Woodside Awards Scarborough FEED Contracts

Wednesday, January 16, 2019

Australian independent oil and gas company Woodside said Wednesday it has awarded four contracts for front-end engineering design (FEED) activities for the proposed US$11 billion Scarborough Project offshore Western Australia.

Each contract was awarded and will be funded initially by Woodside on a 100% basis, without financial support from 25% joint venture partner BHP.

McDermott Australia Pty Ltd has been awarded a contract to undertake engineering studies for the floating production unit, which includes the option to progress to an engineering, procurement and construction contract for execute phase activities.

Subsea Integration Alliance, a consortium between OneSubsea Australia Pty Ltd and Subsea 7 Australia Contracting Pty Ltd, has been awarded a contract to undertake engineering studies for the subsea umbilical risers and flowlines, with the option to progress to an engineering, procurement, construction and installation contract for execute phase activities.

Saipem Australia Pty Ltd has been awarded a contract to provide export trunkline engineering support services with an option to execute line pipe coating and installation activities.

Intecsea Pty Ltd has been awarded a contract for export trunkline engineering.

Woodside CEO Peter Coleman said the award of these contracts support the project schedule and Woodside’s targeted final investment decision (FID) for the Scarborough Project next year.

Each contract includes an option to progress to execute phase activities, which is subject to, among other conditions, a positive FID being taken on the project by the Scarborough joint venture.

“We have made good progress since announcing last year that we had increased our stake in Scarborough. The award of these contracts brings us closer to unlocking the Scarborough resource,” Coleman said.

“We want to continue to maintain the momentum that has been generated during 2018 towards a targeted final investment decision in 2020.”

Woodside’s preferred concept for development of the 7.3 Tcf (2C 100%) Scarborough gas resource (Woodside 75%) is through new offshore facilities connected by an approximately 430 km export pipeline to the Burrup Peninsula with onshore processing at the expanded Pluto LNG facility.

Categories: Contracts Engineering Industry News Natural Gas Australia/NZ Offshore Energy

Related Stories

Indonesia Locks In LNG Supplies from Inpex' Abadi and Eni’s South Hub

Wood Secures Subsea Design Scope on QatarEnergy’s Bul Hanine Redevelopment

Oil Prices Rise as Iran Talks Stall and Inventories Shrink

BP Adds Three Exploration Blocks off Indonesia

Inpex Inks Abadi LNG Gas Supply Deal With Indonesian State Firms

Energean Cuts 2026 Output Forecast After Israel Shutdown

Wison Starts Topsides Fabrication for Türkiye’s Sakarya Deepwater FPU

Inpex Expands Australia Gas Portfolio with Browse Minority Stake Deal

Strike Threat Grows at Ichthys LNG after Workers Reject Deal

Borr Drilling Expects Higher Activity as Rigs Return to Work

Current News

Eni Inks Long-Term Indonesia LNG Supply Agreements

Indonesia Locks In LNG Supplies from Inpex' Abadi and Eni’s South Hub

Wood Secures Subsea Design Scope on QatarEnergy’s Bul Hanine Redevelopment

Oil Prices Rise as Iran Talks Stall and Inventories Shrink

Indonesia Puts 13 Oil And Gas Blocks on Bidding Round Offer

BP Adds Three Exploration Blocks off Indonesia

Indonesia Signs Eight Oil and Gas Contracts

Inpex Inks Abadi LNG Gas Supply Deal With Indonesian State Firms

Energean Cuts 2026 Output Forecast After Israel Shutdown

Wison Starts Topsides Fabrication for Türkiye’s Sakarya Deepwater FPU

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com