BW Offshore, New Zealand Gov't Reach Umuroa FPSO Settlement

Bartolomej Tomic
Friday, November 20, 2020

FPSO operator BW Offshore has reached a settlement with the New Zealand government over the FPSO Umuroa, which has been stuck at the Tui field, around 50 kilometers off the coast of Taranaki, for months.

BW Offshore has been unable to remove its FPSO from the Tui field following the contract termination, client liquidation, and the country's court and environment regulator intervention.

Client Tamarind Taranaki in October 2019 said it wouldn't extend the FPSO contract after December 31, 2019, and went into insolvency in December 2019, without any funding secured for decommissioning and abandonment liabilities. 

BW Offshore then said it would disconnect and demobilize the FPSO, expecting - at the time - to disconnect from the field and sail away to Singapore by the end of March.

Before removing the vessel, BW Offshore needed to disconnect it from Tamarind's equipment on the seafloor, and the country's environment protection regulators then asked for all of this subsea equipment removed as well, something which is, per BW, the responsibility of Tamarind, which is in liquidation, and thus unable to remove the subsea equipment. 

The conundrum has kept the FPSO in place for months, with BW Offshore's subsidiary BW Umuroa incurring the costs for maintaining the FPSO on location and in compliance with regulatory requirements. This has included full remuneration of the local crew and payments to suppliers.

 After months of waiting for a solution, BW last month said it would liquidate the subsidiary operating the FPSO to stop the cash burn, and hand over the asset to liquidators. 

Announcing the liquidation decision, BW Offshore said last month it had incurred more than $21 million in 2020 alone to keep the FPSO on-site and in compliance with regulatory requirements during the period, including demobilization costs for the earlier attempt to disconnect the vessel. 

Settlement

However, almost a month later, BW Offshore said it had on November 18, signed an agreement with the New Zealand government, through the Ministry of Business, Innovation, and Employment (MBIE), which will cover costs for continued safe operations of the FPSO Umuroa until such time when the unit is disconnected from the Tui oil field.

"Subject to prevailing Covid-19 restrictions, the disconnection is expected to be completed before the second half of 2021. As a result, the company has ceased the previously announced voluntary liquidation of BW Umuroa Pte. Ltd, a subsidiary of BW Offshore and the owner of the FPSO Umuroa," BW Offshore said.

In a separate statement, on Friday, MBIE said that the agreement with BW Offshore would allow the first phase of the decommissioning of the Tui Oil Field to start, which will see the FPSO Umuroa disconnect from the oil field and depart.

“Under the agreement, MBIE will reimburse BWU for actual costs associated with the demobilization. The work is expected to be completed during summer 2020/2021,  Chris Bunny, Deputy Chief Executive, Building, Resources and Markets said.

MBIE is responsible for the decommissioning of the Tui Oil Field after the liquidation and receivership of Tamarind Taranaki Ltd. 

A dedicated Tui Project team, within MBIE’s Energy and Resources Markets branch, is planning and preparing for the subsequent phases of full decommissioning of the Tui Oil Field.

The FPSO Umuroa, converted to an FPSO from a 1981-built tanker, has an oil processing capacity of 50,000 b/d, and a gas handling capacity of 25 mmcf/d. It can store 775,000 barrels of oil.

Categories: Offshore Industry News Activity FPSO Floating Production Australia/NZ Regulations

Related Stories

Inpex Picks FEED Contractors for Abadi LNG Onshore Plant

Inpex Kicks Off FEED Work for Abadi LNG Scheme Offshore Indonesia

CNOOC Brings New Offshore Gas Field On Stream

Yinson, PTSC Get $600M Contract for Vietnam-Bound FSO

Woodside Finds South Korean Partners to Advance LNG Value Chain

One Shelf Drilling Rig Up for New Job in India, Other for Disposal

UK Firm Secures Exploration Extension for Two Blocks off Vietnam

ABL Lands Work on BP’s Indonesian Gas and CCUS Project

MODEC, Carbon Clean to Advance FPSO-Mounted Carbon Capture Tech

BP Expands Oil and Gas Scope in Azerbaijan with New Projects and Exploration Rights

Current News

Shipbuilder Delivers Fast Crew Boat Pair to Aesen

Norwegian Oil Investment Will Peak in '25

Saipem Marks First Steel Cut for Tangguh UCC Project at Karimun Yard

Saipem Wins FEED Contract For Abadi LNG Project FPSO Module In Indonesia

Cheniere, JERA Ink Long-Term LNG Sale and Purchase Agreement

Shelf Drilling Lands New Jack-Up Contract in Vietnam, Extends Egypt Deal

Seatrium Engages Axess Group to Clear FPSOs for Brazil Deployment

Inpex Picks FEED Contractors for Abadi LNG Onshore Plant

Inpex Kicks Off FEED Work for Abadi LNG Scheme Offshore Indonesia

ADNOC Signs Long-Term LNG Deal with Hindustan Petroleum Corporation

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com