De Nul–Hitachi consortium is responsible for the first five years of operation and maintenance (O&M) of the TPC Changhua offshore wind farm Phase 1.


Watch the recording of World Energy Report's Offshore Wind Webinar "Outlook for Offshore Wind Power: The Frontier of Future Energy."

Categories: Subsea Offshore Wind Asia Subsea Cables

Related Stories

Four Jack-Up Drilling Rig Deals Set to Bring In $129M for Borr Drilling

Centrica and Thailand’s PTT Ink Long-Term LNG Supply Deal

Japan Protests China’s New Oil and Gas Construction Activities in East China Sea

Woodside and Jera Agree LNG Cargoes Supply for Japan’s Winter Period

Yinson Production, “K” LINE Target Europe's CCS with FSIU and LCO2 Solutions

Petronas-Eni Upstream Joint Venture to Take Up to Two Years to Set Up

CDWE Wraps Up Pin Pile Installation Job for Taiwanese Offshore Wind Farm

CIP Reaches Financial Close for Offshore Wind Farm in Taiwan

ORE Catapult and Japan’s FLOWRA to Jointly Advance Floating Wind

Second Hai Long Substation Heads to Project Site Offshore Taiwan

Current News

One Shelf Drilling Rig Up for New Job in India, Other for Disposal

Four Jack-Up Drilling Rig Deals Set to Bring In $129M for Borr Drilling

PTTEP Hires Velesto’s Jack-Up Rig for Drilling Campaign off Malaysia

Yinson Production Secures $1.17B Refinancing for FPSO Maria Quitéria

Centrica and Thailand’s PTT Ink Long-Term LNG Supply Deal

Petrovietnam, Partners Sign PSC for Block Off Vietnam

Japan Protests China’s New Oil and Gas Construction Activities in East China Sea

CNOOC Signs Hydrocarbons Exploration and Production Deal with Kazakhstan

Thailand's PTT to Buy LNG from Glenfarne's Alaska LNG Project

Woodside and Jera Agree LNG Cargoes Supply for Japan’s Winter Period

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com