Vietsovpetro Brings BK-24 Oil Platform Online Two Months Early

Monday, October 13, 2025

Vietsovpetro, the Vietnamese-Russian joint venture, has started commercial oil production from its BK-24 wellhead platform at the Bach Ho (White Tiger) oil field, more than two months ahead of schedule.

On October 11, 2025, Vietsovpetro achieved the first commercial oil flow produced from the BK-24 platform after carrying out the flow initiation operations at well 24001 in Cuu Long Basin, offshore southern Vietnam in the South China Sea (East Sea).

The platform came onstream 65 days earlier than planned, setting a new benchmark for project execution.

Vietsovpetro said the early start is a clear demonstration of comprehensive capabilities and proactive implementation across the value chain, including geology and field design, drilling, and EPCI (engineering, procurement, construction and installation).

The company described the achievement as particularly significant, highlighting its strength in developing small and marginal fields cost-effectively.

BK-24 is the second field development project completed by Vietsovpetro in 2025, following the KNT-KTN project.

Additional crude production from BK-24 is expected to play a key role in helping Vietsovpetro meet and exceed its 2025 business and production targets, the company said, adding that it will also contribute to Vietnam’s state budget and help reinforce national energy security.

Categories: Drilling Industry News Activity Production Asia Oil and Gas

Related Stories

Thailand Cancels Offshore Energy Exploration Pact with Cambodia

Indonesia’s Mako Gas Project on Track for First Gas in 2027

CNOOC’s First Quarter Profit Rises on Higher Oil Prices, Output

Middle East Conflict Jolts Offshore Drilling Market

Bureau Veritas Expands Offshore Services with New Asia Hub

Oil Flows to Lag Even if Hormuz Strait Reopens

Eni Makes Major Gas Discovery Offshore Indonesia

Pertamina Unit to Operate Indonesia’s Lavender Block under 30-Year PSC

Borr Drilling Expects Higher Activity as Rigs Return to Work

Arabian Drilling Flags Temporary Offshore Rig Suspensions in Persian Gulf

Current News

Lloyd’s Register Approves Wison’s Internal Turret FPSO Concept

Gulf Marine Services Profit Plunges After Gulf Vessel Evacuations

Eni Advances Giant Indonesia Gas Discovery after ‘Exceptional’ Well Test

IEA: Middle East Conflict Reshaping Medium-Term Gas Outlook

ADNOC Drilling Finalizes MB Petroleum JV, Expands Regional Fleet

Brent Near $114 as Middle East Conflict Continues

Thailand Cancels Offshore Energy Exploration Pact with Cambodia

Vessel Sector Deep Dive: WTIVs

Indonesia’s Mako Gas Project on Track for First Gas in 2027

CNOOC’s First Quarter Profit Rises on Higher Oil Prices, Output

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com