Full production has returned to a liquefied natural gas (LNG) train at Chevron's Gorgon facility in Western Australia, a company spokesperson said on Wednesday.

On Oct. 31, an "electrical incident" at a substation providing power supply to the facility had curtailed the output of one of the three LNG production trains at Gorgon to 80% of capacity.

Production at Train 3 had resumed "over the past few days," said the Chevron spokesperson. The output reduction at the train however did not affect domestic gas and the other two LNG production trains at Gorgon.  

Gorgon exports LNG to customers across Asia and produces domestic gas for the Western Australian market. It has three LNG trains, or production units, with a total capacity of 15.6 million metric tons per year.

It also has a domestic gas plant with the capacity to supply 300 terajoules of gas per day to Western Australia.


(Reuters - Reporting by Emily Chow; Editing by Christopher Cushing and Rashmi Aich)

Categories: Energy LNG Industry News Activity Australia/NZ Gas

Related Stories

Petronas Names ‘World's First’ Nearshore FLNG Facility

COSL Places $1.64B Order for 59 Offshore Support Vessels

When Contractors Collide: Keeping Offshore Energy Projects on Schedule

Hanwha Power Secures FSRU Conversion Deal with Energos

CNOOC Set to Restore Production at Major South China Sea Gas Field

QatarEnergy Signs Supply Deal for LNG from Woodside's Louisiana Project

Seadrill Secures Offshore Drilling Deals Across Four Countries

Eni and Petronas JV Extend Drilling Backlog for Ventura Offshore’s Semi-Sub Rig

Southeast Asia Plans 100 GW-Plus Gas Power Expansion Despite LNG Risks

Saudi Aramco Plans Standalone Gas Division in Major Reorganization

Current News

Petronas Names ‘World's First’ Nearshore FLNG Facility

Oil Falls as Supply Glut Concerns Overshadow Hormuz Shipping Risks

Masirah Oil Delays Yumna Production as Drilling Progresses off Oman

Searah Starts Production from New Bukit Tua Well Offshore Indonesia

NMDC Energy to Acquire Wasco’s Engineering Division for $190M

China’s COOEC Lands $800M QatarEnergy Subsea Contract

Oil Prices Rise as Houthi Strikes Revive Supply Disruption Fears

COSL Places $1.64B Order for 59 Offshore Support Vessels

When Contractors Collide: Keeping Offshore Energy Projects on Schedule

Floating Production Outlook: Pipeline Looks Huge, But Not All Projects Are Created Equal

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com