Yamal LNG Reaches Full Capacity

Laxman Pai
Wednesday, December 12, 2018

The Yamal liquefied natural gas (LNG) project in Arctic Russia officially commissioned the third and last production line Tuesday.

Russia's independent natural gas producer PAO Novatek announced that its joint venture Yamal LNG has reached full capacity at the plant’s three LNG trains.

The Yamal LNG project was implemented in record time and on budget with the launches of the second and third trains made ahead of schedule by six months and more than a year, respectively. Russian Federation Prime Minister Dmitry Medvedev participated in the official ceremony commemorating this milestone event at Yamal LNG.

Yamal LNG is comprised of three liquefaction trains with a total nameplate capacity of 16.5 mmtpa, or 5.5 mmtpa per LNG train. The project is supported by a fleet of Arc7 ice-class tankers supplemented by lower ice-class designated tankers to transport LNG cargos.

More than 100 LNG cargoes have been offloaded with approximately 7.5 million tons of LNG produced and delivered to five continents – a year since the project’s first shipment in December 2017.

“Yamal LNG is currently the largest LNG project in Russia with an aggregate share of about five percent of the global LNG market”, noted Leonid V. Mikhelson, Novatek’s Chairman of the Management Board.

Mikhelson added, “We believe that Yamal LNG represents a unique benchmark for the global oil and gas industry in terms of project success and implementation. Moreover, the Yamal LNG project enabled us to become one of the major players in the global LNG market. Our accomplishments pave the way to create a large-scale LNG platform utilizing the prolific conventional natural gas resources on the Yamal and Gydan peninsulas as well as facilitating the achievement of our strategic goal to produce 55 - 60 mmtpa by 2030.”

The Yamal LNG project is owned by Russia's Novatek (50.1 percent), France's Total (20 percent), CNPC (20 percent) and China's Silk Road Fund (9.9 percent).

The plant consists of three production lines, each having a capacity of 5.5 million tons per year. The first production line started operation in December 2017 and the second one was launched in August 2018.

Categories: Energy LNG Production Tankers Russia Arctic

Related Stories

Vantage Drilling Agrees to $258M Takeover by Eldorado Drilling

Oil Jumps Over 3% After US-Iran Exchange Attacks

BP to Boost Azerbaijan Portfolio with Babek Gas Field Operatorship Takeover

Petrobras Nears Deal With SBM Offshore for Two Sergipe FPSOs

Three Dead After Incident at Petronas' FSO Offshore Malaysia

Oil Prices Rise as Iran Talks Stall and Inventories Shrink

ScioSense Launches UFC23 Ultrasonic Flow Converter for High-Precision, Ultra-Low-Power Smart Metering

Norway O&G Revenue Forecast Jumps 30% for '26

Strike Threat Grows at Ichthys LNG after Workers Reject Deal

MidEast Energy Output Recovery to Take Two Years, IEA Says

Current News

Inpex Faces Threat of Broad LNG Loading Ban as AU Labour Dispute Deepens

INEOS Inks LNG Supply Deal with Marubeni for Asian Markets

Cambodia Starts UN Process to Resolve Maritime Dispute with Thailand

Oil Prices Edge Lower Amid Uncertainty Over US-Iran Deal

Vantage Drilling Agrees to $258M Takeover by Eldorado Drilling

Azerbaijan’s Absheron Gas Project Advances with New Sales Agreement

BP Launches Gas Production at Azerbaijan’s Giant ACG Field

Iran Restarts Output at Three South Pars Offshore Gas Platforms

Oil Jumps Over 3% After US-Iran Exchange Attacks

BP to Boost Azerbaijan Portfolio with Babek Gas Field Operatorship Takeover

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com