Formosa 1 Phase 2 Foundations Installed

Tuesday, August 20, 2019

Jan De Nul Group said it has installed all 20 foundations for the 120-megawatt (MW) Formosa 1 Phase 2 wind farm offshore Taiwan.

As part of the Dutch company mobilized the Seaway Yudin to install the foundations as part of its EPCI contract for building of the overall balance of plant.

The foundations consist of a monopile and transition piece structure with a grouted connection. The monopiles range from 752 to 1,230 tons, with a maximum diameter of 8.4 meters and a length ranging from 60.1 to 79.5 meters. Each of the transition pieces weigh 465 tons and consists of five internal platforms, an external platform and boat landing.

Over a period of less than one year, Jan De Nul completed the fabrication process, the sea transport, the load in and out at the marshaling harbor in the Port of Taichung, and finally the installation of all foundations offshore.

The parallel installation of scour protection, export and inter array cables is also well underway, Jan De Nul said.

The wind farm is owned by Formosa I Wind Power Co. Ltd., a partnership of Ørsted (35%), JERA (32.5%), Macquarie Capital (25%) and Swancor Holding (7.5%).

The offshore wind farm is located around 6 kilometers off the west coast of the Miaoli district in the Taiwan Strait, with water depths ranging between 15 and 30 meters. The project comprises 2 phases: phase 1 of two wind turbines with a total capacity of 8MW. Extended from phase 1, this second phase will add 20 offshore wind turbines with a total capacity of 120MW to Formosa 1's current 8MW capacity. Formosa 1 will be the first commercial-scale offshore wind farm in Taiwan before 2020.

Categories: Offshore Offshore Energy Engineering Activity Asia Renewables Installation

Related Stories

Ichthys LNG Strike Causes Delay to Taiwan-Bound Cargo

Oil Jumps Over 3% After US-Iran Exchange Attacks

Oil Prices Rise as Iran Talks Stall and Inventories Shrink

Oil Prices Ease as US Holds Off Renewed Strikes Against Iran

Petronas Signs 20-year Charter Deal with MISC for Five LNG Carrier Newbuilds

Iraq, Pakistan Secure Oil Shipments via Hormuz with Iran Agreements

IEA: Middle East Conflict Reshaping Medium-Term Gas Outlook

Brent Near $114 as Middle East Conflict Continues

Bureau Veritas Expands Offshore Services with New Asia Hub

Toyo, OneSubsea Form Subsea CCS Partnership

Current News

Oil Slips as Oman Reports Normal Operations at Key Oil Terminal

Petronas Signs Offshore Oil Recovery Collaboration Deal

SBM Offshore to Sell 45% Stake in Mexico-Bound FSO to NYK

Conrad Secures Drilling Rig for Mako Gas Field off Indonesia

Oman’s Block 50 Offshore Drilling Ops Face Further Delays

Aramco Picks McDermott for Energy Projects in Saudi Arabia

Velesto’s Jack-Up Rig Up for Gulf of Thailand Drilling Campaign

Kuwait Sees 70% Oil Output Recovery within Two Months of Hormuz Reopening

Capricorn Energy Grants Third Extension for Potential Takeover Offer

Ichthys LNG Strike Causes Delay to Taiwan-Bound Cargo

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com