Court Battle Between Santos and Traditional Owners Continues

Wednesday, November 15, 2023

Santos has issued a statement after the decision of the Federal Court of Australia on November 15 ruling that pipelay activities can commence on an 86-kilometer section of pipeline for the Barossa Gas Export Pipeline (GEP) – but not south of kilometre point 86 (KP86).

This southern section would pass to the west of the Tiwi Islands.

The Court has set December 4, 2023 as the date of commencement of the hearing of application brought by Jikilaruwu traditional owner Simon Munkara and two others seeking to restrain Santos from continuing the pipelay until it revises its environmental plan after re-consultation with relevant persons, and the National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA) accepts a revised plan.

Santos intends to vigorously defend those proceedings.

Munkara alleges laying the GEP will impact submerged Tiwi cultural heritage, creating a new environmental risk. Munkara’s lawyers say that the 263km pipeline would damage burial sites on the sea floor, dreaming tracks and songlines. (Songlines describes the features and directions of travel that were included in a song that had to be sung and memorised for the traveller to know the route to their destination.)

All three Tiwi Traditional Owners are represented by the Environmental Defenders Office (EDO).  

Senior Elder Molly Munkara said: “My heart is beating, happy one. It’s really our waterways, our place where we go and have traditional life. We are part of that area, the land and the sea. It means a lot to me. And I’m glad, I’m happy.”

EDO Special Counsel Alina Leikin said: “The Federal Court has already established that Santos needs to do proper consultation with Traditional Owners before a valid approval for work can be issued. This case is about ensuring that companies properly assess evidence of new impacts and risks caused by their projects when it comes to light in accordance with the law.”

However, Santos says it has complied with a General Direction issued by NOPSEMA in January 2023 in relation to impacts on underwater cultural heritage places to which Indigenous people have spiritual and cultural connections.

An independent expert anthropologist concluded there were no such underwater cultural heritage places, following interviews with around 170 Tiwi people and extensive archaeological and anthropological literature and studies. These studies included consideration of independent expert archaeological, geological and sedimentological assessment of the pipeline route.

Santos says it is committed to delivering the Barossa Gas Project. “With the Barossa Project set to supply the Darwin LNG plant for years to come, it is important for local jobs, as well as opportunities for Traditional Owners, exports, and relationships with investors and gas customers in Asia, that this project continues.”

Australian Energy Producers Chief Executive Samantha McCulloch said: “The economic and energy security of Australia and its valued international partners is being damaged.” The court decision is further evidence of the urgent need for the Australian Government to provide certainty for businesses and fix the broken offshore regulatory approvals system, she says.

“Reliable and affordable energy for Australian households and businesses is at risk alongside the tens of billions of dollars of economic benefits and jobs our exports deliver for Australia. The Government must act immediately to fix this issue and end the lawfare.

“Wait times for some approvals have blown out to more than two years. Courts continue to overturn or block approvals already awarded by the National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA).

“Companies which consult with stakeholders in good faith are watching approvals granted by the regulator be overturned or blocked in court. Regulations that provide clarity and certainty for industry while maintaining comprehensive and meaningful consultation with stakeholders are urgently needed.”

Categories: Offshore Pipelines Gas Subsea Pipelines

Related Stories

TotalEnergies Inks $530M Deal to Acquire Malaysia’s SapuraOMV

MOL Puts FSRU for Indonesia's Jawa 1 LNG Power Plant Into Operation

Turkish Oil Terminal Halts Russian Oil Business

Quick Connect: OAL Subsea Pipeline Completed

Enhancing Environmental Accountability in Offshore Operations via Data Analytics

Digitalization is Drawing CCS a New Learning Curve

Marine Power R&D Insights: Matt Hart, Wabtec Corporation

BW Opal FPSO Starts Taking Final Shape Ahead of Barossa Assignment

T7 Global's MOPU Set for Work at Valeura’s Gulf of Thailand Field

QatarEnergy Signs 15-year LNG Supply Deal with Excelerate Energy

Current News

ConocoPhillips Misses Quarterly Profit Estimates

Taliban Plan Regional Energy Trade Hub with Russian Oil in Mind

Russia Shipping Oil to North Korea Above UN Mandated Levels

Yinson Completes $1.3B Financing for Agogo FPSO

Sapura Energy Hooks Subsea Services Contract from Thai Oil Major Off Malaysia

Philippines' PXP Energy Eyes Petroleum Blocks in Non-Disputed Areas

BP Suspends Production at Azerbaijani Platform for Maintenance Works

SOVs – Analyzing Current, Future Demand Drivers

Decarbonization Offshore O&G: Navigating the Path Forward

Subsea Vessel Market is Full Steam Ahead

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com