Formosa 1 Phase 2 Foundations Installed

Tuesday, August 20, 2019

Jan De Nul Group said it has installed all 20 foundations for the 120-megawatt (MW) Formosa 1 Phase 2 wind farm offshore Taiwan.

As part of the Dutch company mobilized the Seaway Yudin to install the foundations as part of its EPCI contract for building of the overall balance of plant.

The foundations consist of a monopile and transition piece structure with a grouted connection. The monopiles range from 752 to 1,230 tons, with a maximum diameter of 8.4 meters and a length ranging from 60.1 to 79.5 meters. Each of the transition pieces weigh 465 tons and consists of five internal platforms, an external platform and boat landing.

Over a period of less than one year, Jan De Nul completed the fabrication process, the sea transport, the load in and out at the marshaling harbor in the Port of Taichung, and finally the installation of all foundations offshore.

The parallel installation of scour protection, export and inter array cables is also well underway, Jan De Nul said.

The wind farm is owned by Formosa I Wind Power Co. Ltd., a partnership of Ørsted (35%), JERA (32.5%), Macquarie Capital (25%) and Swancor Holding (7.5%).

The offshore wind farm is located around 6 kilometers off the west coast of the Miaoli district in the Taiwan Strait, with water depths ranging between 15 and 30 meters. The project comprises 2 phases: phase 1 of two wind turbines with a total capacity of 8MW. Extended from phase 1, this second phase will add 20 offshore wind turbines with a total capacity of 120MW to Formosa 1's current 8MW capacity. Formosa 1 will be the first commercial-scale offshore wind farm in Taiwan before 2020.

Categories: Offshore Offshore Energy Engineering Activity Asia Renewables Installation

Related Stories

Hormuz Crossings Decline as US Renews Iran Blockade

Sunda Energy Applies for Exploration Permit Offshore New Zealand

Hormuz Traffic Falls to Five-Week Low as Tensions Escalate

Oil Surges 3% on Renewed US-Iran Strikes

Markets: Oil Majors Reload Exploration Hoppers Across Sub-Saharan Africa

Qatari LNG Carriers Re-Enter Hormuz as Traffic Through Strait Slumps

Oil Edges Higher as Uncertainty Clouds US-Iran Truce

Post-War Gulf Faces Push for Alternative Export Routes

IEA Expects Gradual Hormuz Recovery, Oversupplied Market in 2027

Japan’s Shipping Industry Awaits Clarifications on Hormuz Reopening

Current News

ConocoPhillips, CNOOC Put Penglai Field off China Into Full Operation

Mermaid Maritime Expands Into US Offshore Market

ONGC Nears Venezuela Operatorship Deals, Regains Russia’s Sakhalin-1 Stake

Fugro Secures India Deepwater Drilling ROV Contract

Vantris Energy Secures Petronas’ Offshore Drilling Work Orders

ADNOC, SLB Roll Out AI Platform Across More Than 120 Drilling Rigs

Oil Rises as Uncertainty Clouds US-Iran Peace Talks

India’s ONGC to Allocate Half of New Oil Storage to Strategic Reserves

Subsea7 Lands ‘Sizeable’ Contract for Work Offshore Brunei

FPSO for Azule Energy’s Angola Offshore Field Starts Taking Shape in China

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com