Seatrium Unit Launches Arbitration Against Petrobras over FPSO Contract

Tuesday, February 10, 2026

Seatrium, through its wholly owned subsidiary Jurong Shipyard, has started arbitration proceedings against Petrobras Netherlands in connection with a legacy contract for the conversion of the P-54 floating production, storage and offloading vessel (FPSO).

The dispute relates to a settlement agreement reached in 2008 following amendments to the original 2004 contract. Under the settlement, Petrobras Netherlands agreed to pay Jurong Shipyard a close-out amount of $152.3 million, of which $55.7 million was withheld pending a final decision by Brazil’s Federal Court of Accounts.

Seatrium said the Brazilian court issued its final decision in November 2023, removing the basis for withholding the payment, but the amount has not been released. Jurong Shipyard has therefore initiated arbitration seeking recovery of the withheld funds and asserting that Petrobras Netherlands is in breach of the settlement agreement.

According to Seatrium, Petrobras, the parent company of Petrobras Netherlands, has also issued a demand letter claiming $135.3 million in alleged overpayments under the P-54 contract and seeking a net payment of $79.6 million after deducting the withheld amount.

The arbitration, to be conducted in London under UNCITRAL rules and governed by English law, is intended to secure payment of the withheld funds and address claims related to the P-54 contract, Seatrium said.

The P-54 FPSO is deployed at Roncador field, the largest offshore discovery in Brazil in the 1990s and currently has a production potential of nearly 150,000 barrels of oil equivalent per day.

It is also the largest producing field outside the Brazilian pre-salt area, with approximately 10 billion barrels of oil equivalent originally in the reservoir. It is operated by Petrobras (75%), in partnership with Equinor (25%), and in addition to P-43, it has three other production units P-52, P-55, and P-62.

Categories: Industry News Activity FPSO Oil and Gas Arbitration

Related Stories

Indonesia’s Mako Gas Project on Track for First Gas in 2027

Saipem Poised for Middle East Repair Work After Iran War

Bureau Veritas Expands Offshore Services with New Asia Hub

Valeura Charters Shelf Drilling’s Jack-Up Rig for Gulf of Thailand Ops

US-Israel War on Iran Creates Biggest Energy Crisis in History

Oil Flows to Lag Even if Hormuz Strait Reopens

MidEast Energy Output Recovery to Take Two Years, IEA Says

Philippines Seeks US Extension to Buy Russian Oil

Hormuz Crisis Signals New Era of Risk for Gulf Energy

Fire at ONGC's Offshore Platform Injures 10, Operations Normalized

Current News

Vessel Sector Deep Dive: WTIVs

Indonesia’s Mako Gas Project on Track for First Gas in 2027

CNOOC’s First Quarter Profit Rises on Higher Oil Prices, Output

UAE Exit Weakens OPEC, Raises Risk of Price War

United Arab Emirates Exits OPEC and OPEC+

Technology as Enabler of Energy Security in Offshore Asia

Saipem Poised for Middle East Repair Work After Iran War

Middle East Conflict Jolts Offshore Drilling Market

Bureau Veritas Expands Offshore Services with New Asia Hub

Valeura Charters Shelf Drilling’s Jack-Up Rig for Gulf of Thailand Ops

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com