BP Suspends Production at Azerbaijani Platform for Maintenance Works

Monday, April 29, 2024

BP, as the operator of the Azeri-Chirag-Deepwater Gunashli (ACG) field development in the Caspian Sea, has kicked off planned maintenance (turnaround - TAR) works on the Deepwater Gunashli platform.

In accordance with the plan, production from the Deepwater Gunashli platform was suspended on April 25 for 15 days to enable efficient maintenance, inspection and project work to be undertaken.

During the TAR, various projects including valves changeouts and nucleonic sources replacement, as well as required repair works will be undertaken.

This is a planned program, which started in 2023, and is part of normal operations, BP said. The shut-down is also included in the annual production forecast.

Production from the other ACG platforms, as well as the platforms on the Shah Deniz field, Sangachal terminal operations and export operations via Baku-Tbilisi-Ceyhan and the South Caucasus Pipeline (SCP and SCPX) continue as normal.



“This planned event is a necessary part of the long-term reliability, integrity and production performance, driven by repair and facility modification work that can only be performed during a plant outage,” BP said.

Deepwater Gunashli complex is the third phase of development of the ACG field in the Azerbaijan sector of the Caspian Sea. It is located on the east side of the Gunashli field at 175 meters of water depth. The platform has been in operation since April 2008 producing oil from the ACG field.

The complex comprises of two bridge-linked platforms - a drilling and production platform bridge linked to a water injection and gas compression platform.

Production export off the complex is via two 30-inch oil pipeline tie-ins and a single 28 inch gas pipeline tie-in into pre-installed pipeline junctions located on the Azeri field subsea export pipelines to the onshore Sangachal Terminal.

Production from the Deepwater Gunashli is boosted by remarkable Caspian first – subsea water injection intended to ramp-up oil production by injecting seawater into DWG reservoir to increase its pressure

Total Deepwater Gunashli production for the full year was 67.000 barrels per day.

Categories: Industry News Activity Europe Production Asia Caspian Sea Oil and Gas

Related Stories

MODEC, Eld Energy Advance Fuel Cell Power for FPSOs

TPAO Eyes Karabakh Offshore Expansion with SOCAR

Asia's Oil Industry Braces for Prolonged Hormuz Disruption

Saipem Bags Commissioning Contract for Türkiye-Bound FPU

Oil Jumps as Houthi Strikes Disrupt Saudi Energy Operations

PTTEP, Petronas Ink 35-Year Malaysia-Thailand Gas Deals

Energean Lifts Karish Fields FPSO Oil Processing Capacity

Jadestone Energy Lifts Malaysia Production with Second Online Well

EnQuest Clears Key Hurdle for $833M Malaysia Offshore Deal

Oil Surges 3% on Renewed US-Iran Strikes

Current News

MODEC, Eld Energy Advance Fuel Cell Power for FPSOs

Santos Expands LNG Portfolio with Asia, Canada Deals

Petronas, PTTEP Get Approvals for New Gas Block Sharing Contract

TPAO Eyes Karabakh Offshore Expansion with SOCAR

XRG, ADNOC and SEFE Deepen Gas Ties in Europe

Saudi Oil Lifeline Shut After Attack as Red Sea Threat Grows

Greater Sunrise Gas Production Pushed Back to 2034

SED Energy Holdings and Ventura Offshore Set to Combine Ops

Asia's Oil Industry Braces for Prolonged Hormuz Disruption

Petronas Awards Estuary Cluster PSC to Harvester Energy

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com