BP, as the operator of the Azeri-Chirag-Deepwater Gunashli (ACG) field development in the Caspian Sea, has kicked off planned maintenance (turnaround - TAR) works on the Deepwater Gunashli platform.

In accordance with the plan, production from the Deepwater Gunashli platform was suspended on April 25 for 15 days to enable efficient maintenance, inspection and project work to be undertaken.

During the TAR, various projects including valves changeouts and nucleonic sources replacement, as well as required repair works will be undertaken.

This is a planned program, which started in 2023, and is part of normal operations, BP said. The shut-down is also included in the annual production forecast.

Production from the other ACG platforms, as well as the platforms on the Shah Deniz field, Sangachal terminal operations and export operations via Baku-Tbilisi-Ceyhan and the South Caucasus Pipeline (SCP and SCPX) continue as normal.



“This planned event is a necessary part of the long-term reliability, integrity and production performance, driven by repair and facility modification work that can only be performed during a plant outage,” BP said.

Deepwater Gunashli complex is the third phase of development of the ACG field in the Azerbaijan sector of the Caspian Sea. It is located on the east side of the Gunashli field at 175 meters of water depth. The platform has been in operation since April 2008 producing oil from the ACG field.

The complex comprises of two bridge-linked platforms - a drilling and production platform bridge linked to a water injection and gas compression platform.

Production export off the complex is via two 30-inch oil pipeline tie-ins and a single 28 inch gas pipeline tie-in into pre-installed pipeline junctions located on the Azeri field subsea export pipelines to the onshore Sangachal Terminal.

Production from the Deepwater Gunashli is boosted by remarkable Caspian first – subsea water injection intended to ramp-up oil production by injecting seawater into DWG reservoir to increase its pressure

Total Deepwater Gunashli production for the full year was 67.000 barrels per day.

Categories: Industry News Activity Europe Production Asia Caspian Sea Oil and Gas

Related Stories

Venture Global, Tokyo Gas Ink 20-Year LNG Supply Deal

Malaysia Issues First Offshore CCS Permit to Petronas Subsidiary

Russia's Lukoil Takes Up Gunvor’s Offer for Foreign Assets

US Pressure on India Could Propel Russia's Shadow Oil Exports

ABL Secures Rig Moving Assignment with India's ONGC

Russia Targets 2028 for Sakhalin-3 Gas Project Start Up

Saipem Bags $1.5B Contract for Türkiye Largest Offshore Gas Field

TotalEnergies Inks 10-Year LNG Supply Deal with South Korea’s KOGAS

CNOOC Brings Online Another Oil and Gas Project in South China Sea

CNOOC Brings New Offshore Gas Field On Stream

Current News

CNOOC Puts New South China Sea Development Into Production Mode

ADES Nets $63M Contract for Compact Driller Jack-Up off Brunei

Mubadala Energy, PLN Energy Primer Team Up for Andaman Sea Gas Supply

BP Hires Seatrium to Deliver Tiber FPU in Gulf of America

Venture Global, Tokyo Gas Ink 20-Year LNG Supply Deal

Greater Sunrise Moves to Next Phase with Timor-Leste, Woodside Deal

Russia Seeks to Boost Oil Exports to China as Sanctions Tighten

Blackford Dolphin Semi-Sub to Keep Drilling Offshore India

Aramco Expands US Partnerships with $30B in New Deals

Pakistan Greenlights TPOC-Led Offshore Exploration in Block-C

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com