Formosa 1 Phase 2 Foundations Installed

Tuesday, August 20, 2019

Jan De Nul Group said it has installed all 20 foundations for the 120-megawatt (MW) Formosa 1 Phase 2 wind farm offshore Taiwan.

As part of the Dutch company mobilized the Seaway Yudin to install the foundations as part of its EPCI contract for building of the overall balance of plant.

The foundations consist of a monopile and transition piece structure with a grouted connection. The monopiles range from 752 to 1,230 tons, with a maximum diameter of 8.4 meters and a length ranging from 60.1 to 79.5 meters. Each of the transition pieces weigh 465 tons and consists of five internal platforms, an external platform and boat landing.

Over a period of less than one year, Jan De Nul completed the fabrication process, the sea transport, the load in and out at the marshaling harbor in the Port of Taichung, and finally the installation of all foundations offshore.

The parallel installation of scour protection, export and inter array cables is also well underway, Jan De Nul said.

The wind farm is owned by Formosa I Wind Power Co. Ltd., a partnership of Ørsted (35%), JERA (32.5%), Macquarie Capital (25%) and Swancor Holding (7.5%).

The offshore wind farm is located around 6 kilometers off the west coast of the Miaoli district in the Taiwan Strait, with water depths ranging between 15 and 30 meters. The project comprises 2 phases: phase 1 of two wind turbines with a total capacity of 8MW. Extended from phase 1, this second phase will add 20 offshore wind turbines with a total capacity of 120MW to Formosa 1's current 8MW capacity. Formosa 1 will be the first commercial-scale offshore wind farm in Taiwan before 2020.

Categories: Offshore Offshore Energy Engineering Activity Asia Renewables Installation

Related Stories

Woodside Agrees Long-Term LNG Supply with Petronas Unit

MODEC and Terra Drone Renew FPSO Drone Inspection Partnership

Petronas-Eni Upstream Joint Venture to Take Up to Two Years to Set Up

Wood JV Gets EPC Job for Shell off Brunei

Chuditch Gas Field Drilling Ops Get Delayed to Next Year

Fugro Expands Geotechnical Testing Capabilities in Indonesia

MODEC, Carbon Clean to Advance FPSO-Mounted Carbon Capture Tech

CDWE Wraps Up Pin Pile Installation Job for Taiwanese Offshore Wind Farm

ABS Greenlights SHI’s Multi-Purpose Deepwater LNG Floating Unit

‘Ultra-Mega’ Offshore Deal for L&T at QatarEnergy LNG’s North Field Gas Scheme

Current News

Petronas Expands Suriname Portfolio with Deepwater Block Acquisition

Japanese Oil and Gas Firm Enters Two Blocks off Malaysia

Yinson Production, “K” LINE Target Europe's CCS with FSIU and LCO2 Solutions

Woodside Agrees Long-Term LNG Supply with Petronas Unit

MODEC and Terra Drone Renew FPSO Drone Inspection Partnership

Yinson Production Closes $1B Investment to Drive Further Growth

Petronas-Eni Upstream Joint Venture to Take Up to Two Years to Set Up

Wood JV Gets EPC Job for Shell off Brunei

Chuditch Gas Field Drilling Ops Get Delayed to Next Year

French Oil Major Acquires Interests in Multiple Blocks in Southeast Asia

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com