Pacific Drilling Must Pay $320M for Rig Order Cancellation

OE Staff
Thursday, January 16, 2020

A London arbitration tribunal has ordered offshore drilling company Pacific Drilling to pay $320 million to Samsung Heavy Industries for a 2015 drillship order cancellation.

Pacific Drilling had ordered the Pacific Zonda ultra-deepwater drillship from Samsung in 2013, with the expected delivery in early 2015.
The company then in July 2015 decided to delay the rig delivery for the fourth quarter for 2015, only for it to abolish the order in October 2015, citing the failure of Samsung Heavy Industries "to timely deliver a vessel that substantially meets the criteria required for completion of the vessel in accordance with the construction contract and its specifications."

The move then led the shipyard to start an arbitration proceeding, from which it on Wednesday emerged as a winner.

Pacific Drilling confirmed Wednesday that arbitration proceedings between its subsidiaries, Pacific Drilling VIII Limited and Pacific Drilling Services,  and Samsung Heavy Industries related to the contract for the construction and sale of the Pacific Zonda concluded with Samsung winning the case.

"An arbitration tribunal in London, England awarded SHI approximately $320 million with respect to its claims against PDVIII and PDSI. The award does not include approximately $100 million in interest and costs sought by SHI, on which the Tribunal reserved making a decision to a later date," Pacific Drilling said.

Surprised and disappointed

Pacific Drilling CEO Bernie Wolford commented, “The company is surprised and disappointed by the Tribunal’s decision. However, this outcome will not impact our commitment and ability to continue to deliver to our customers the highest level of deepwater drilling services in our industry.”

The offshore drilling company said that PDVIII and PDSI (the “Zonda Debtors”) which have approximately $4.5 million in cash and no other material assets will be liquidated once the Tribunal’s award becomes final and unappealable.

"The Company does not expect the Tribunal’s decision to have any material adverse effect on its operations or to cause any default under any of its material contracts including under the indentures for its outstanding notes. As a result of the Tribunal’s decision, the Company expects to recognize a loss of approximately $225 million during the fourth quarter of 2019, primarily related to the elimination of the Zonda receivable on the balance sheet," Pacific Drilling said.

"PDVIII and PDSI are currently considering whether to seek permission to appeal and are exploring all available legal remedies. Under the rules governing the arbitration proceedings, PDVIII and PDSI have no automatic right to appeal and the grounds on which the High Court in London may grant permission to appeal are limited. PDVIII and PDSI must seek permission to appeal no later than 28 days from the date of the award, or by February 12, 2020," the drilling company said.

The Pacific Zonda is an upgraded Dual Load Path Samsung 12000 design dynamically-positioned, Dual Gradient capable, drillship operating in moderate environments and water depths up to 3,657 m (12,000 ft) using 183/4n BOP and 21″ OD marine drilling riser. The vessel can accommodate 200 persons. 

According to Marine Traffic, the rig is still located at the Samsung Heavy Industries yard in Geoje, South Korea.



Categories: Vessels Deepwater Europe Asia Rigs

Related Stories

ONGC Nears Venezuela Operatorship Deals, Regains Russia’s Sakhalin-1 Stake

Keppel Launches $2.9B Program to Monetize Legacy Offshore Drilling Rigs

QatarEnergy Prolongs LNG Force Majeure, Charters Out Tankers

ABL Gets Papua New Guinea FSO Job

Sunda Energy Applies for Exploration Permit Offshore New Zealand

Unity Enters Asia-Pacific Market with Malaysia P&A Work

James Fisher, Aquaterra Launch Global Decommissioning Partnership

Arabian Drilling Set to Resume Ops with Three Offshore Rigs

Hormuz Traffic Falls to Five-Week Low as Tensions Escalate

Yinson Production Names FSO for Murphy's Lac Da Vang Project off Vietnam

Current News

China's CNOOC Posts Record First-Half Profit

BP Completes Central Azeri Platform Maintenance, Ramps Up Production

Iran-Oman Talks on Hormuz Reopening Drive Down Oil Prices

Viridien Progresses Hybrid Multi-Client Survey Offshore Malaysia

TGS Extends Work on Indonesia’s Largest Seismic Acquisition Project

Saudi Contractor Enters Oman with Four-Well Drilling Assignment

McDermott Gets ADNOC’s ‘Mega Contract’ to Advance Umm Shaif Field

Iran Tightens Enforcement of Strait of Hormuz Transit Rules

TenneT Completes Drilling, Installation of Protective Conduits for Wind Farms

ConocoPhillips, CNOOC Put Penglai Field off China Into Full Operation

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com