Formosa 1 Phase 2 Foundations Installed

Tuesday, August 20, 2019

Jan De Nul Group said it has installed all 20 foundations for the 120-megawatt (MW) Formosa 1 Phase 2 wind farm offshore Taiwan.

As part of the Dutch company mobilized the Seaway Yudin to install the foundations as part of its EPCI contract for building of the overall balance of plant.

The foundations consist of a monopile and transition piece structure with a grouted connection. The monopiles range from 752 to 1,230 tons, with a maximum diameter of 8.4 meters and a length ranging from 60.1 to 79.5 meters. Each of the transition pieces weigh 465 tons and consists of five internal platforms, an external platform and boat landing.

Over a period of less than one year, Jan De Nul completed the fabrication process, the sea transport, the load in and out at the marshaling harbor in the Port of Taichung, and finally the installation of all foundations offshore.

The parallel installation of scour protection, export and inter array cables is also well underway, Jan De Nul said.

The wind farm is owned by Formosa I Wind Power Co. Ltd., a partnership of Ørsted (35%), JERA (32.5%), Macquarie Capital (25%) and Swancor Holding (7.5%).

The offshore wind farm is located around 6 kilometers off the west coast of the Miaoli district in the Taiwan Strait, with water depths ranging between 15 and 30 meters. The project comprises 2 phases: phase 1 of two wind turbines with a total capacity of 8MW. Extended from phase 1, this second phase will add 20 offshore wind turbines with a total capacity of 120MW to Formosa 1's current 8MW capacity. Formosa 1 will be the first commercial-scale offshore wind farm in Taiwan before 2020.

Categories: Offshore Offshore Energy Engineering Activity Asia Renewables Installation

Related Stories

Sapura Energy to Provide Subsea Services for Shell Off Malaysia

Dyna-Mac Secures $664M Backlog with New Contracts

JUB Pacific Bolsters Liftboat Fleet

ABS Awards AIP for OceanSTAR’s FSO Design

Turkish Oil Terminal Halts Russian Oil Business

Singapore's Temasek Shortlists Saudi Aramco, Shell in Sale of Pavilion Energy Assets

ONE Guyana FPSO for ExxonMobil’s Yellowtail Field Leaves Drydock in Singapore

Equinor Pens 15-Year LNG Supply Deal with Indian Firm

Brassavola Completes Maiden Ship-to-Ship LNG Bunkering Operation

QatarEnergy and Petronet Sign 20-Year LNG Supply Deal for India

Current News

SOVs – Analyzing Current, Future Demand Drivers

Decarbonization Offshore O&G: Navigating the Path Forward

Subsea Vessel Market is Full Steam Ahead

China's Imports of Russian Oil Near Record High

TotalEnergies Inks $530M Deal to Acquire Malaysia’s SapuraOMV

Energy Storage on O&G Platforms - A Safety Boost, too?

Malampaya Gas Field Exceeds Export Capacity Amid Grid Demands in Philippines

Timor-Leste: Chuditch-2 Well to be Drilled at New Location Following Site Surveys

Akastor’s Subsidiary Wins $101M Case Against Seatrium's Jurong Shipyard

ONGC Hires Consortium to Deliver FEED Work for Bay of Bengal Oil Field

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com