Valeura Starts Wassana Platform Installation Offshore Thailand

Friday, October 9, 2026

Valeura Energy has started offshore installation work at its Wassana oil field redevelopment project in the Gulf of Thailand, marking a milestone in the development of a new central processing platform (CPP).

The company confirmed the start of offshore installation in an October 9 update, following the early completion of onshore construction of the CPP earlier in the month.

The platform and its supporting jacket were subsequently loaded onto vessels for transportation to the Wassana field, located in Block G10/48, where Valeura holds a 100% operated interest.

The installation follows the completion of an oil export pipeline in September, which will connect the new CPP to a floating storage and offloading vessel.

Valeura is targeting first oil from the new platform around the beginning of the second quarter of 2027, approximately two months earlier than originally planned.

(Credit: Valeura Energy)

Development drilling is expected to begin in late 2026, with the company having arranged for the Shelf Enterprise drilling rig to start its charter on November 1.

The rig is scheduled to initially drill additional wells at the Nong Yao field before moving to Wassana to support the accelerated redevelopment program.

The new Wassana CPP is expected to achieve a production plateau of approximately 7,500 barrels of oil per day. Valeura estimates that accelerating the project's start-up by two months could add around 430,000 barrels of oil production in 2027 compared with its original development schedule.

Valeura approved the Wassana redevelopment in 2025 to increase recoverable oil volumes and extend the field's economic life beyond what could be achieved using the existing mobile offshore production unit, Ingenium, which is expected to be decommissioned around the end of 2027.

The new platform has also been designed to accommodate potential future tie-ins from satellite production facilities targeting additional oil accumulations north and south of the field.

Valeura has described Wassana as its first organic greenfield development in Thailand and the largest capital project undertaken by the company.

The redevelopment remains on budget, although the accelerated schedule has brought some spending forward from 2027 into 2026.

Categories: Engineering Industry News Activity Asia Gulf of Thailand Oil and Gas

Related Stories

Shell Brings Deepwater Gas Fields Onstream off Malaysia

Orlen's Termination of Qatar LNG Deal Could Yield $2B in Savings

First Oil Flows from Vietsovpetro's Platform Offshore Vietnam

Iran Brings South Pars Gas Platform Fire Under Control

Oil Prices Slide as Trump Signals Pause in Iran Strikes

Velesto’s Jack-Up Rig Up for Drilling Job with Petronas

Aker Solutions Lands Major Role in Qatar’s Offshore Oil Field Revamp

Valaris Secures $600M in New Contracts as Backlog Rises to $4.8B

Big Oil Pockets Near-Record Profits but Spending Restraint Signals Long-Term Doubts

Inpex Moves $21B Indonesian LNG Project Closer to Investment Decision

Current News

When Contractors Collide: Keeping Offshore Energy Projects on Schedule

Floating Production Outlook: Pipeline Looks Huge, But Not All Projects Are Created Equal

Shell Brings Deepwater Gas Fields Onstream off Malaysia

Hanwha Power Secures FSRU Conversion Deal with Energos

Orlen's Termination of Qatar LNG Deal Could Yield $2B in Savings

Oil Heads for Weekly Decline Despite Middle East Supply Threats

Inpex Raises Profit Forecast on Strong Ichthys LNG Production

Singapore Seeks LNG Floating Storage Operators to Expand Bunkering Ops

CNOOC Makes Ultra-Deep Gas Discovery in China's Bohai Sea

First Oil Flows from Vietsovpetro's Platform Offshore Vietnam

Magazine

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com