MODEC Ramps Up Hammerhead FPSO Work After ExxonMobil's Go-Ahead

Tuesday, September 30, 2025

MODEC has been awarded the full engineering, procurement, construction, and installation (EPCI) scope to develop a floating production, storage and offloading (FPSO) vessel for the Hammerhead project in Guyana following a final investment decision (FID) by ExxonMobil.

In April 2025, MODEC received a Limited Notice to Proceed (LNTP) enabling it to commence FPSO design activities to support the earliest possible startup in 2029, subject to required government approvals.

Phase One of the contract, covering front-end engineering and design (FEED), has since been completed and MODEC is advancing Phase Two, EPCI, execution readiness in line with project governance.

The Hammerhead FPSO will have the initial annual average production of 150,000 barrels of oil per day (BOPD), along with associated gas and water. It will be moored at a water depth of approximately 1,025 meters using SOFEC’s Spread Mooring System.

The Hammerhead FPSO will be MODEC’s second for use in Guyana, following the Errea Wittu, which is currently being built for ExxonMobil Guyana’s Uaru project.

As with the Uaru Project, MODEC will provide ExxonMobil with operations and maintenance services for the FPSO for 10 years from first oil.

“We are honored to be entrusted with the full EPCI scope for Hammerhead. This award reflects MODEC’s integrated capabilities to design, build and operate—from concept and FEED through to safe execution and timely delivery of the project.

“Building on the strong progress we’ve made on the Uaru Project, this milestone further underscores the momentum of our collaboration. MODEC’s strategic relationship with ExxonMobil Guyana positions us to work with them and our stakeholders to create lasting value throughout the project lifecycle,” said Soichi Ide, Head of Floating Production Solutions Business Unit of MODEC.

To remind, ExxonMobil made a final investment decision for the Hammerhead development earlier in September 2025, after receiving the required regulatory approvals. 


Categories: Industry News Activity South America Oil and Gas FPSOs

Related Stories

Jadestone Secures Gas Sales Deal for Fields Offshore Vietnam

Oil Flows to Lag Even if Hormuz Strait Reopens

MidEast Energy Output Recovery to Take Two Years, IEA Says

Philippines Seeks US Extension to Buy Russian Oil

China Calls for De-Escalation as US Threatens Hormuz Blockade

UK Declines to Support US Hormuz Blockade, PM Starmer Says

Israel Orders Restart of Ops at Karish Offshore Gas Platform

Russia’s Yamal LNG Resumes Shipments to China After Months-Long Gap

Energy Crisis from War on Iran Deeper Than Widely Assumed

India Resumes Iranian Oil Imports After Seven-Year Hiatus

Current News

Jadestone Secures Gas Sales Deal for Fields Offshore Vietnam

Oil Flows to Lag Even if Hormuz Strait Reopens

Eni Makes Major Gas Discovery Offshore Indonesia

Strike Threat Grows at Ichthys LNG after Workers Reject Deal

Pertamina Unit to Operate Indonesia’s Lavender Block under 30-Year PSC

MidEast Energy Output Recovery to Take Two Years, IEA Says

Metropolitan CCS Cleared to Drill CO2 Storage Wells off Japan

Saipem Bags $400M in Offshore Contracts from Aramco in Saudi Arabia

Toyo, OneSubsea Form Subsea CCS Partnership

Japan to Launch $10B Fund to Help Asia Secure Oil

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com