Marine Survey Work Starts for Greenlink Interconnector

Posted by Michelle Howard
Tuesday, September 25, 2018

The subsea field work for the Greenlink interconnector, one of Europe’s most important infrastructure projects, gets under way with the launch of the first of MMT’s survey vessels, MV Franklin.

The offshore and nearshore surveying along the proposed route of the electricity link between the UK and Ireland is expected to take approximately 40 days, depending on weather conditions. MMT were awarded the contract for the Greenlink Marine Survey (GMS) by Greenlink Interconnector Ltd in August.

Further survey work along the 170km marine route will be undertaken by vessels MV Seabeam, MV Edda Fonn and RED7 Jack-up rig Seariser 2. 

The survey area is between Freshwater West, Pembroke, Wales and Baginbun, Co Wexford, Ireland. A Notice to Mariners has been issued for the area.

The objective of the GMS is to acquire all appropriate data for the confirmation of a preferred route for the High Voltage Direct Current (HVDC) cable system. The surveys will also contribute to the cable burial risk assessment and provide information for the planning applications ensuring that the final route selected is designed sympathetically to the existing marine environment.

Greenlink is a proposed 500MW electrical underground and submarine interconnector, connecting the UK National Grid system at Pembroke substation in Pembrokeshire, Wales to the Irish network at Great Island substation in County Wexford, Ireland. The privately-financed €400 million ($471 mln) project is being developed by Greenlink Interconnector Limited, a subsidiary of Element Power. The commencement of the GMS represents a significant milestone in the development of the project, in preparation for the start of construction scheduled for 2020.

MMT’s geophysical marine survey work comprises intertidal topographic survey, geophysical / hydrographic nearshore and offshore data acquisition, geotechnical investigations with vibrocoring / piston coring and cone penetration testing (PCPT), environmental sampling and imagery, infrastructure crossing survey with ROV, UXO survey, and geotechnical boreholes to inform horizontal directional drilling.

These operations shall provide high resolution and accurate measurements of the bathymetry and seabed features and the shallow geological conditions along the route(s). This will be supplemented by localized unexploded ordnance (UXO) surveys, environmental sampling and imagery as well as surveys of infrastructure crossings using an ROV.

Categories: Surveyors Unmanned Vehicles Hydrographic Offshore Energy Engineering Subsea Vessels

Related Stories

Iran Outlines Terms for Restoring Hormuz Shipping

Seatrium Nears Dual FPSO Sailaway for Petrobras' Búzios Field

Strait of Hormuz Shipping Marks Slight Rise

Iran Tightens Enforcement of Strait of Hormuz Transit Rules

Fugro Secures India Deepwater Drilling ROV Contract

Saipem Cuts Earnings Outlook as Middle East Costs Rise

QatarEnergy Prolongs LNG Force Majeure, Charters Out Tankers

Unity Enters Asia-Pacific Market with Malaysia P&A Work

Hormuz Standoff Risks Chronic Instability for Gulf Oil Flows

Offshore Vessel Pair Ordered from Grandweld Shipyard

Current News

MODEC, Eld Energy Advance Fuel Cell Power for FPSOs

Santos Expands LNG Portfolio with Asia, Canada Deals

Petronas, PTTEP Get Approvals for New Gas Block Sharing Contract

TPAO Eyes Karabakh Offshore Expansion with SOCAR

XRG, ADNOC and SEFE Deepen Gas Ties in Europe

Saudi Oil Lifeline Shut After Attack as Red Sea Threat Grows

Greater Sunrise Gas Production Pushed Back to 2034

SED Energy Holdings and Ventura Offshore Set to Combine Ops

Asia's Oil Industry Braces for Prolonged Hormuz Disruption

Petronas Awards Estuary Cluster PSC to Harvester Energy

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com