Barossa Project: BW Offshore's Massive FPSO Hull Sets Sail for Singapore

Thursday, November 9, 2023

FPSO leasing company BW Offshore said Thursday that the hull of BW Opal, one of the largest FPSO hulls ever built and destined for Santos' Barossa gas project in Australia, had set sail from a yard in South Korea and was en route to Singapore for topside integration.

"On October 28, 2023, at 11:30 local time, the newbuild hull for the BW Opal FPSO, which is based on BW Offshore’s RapidFramework concept, started tow from the SK Oceanplant (SKOP) yard in South Korea, to the integration shipyard in Singapore, where it is expected to arrive later this month," BW Offshore said.

The hull has an overall length of 358 meters and a width of 64 meters. 

The hull has been built over the last 22 months, starting with the first steel cuttin on November 24, 2021. 

The hull is built in six giga blocks, which have been joined in the floating dock. The hull was launched in June 2023, and subsequently, living quarters, engine casing, and topsides process pipe racks have been installed. 

Credit: BW Offshore

In addition to steel, 670 kilometers of cable has been pulled and around 30,000 pipe spools have been installed to complete construction, mechanical completion and pre-commissioning activities. 

Upon arrival in Seatrium yard in Singapore, fully completed process modules, E-house and Turret modules will be lifted onto the hull to start integration activities. After completion of integration and commissioning, the fully commissioned BW Opal FPSO will start its voyage to Australia to start production in the first half of 2025.

The Final Investment Decision (FID) for the FPSO for the Barossa project was confirmed by Santos and its partners on March 30, 2021, with a services contract including Operation & Maintenance (O&M) with a firm period of 15 years, and 10 years of options. 

The Barossa gas field is located 300 kilometers offshore Darwin in northern Australia and will be developed via the BW Opal FPSO with six subsea production wells, in-field facilities, and a gas export pipeline tied into the Bayu-Undan to Darwin pipeline system that supplies gas to Darwin LNG. BW Offshore is responsible for engineering, procurement, construction, installation, and operation of the FPSO.


Categories: Engineering Industry News Activity FPSO Floating Production Offshore

Related Stories

Asian Buyers Rush for Russian Oil Amid Supply Disruption

IEA Weighs Further Oil Stock Releases as War on Iran Continues

Eni Advances Angola Gas Project, Secures $9B Credit Facility

Oil Drops 7% After Trump Predicts War Could End Soon

Aramco Warns of Severe Oil Market Fallout from Hormuz Blockade

Oil Prices Go Up 3% as Iran Crisis Disrupts Supply

China Looks Best Placed to Weather Iran Energy Shock

MISC, PTSC Extend Ruby II FPSO Operations Offshore Vietnam

MODEC, Eld Energy Partnership Targets Low-Carbon FPSO Power

Thailand's Gulf Energy Eyes Long-Term LNG Supply

Current News

Eni Exits Consortium for Oil and Gas Exploration Offshore Israel

Big Oil to Reap Billions from Energy Price Surge

UAE Stands Ready to Join Force to Reopen Strait of Hormuz

Asian Buyers Rush for Russian Oil Amid Supply Disruption

Mubadala Energy Secures Southwest Andaman Exploration Block off Indonesia

Strohm to Supply Insulated TCP Jumpers for Malaysia’s Offshore Project

Arabian Drilling Flags Temporary Offshore Rig Suspensions in Persian Gulf

Iran War Sends LNG Prices Soaring, Curbing Asia Demand

Rising Costs of War: Gulf Energy Infrastructure Stares Down $25B Repair Bill

ADES Expects Up to 44% Earnings Rise Despite Regional Tensions Impacting Rigs

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com