Barossa Project: BW Offshore's Massive FPSO Hull Sets Sail for Singapore

Thursday, November 9, 2023

FPSO leasing company BW Offshore said Thursday that the hull of BW Opal, one of the largest FPSO hulls ever built and destined for Santos' Barossa gas project in Australia, had set sail from a yard in South Korea and was en route to Singapore for topside integration.

"On October 28, 2023, at 11:30 local time, the newbuild hull for the BW Opal FPSO, which is based on BW Offshore’s RapidFramework concept, started tow from the SK Oceanplant (SKOP) yard in South Korea, to the integration shipyard in Singapore, where it is expected to arrive later this month," BW Offshore said.

The hull has an overall length of 358 meters and a width of 64 meters. 

The hull has been built over the last 22 months, starting with the first steel cuttin on November 24, 2021. 

The hull is built in six giga blocks, which have been joined in the floating dock. The hull was launched in June 2023, and subsequently, living quarters, engine casing, and topsides process pipe racks have been installed. 

Credit: BW Offshore

In addition to steel, 670 kilometers of cable has been pulled and around 30,000 pipe spools have been installed to complete construction, mechanical completion and pre-commissioning activities. 

Upon arrival in Seatrium yard in Singapore, fully completed process modules, E-house and Turret modules will be lifted onto the hull to start integration activities. After completion of integration and commissioning, the fully commissioned BW Opal FPSO will start its voyage to Australia to start production in the first half of 2025.

The Final Investment Decision (FID) for the FPSO for the Barossa project was confirmed by Santos and its partners on March 30, 2021, with a services contract including Operation & Maintenance (O&M) with a firm period of 15 years, and 10 years of options. 

The Barossa gas field is located 300 kilometers offshore Darwin in northern Australia and will be developed via the BW Opal FPSO with six subsea production wells, in-field facilities, and a gas export pipeline tied into the Bayu-Undan to Darwin pipeline system that supplies gas to Darwin LNG. BW Offshore is responsible for engineering, procurement, construction, installation, and operation of the FPSO.


Categories: Engineering Industry News Activity FPSO Floating Production Offshore

Related Stories

Big Oil Pockets Near-Record Profits but Spending Restraint Signals Long-Term Doubts

Seatrium Inks $390M Deal to Complete Four Offshore Rigs for Keppel’s Rigco

PTTEP, Eni Launch Joint Venture for ADNOC-Operated Ghasha Offshore Project

Jack-Up Rig Arrives in Indonesia for Conrad Asia Energy's MOPU Conversion

Iran Weighs US Response as Hormuz Reopening Talks Stall

Valeura Starts Wassana Platform Installation Offshore Thailand

Oil Stabilizes as IEA Moves to Speed Up Emergency Stock Releases

Oil Climbs on US Storm Threat, Saudi Attack Risks

Oil Industry Braces for Years of Market Disruption

Larsen & Toubro Adds Major ONGC Offshore Project to Orderbook

Current News

Tender-Assist Rigs: Southeast Asia’s Quiet Workhorses Head for Full Utilization

Aker Solutions Lands Major Role in Qatar’s Offshore Oil Field Revamp

TotalEnergies Inks 15-Year LNG Supply Deal with China's Jiangsu Guoxin

Baker Hughes Sets Up Global Network to Bolster Mature Oil and Gas Fields Production

Valaris Secures $600M in New Contracts as Backlog Rises to $4.8B

Production Restart at Australian Offshore Fields Boosts Jadestone's Oil Output

Aramco Targets Hormuz Bypass with East-West Pipeline Expansion

ADES Lands New Offshore Drilling Rig Deals in Angola and Indonesia

Shell to Exit Australia's North West Shelf Project in $1.45B Deal with XRG

Aramco Third Quarter Profit Up 35% Despite War Disruptions

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com