Barossa Project: BW Offshore's Massive FPSO Hull Sets Sail for Singapore

Thursday, November 9, 2023

FPSO leasing company BW Offshore said Thursday that the hull of BW Opal, one of the largest FPSO hulls ever built and destined for Santos' Barossa gas project in Australia, had set sail from a yard in South Korea and was en route to Singapore for topside integration.

"On October 28, 2023, at 11:30 local time, the newbuild hull for the BW Opal FPSO, which is based on BW Offshore’s RapidFramework concept, started tow from the SK Oceanplant (SKOP) yard in South Korea, to the integration shipyard in Singapore, where it is expected to arrive later this month," BW Offshore said.

The hull has an overall length of 358 meters and a width of 64 meters. 

The hull has been built over the last 22 months, starting with the first steel cuttin on November 24, 2021. 

The hull is built in six giga blocks, which have been joined in the floating dock. The hull was launched in June 2023, and subsequently, living quarters, engine casing, and topsides process pipe racks have been installed. 

Credit: BW Offshore

In addition to steel, 670 kilometers of cable has been pulled and around 30,000 pipe spools have been installed to complete construction, mechanical completion and pre-commissioning activities. 

Upon arrival in Seatrium yard in Singapore, fully completed process modules, E-house and Turret modules will be lifted onto the hull to start integration activities. After completion of integration and commissioning, the fully commissioned BW Opal FPSO will start its voyage to Australia to start production in the first half of 2025.

The Final Investment Decision (FID) for the FPSO for the Barossa project was confirmed by Santos and its partners on March 30, 2021, with a services contract including Operation & Maintenance (O&M) with a firm period of 15 years, and 10 years of options. 

The Barossa gas field is located 300 kilometers offshore Darwin in northern Australia and will be developed via the BW Opal FPSO with six subsea production wells, in-field facilities, and a gas export pipeline tied into the Bayu-Undan to Darwin pipeline system that supplies gas to Darwin LNG. BW Offshore is responsible for engineering, procurement, construction, installation, and operation of the FPSO.


Categories: Engineering Industry News Activity FPSO Floating Production Offshore

Related Stories

Pharos Energy Kicks Off Drilling Campaign Offshore Vietnam

US Pressure on India Could Propel Russia's Shadow Oil Exports

Energy Drilling’s EDrill-2 Rig Starts Ops for PTTEP in Gulf of Thailand

Eni-Petronas Gas Joint Venture Up for Launch in 2026

POSH Set to Tow Nguya FLNG from China to Eni’s Congo Field

Marco Polo Picks Salt Ship Design for Next-Gen Offshore Energy CSOV

CNOOC Brings Online Another Oil and Gas Project in South China Sea

Saipem Wins FEED Contract For Abadi LNG Project FPSO Module In Indonesia

Inpex Picks FEED Contractors for Abadi LNG Onshore Plant

China Starts Production at Major Oil Field in Bohai Sea

Current News

PTTEP Orders OneSubsea Systems for Two Deepwater Projects off Malaysia

Russia's Lukoil Takes Up Gunvor’s Offer for Foreign Assets

How Hot Is Your Cable? Understanding Subsea Cable Thermal Performance

Sponsored: UAE Breaks Ground on GW-Scale Renewable Energy Hybrid

Pertamina Joins Petronas in Ultra-Deepwater Asset off Indonesia

Malaysia’s Petronas and Oman’s OQEP Strengthen Oil and Gas Ties

Southeast Asia’s 2GW Cross-Border Offshore Wind Scheme Targets 2034 Buildout

Pharos Energy Kicks Off Drilling Campaign Offshore Vietnam

Viridien to Shed More Light on Malaysia’s Offshore Oil and Gas Potential

US Pressure on India Could Propel Russia's Shadow Oil Exports

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com