BP Suspends Production at Azerbaijani Platform for Maintenance Works

Monday, April 29, 2024

BP, as the operator of the Azeri-Chirag-Deepwater Gunashli (ACG) field development in the Caspian Sea, has kicked off planned maintenance (turnaround - TAR) works on the Deepwater Gunashli platform.

In accordance with the plan, production from the Deepwater Gunashli platform was suspended on April 25 for 15 days to enable efficient maintenance, inspection and project work to be undertaken.

During the TAR, various projects including valves changeouts and nucleonic sources replacement, as well as required repair works will be undertaken.

This is a planned program, which started in 2023, and is part of normal operations, BP said. The shut-down is also included in the annual production forecast.

Production from the other ACG platforms, as well as the platforms on the Shah Deniz field, Sangachal terminal operations and export operations via Baku-Tbilisi-Ceyhan and the South Caucasus Pipeline (SCP and SCPX) continue as normal.



“This planned event is a necessary part of the long-term reliability, integrity and production performance, driven by repair and facility modification work that can only be performed during a plant outage,” BP said.

Deepwater Gunashli complex is the third phase of development of the ACG field in the Azerbaijan sector of the Caspian Sea. It is located on the east side of the Gunashli field at 175 meters of water depth. The platform has been in operation since April 2008 producing oil from the ACG field.

The complex comprises of two bridge-linked platforms - a drilling and production platform bridge linked to a water injection and gas compression platform.

Production export off the complex is via two 30-inch oil pipeline tie-ins and a single 28 inch gas pipeline tie-in into pre-installed pipeline junctions located on the Azeri field subsea export pipelines to the onshore Sangachal Terminal.

Production from the Deepwater Gunashli is boosted by remarkable Caspian first – subsea water injection intended to ramp-up oil production by injecting seawater into DWG reservoir to increase its pressure

Total Deepwater Gunashli production for the full year was 67.000 barrels per day.

Categories: Industry News Activity Europe Production Asia Caspian Sea Oil and Gas

Related Stories

Op-Ed: Kazakhstan’s National O&G Firm Positioning Itself as Global Energy Player

CNOOC Sees 11% Profit Growth in 2024 Driven by Record Oil Production

All Gas from Conrad’s Mako Field to be Sold to Indonesia’s PLN

Shell Launches Next Phase of Malaysia's Deepwater Project with First Oil Production

Valeura Wraps Up Infill Drilling Campaign in Gulf of Thailand

Tokyo Gas Enters LNG Market in Philippines

ONGC and BP Sign Deal to Boost Production at India's Largest Offshore Oil Field

ADNOC Secures LNG Supply Deal with India's BPCL

Japan's Mitsui Eyes Alaska LNG Project

China's CNOOC Aims for Record Oil and Gas Production in 2025

Current News

Mitigate SCC & HE to Keep Offshore Metal Structures Ship Shape

India Stretches Bids Deadline for 13 Offshore Deep-Sea Mineral Blocks

Indonesia Awards Oil and Gas Blocks to Boost Reserves

Sapura Energy Nets $22.6M in Offshore Support Vessel Contracts

CNOOC Puts Into Production New Oil Field in South China Sea

Sunda Energy Starts Environmental Consultation for Chuditch-2 Well Drilling Plans

Pakistan’s OGDC to Start Production at ADNOC’s Offshore Block by 2027

Petrovietnam, Petronas Extend PSC for Offshore Block

Sapura Energy Scoops Close to $9M for O&M Work off Malaysia

Hanwha Ocean Marks Entry into Deepwater Drilling Market with First Drillship

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com