Construction of Cambodia's Maiden Offshore Oil Platform Complete

OE Staff
Wednesday, August 26, 2020

Construction of KrisEnergy's minimum facilities wellhead platform for the Apsara oil development offshore Cambodia has been completed and the platform has sailed away to its offshore location.

KrisEnergy said the topsides and the jacket of the "mini-platform" were being transported to Cambodian waters in the Block A in the Gulf of Thailand for installation. 

Fabrication of the Mini-Platform for Cambodia’s maiden oil field development began in early December 2019 at NOV’s PT Profab1 facility on Batam Island, Indonesia. Loadout and sail away of the structures were completed on Tuesday, August 25, 2020.

Kelvin Tang, KrisEnergy’s Chief Executive Officer and President of KrisEnergy’s Cambodian operations, said: "From first steel cutting to sail away has been nine months and this landmark is made all the more remarkable given the difficulties and restrictions our project team and our NOV Profab colleagues have faced since early 2020 as a result of the coronavirus pandemic."

"Thanks to the enormous efforts of all parties involved, including suppliers and contractors who have overcome logistical hurdles to keep deliveries of equipment and materials on track to the Batam facility from across the globe, we continue to advance towards our target of first Apsara oil before the end of the year.” 

Kim Lamb, NOV Profab’s Managing Director said: “It was great to play an integral part of such a groundbreaking project for Cambodia. Both the NOV and the KrisEnergy project teams worked closely together, adopting a fully integrated team approach to deliver a quality platform which is a true testimony of the dedication of all involved. We look forward to working with KrisEnergy again in the future.” 

The Apsara field in Cambodia Block A lies over the Khmer Basin, an unproduced geological basin in Cambodian maritime waters of the Gulf of Thailand. 

Due to the unproven production performance of the basin, KrisEnergy has opted for a phased development to mitigate risk and provide time for the collection and analysis of critical data to be applied in future phases. 

The Mini Phase 1A development comprises the Mini-Platform and five initial development wells connected to the Ingenium II production barge for oil, gas, and water processing. 

The company recently said that the Ingenium II production barge was being upgraded and refurbished, and nearing mechanical completion. 

Installation of heating, ventilation, and air conditioning system was completed in July 2020 and the power generation system is running, KrisEnergy said earlier this month.

"The vessel will shortly go into one month of commissioning required for safety systems, fire and gas systems, process control systems, electrical power distribution systems, as well as accommodation and mooring systems," Kris Energy said.

The Mini Phase 1A Apsara development is expected to reach a peak rate of 7,500 barrels of oil per day.


Categories: Energy Activity Production Asia Shallow Water

Related Stories

Yinson Production Cuts First Steel for Vietnam-Bound FSO

Fugro Nets Mubadala Energy’s Deepwater Gas Job in Asia

Petronas Enlists MISC for FPU Job at Gas Field Offshore Brunei

CNOOC Puts New South China Sea Development Into Production Mode

MODEC Forms Dedicated Mooring Solutions Unit

Major Oil and Gas Projects Drive Strong OSV Demand in the Middle East

PTTEP Orders OneSubsea Systems for Two Deepwater Projects off Malaysia

Timor Gap Boosts Stake in Finder Energy’s Timor-Leste Oil Fields

SBM Offshore Starts Construction of FSO for Trion Oil Field off Mexico

DOF Secures Moorings Hook-Up Job in Asia Pacific

Current News

Yinson Production Cuts First Steel for Vietnam-Bound FSO

CNOOC Makes Major Oil Discovery in Bohai Sea

DOF Bags Two Deals in Asia-Pacific Region

CNOOC Launches New Offshore Oil Development in Southern China

Saipem Nets Multibillion-Dollar Job at World's Largest Offshore Gas Field

Indonesia Tenders Eight Oil and Gas Blocks as Output Declines

Fugro Nets Mubadala Energy’s Deepwater Gas Job in Asia

EnQuest Set to Top 2025 Production Forecast on Southeast Asia Gains

Velesto Agrees $63M Jack-Up Drilling Rig Sale with Indonesian Firm

TotalEnergies Sells Stake in Malaysia’s Block to Thailand’s PTTEP

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com