Australia Court Halts Santos' Pipeline Works on $3.6B Barossa Gas Project

Renju Jose and Ayushman Ojha
Thursday, November 2, 2023

Santos said on Thursday an Australian court had granted an interim injunction preventing it from starting work on laying undersea pipelines on its $3.6 billion Barossa gas project off northern Australia.

The ruling comes after Simon Munkara, a traditional land owner from the Tiwi Islands, lodged proceedings with the Federal Court of Australia to halt the pipeline works until its impact and risk to underwater cultural heritage were properly assessed.

Law firm Environmental Defenders Office (EDO) represented Munkara and other indigenous elders from the Tiwi Islands who had urged the government to make an urgent declaration to block the pipeline construction.

The pipeline would cause significant damage to ancient burial grounds, aboriginal art and other sacred ancestral sites, Munkara said, according to a statement from EDO.

The court will sit on Nov. 13 to determine whether to extend the injunction until the final hearing, which will be held on an expedited basis. 

Santos, which aims to start producing gas from Barossa in the first half of 2025, said its guidance on cost and schedule for the project remained unchanged. It will continue to defend the court proceedings.  

Australia's offshore regulator ordered Santos in January to evaluate the environmental risks to underwater indigenous cultural heritage before starting pipeline work though it did not prohibit the start of work.

Santos has said, citing an independent expert, that there were no specific underwater cultural heritage sites along the planned route of the pipeline. 

A Santos ship was hours away from beginning work on the pipeline, lawyers for Munkara told the court. Santos said the vessel will remain at its current location but no pipeline works will be conducted during the interim injunction.

The court's ruling poses another hurdle for the project and a win for Indigenous groups opposing fossil fuel developments, who have been raising concerns it could damage the environment and their cultural heritage.

In September, the federal court halted approval for Woodside to conduct seismic blasting under the seabed for its $12 billion Scarborough gas project after a legal challenge by an Indigenous woman.    

(Reuters - Reporting by Renju Jose in Sydney and Ayushman Ojha in Bengaluru; Editing by  Mrigank Dhaniwala, Rashmi Aich and Jacqueline Wong)

Categories: Pipelines Activity Australia/NZ

Related Stories

PTTEP Sells Its Entire Stake in Deepwater Block Offshore Mexico to Repsol

First Oil Starts Flowing at CNOOC’s South China Sea Field

Korea's Hanhwa Sets Out Plan for Full Takeover of Singapore's Dyna-Mac

ADES Buys Two Jack-Ups from Vantage Drilling in $190M Deal

Santos Pens Mid-Term LNG Supply Deal

New Partner Joins Timor-Leste Offshore Gas Development

CNOOC Brings Online Another South China Sea Field

ADNOC Signs LNG Supply Agreement with Osaka Gas for Ruwais LNG Project

Valeura Set to Restart Wassana Production Offshore Thailand

South Korea's KOMIPO Cancels Plans for LNG Import Terminal

Current News

Velesto Completes Removal of Wrecked Naga 7 Jack-Up Rig Off Malaysia

BP Greenlights $7B CCUS Scheme Tied to Indonesia LNG Facility

Sapura Scoops Petrobras Contract for Pan-Malaysia Offshore Services

Velesto’s Drilling Rigs Up for Automatization Overhaul Under New Tech Alliance

US Firm Finds Chinese Partner to Deliver Mobile Offshore Drilling Units

TotalEnergies and Oil India to Jointly Tackle Methane Emissions Issues

Keppel Reclaiming Control of 13 Rigs to Cash In on Offshore Drilling Market's Growth

Global Offshore Wind Stumbles to the End of '24

Seatrium Delivers Fifth Jack-Up to Borr Drilling

Malaysia's FPSO Firm Bumi Armada Eyes Merger with MISC’s Offshore Unit

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com