Barossa Project: BW Offshore's Massive FPSO Hull Sets Sail for Singapore

Thursday, November 9, 2023

FPSO leasing company BW Offshore said Thursday that the hull of BW Opal, one of the largest FPSO hulls ever built and destined for Santos' Barossa gas project in Australia, had set sail from a yard in South Korea and was en route to Singapore for topside integration.

"On October 28, 2023, at 11:30 local time, the newbuild hull for the BW Opal FPSO, which is based on BW Offshore’s RapidFramework concept, started tow from the SK Oceanplant (SKOP) yard in South Korea, to the integration shipyard in Singapore, where it is expected to arrive later this month," BW Offshore said.

The hull has an overall length of 358 meters and a width of 64 meters. 

The hull has been built over the last 22 months, starting with the first steel cuttin on November 24, 2021. 

The hull is built in six giga blocks, which have been joined in the floating dock. The hull was launched in June 2023, and subsequently, living quarters, engine casing, and topsides process pipe racks have been installed. 

Credit: BW Offshore

In addition to steel, 670 kilometers of cable has been pulled and around 30,000 pipe spools have been installed to complete construction, mechanical completion and pre-commissioning activities. 

Upon arrival in Seatrium yard in Singapore, fully completed process modules, E-house and Turret modules will be lifted onto the hull to start integration activities. After completion of integration and commissioning, the fully commissioned BW Opal FPSO will start its voyage to Australia to start production in the first half of 2025.

The Final Investment Decision (FID) for the FPSO for the Barossa project was confirmed by Santos and its partners on March 30, 2021, with a services contract including Operation & Maintenance (O&M) with a firm period of 15 years, and 10 years of options. 

The Barossa gas field is located 300 kilometers offshore Darwin in northern Australia and will be developed via the BW Opal FPSO with six subsea production wells, in-field facilities, and a gas export pipeline tied into the Bayu-Undan to Darwin pipeline system that supplies gas to Darwin LNG. BW Offshore is responsible for engineering, procurement, construction, installation, and operation of the FPSO.


Categories: Offshore Engineering Industry News Activity FPSO Floating Production

Related Stories

Yinson Holds Naming Ceremony for Brazil-Bound ‘Greener’ FPSO

Seatrium Scoops $259M Worth of Repairs and Upgrades Work

Dyna-Mac Secures $664M Backlog with New Contracts

Saipem Loads Out Three Topsides for QatarEnergy LNG’s North Field Gas Project

MMHE Delivers Topside for Jerun Gas Field Platform Offshore Malaysia

ABS Awards AIP for OceanSTAR’s FSO Design

Borr Drilling Secures $82M for Three Jack-up Rigs

QatarEnergy Signs 15-year LNG Supply Deal with Excelerate Energy

Jadestone Outlines Gas Sale Terms with PV Gas for Fields Offshore Vietnam

Aibel-Built Modules for Bacalhau FPSO Set Sail for Singapore

Current News

SOVs – Analyzing Current, Future Demand Drivers

Decarbonization Offshore O&G: Navigating the Path Forward

Subsea Vessel Market is Full Steam Ahead

China's Imports of Russian Oil Near Record High

TotalEnergies Inks $530M Deal to Acquire Malaysia’s SapuraOMV

Energy Storage on O&G Platforms - A Safety Boost, too?

Malampaya Gas Field Exceeds Export Capacity Amid Grid Demands in Philippines

Timor-Leste: Chuditch-2 Well to be Drilled at New Location Following Site Surveys

Akastor’s Subsidiary Wins $101M Case Against Seatrium's Jurong Shipyard

ONGC Hires Consortium to Deliver FEED Work for Bay of Bengal Oil Field

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com