Nord Stream 2 is 75% Complete

August 28, 2019

Image: Nord Stream 2
Image: Nord Stream 2

The Nord Stream 2, export gas pipeline running from Russia to Europe across the Baltic Sea, is 75% complete, the project's operator, Nord Stream 2 AG, said in a statement.

A total of 1,855 kilometers of the Nord Stream 2 pipeline were built along the bottom of the Baltic Sea in the waters of Russia, Finland, Sweden and Germany. That's about 75 percent of the total length of the pipeline, the release said.

Both strings have already been completed in German territorial waters and Finnish waters. Pipelay is currently ongoing in Russian territorial waters. At the landfalls in Germany and Russia, construction works have reached an advanced stage.

All pipes needed for the twin pipeline system have been concrete weight coated. Logistics operations are nearing completion.

In Hanko, Finland and Karlshamn Sweden, the last pipes were loaded out to pipelay vessels during this summer. Storage and logistics are continuing in the Finnish and German hubs, Kotka and Mukran respectively.

Categories: Pipelines Europe Gas Pipe


Current News

Asia Pacific’s Decarbonization Bill to Hit $3.5 Trillion in 2040

Asia Pacific’s Decarbonization Bill to Hit $3.5 Trillion in 2040

China Expects Balanced Energy Supply/Demand

China Expects Balanced Energy Supply/Demand

India to Invite Foreign Investment in State-owned Oil Companies

India to Invite Foreign Investment in State-owned Oil Companies

Southeast Asia Bullish on OFS Market

Southeast Asia Bullish on OFS Market

BMT Delivers Real Time Monitoring for Helang FPSO

BMT Delivers Real Time Monitoring for Helang FPSO

Saipem Inks Deal with Daewoo for Onshore Projects

Saipem Inks Deal with Daewoo for Onshore Projects

Indonesia Inks 20-year PSC for Corridor Block

Indonesia Inks 20-year PSC for Corridor Block

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week