All 47 Turbines Installed at Formosa 2 Offshore Wind Project

OEDigital
Wednesday, February 1, 2023

All 47 offshore wind turbine generators have been installed at the Formosa 2 offshore wind project the 376MW Formosa 2 offshore wind project off the coast of Miaoli in western Taiwan.

The last wind turbine was successfully installed on January 31. 

According to information on the project's website, commissioning and completion works continue, and soon the wind farm will be supplying electricity to Taiwan's grid at full capacity.

Currently, over 80% of the installed turbines are supplying power to the grid.

Formosa 2 utilizes BMW Direct Drive wind turbines manufactured by Siemens Gamesa Renewable Energy, with a rotor diameter of 167 meters, hub height of 116.4 meters, and blade length of 81 meters.

Credit: Formosa 2

Tiemen Maebe, Project Director of Formosa 2, said: "We extend our sincere gratitude to our valued partners, contractors, and project team members for their unwavering commitment and outstanding contributions. With the successful completion of this milestone, we are now well positioned to move forward towards commercial operation and the operation and maintenance phase, while ensuring adherence to the most stringent standards of health, safety, and environmental performance. We remain fully committed to providing sustainable and renewable energy to Taiwan."

Formosa 2 offshore wind project has an installed capacity of 376 MW and generate enough electricity to power the equivalent of approximately 380,000 households. It is being developed by JERA, Macquarie's Green Investment Group (GIG) and Synera Renewable Energy (SRE) (formerly known as Swancor Renewable Energy). GIG is supported by its portfolio company, Corio Generation.


Categories: Energy Renewable Energy Activity Renewables Offshore Wind

Related Stories

Op-Ed: Kazakhstan’s National O&G Firm Positioning Itself as Global Energy Player

CIP Reaches Financial Close for Offshore Wind Farm in Taiwan

Second Hai Long Substation Heads to Project Site Offshore Taiwan

China Unveils Plans for New Offshore Wind Farms to Tackle Carbon Emissions

EnQuest to Acquire Harbour Energy's Vietnamese Assets

CNOOC Boosts Dongfang Gas Fields Output with New Platform Coming Online

Petronas to Retain National Authority After Sarawak Gas Deal

Abu Dhabi's NMDC Group Gets $1.1B Subsea Gas Pipeline Job in Taiwan

Vestas Lands First 15MW Offshore Wind Turbine Order in Asia Pacific

Shell Shuts Down Oil Processing Unit in Singapore Due to Suspected Leak

Current News

Shell-Reliance-ONGC JV Complete India’s First Offshore Decom Project

The Future of Long-Idle Drillships: Cold-Stacked or Dead-Stacked?

TMC Books Compressors Orders for FPSO and LNG Vessels

MODEC, Sumitomo Partner Up for Delivery of Gato do Mato FPSO

Chuditch Gas Field Up for Summer Drilling Ops as Sunda Reshapes Ownership Structure

EnQuest Bags Two Production Sharing Contracts off Indonesia

Hanwha Drilling’s Tidal Action Drillship En Route to Petrobras’ Roncador Field

China's ENN, Zhenhua Oil Ink LNG Supply Deals with ADNOC

MODEC Wins ExxonMobil Guyana’s Hammerhead FPSO Contract

India Stretches Bids Deadline for 13 Offshore Deep-Sea Mineral Blocks

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com