Australia Court Scraps Drilling Permit for Santos' $3.6B Barossa Offshore Gas Project

Sonali Paul
Wednesday, September 21, 2022

Australia's Federal Court on Wednesday ruled in favor of an indigenous group's challenge against a drilling permit for Santos Ltd's Barossa gas development, in what Santos called a "disappointing" setback for the $3.6 billion project.

Traditional landowners from the Tiwi Islands led by Dennis Tipakalippa had asked the court in June to overturn drilling approval for the Barossa project near the islands off the northern Australia coastline granted by the industry regulator, the National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA).

The stakes are high for Santos, which announced plans to seek an expedited appeal soon after the ruling was issued. Barossa is the company's biggest project, and essential for its Darwin liquefied natural gas (LNG) plant, which will lose supply from its foundation gas source, the Bayu Undan field, later this year.

"Mr. Tipakalippa has established that NOPSEMA ... failed, in accordance with the Regulations, to assess whether the Drilling EP (environment plan) demonstrated that Santos consulted with each person that it was required by the Regulations to consult with," Judge Mordecai Bromberg said in his ruling.

"The acceptance (or permission) given by NOPSEMA was legally invalid. NOPSEMA's decision to accept the Drilling EP must therefore be set aside," he said.

Announcing its plans to appeal, Santos said the decision should be reviewed by the full Federal Court, given the significance of the decision to the company, its international joint venture partners and customers.

Santos' partners in the Barossa project are South Korean energy company SK E&S and Japan's top power generator JERA, a joint venture between Tokyo Electric Power and Chubu Electric Power.



"This is a disappointing outcome," Santos said in a statement to the Australian Stock Exchange, adding that the relevant drilling was to occur at a site in the Timor Sea about 140 kilometers north of the Tiwi Islands.

"Project approval uncertainty is a public policy issue that should be urgently addressed by Australian governments to reduce risk for trade and investment in projects around the country," Santos said.

NOPSEMA said it noted the verdict and was considering the implications of the decision. "It is a matter for Santos to consider what the decision means for the Barossa project," a NOPSEMA spokesperson said in emailed comments.

Tipakalippa, who filed the challenge, said Santos had not properly consulted the traditional owners about the drilling, and told the court that the Barossa project posed a risk to sacred sites and spiritual connection to Sea Country.

"We are so happy and so relieved. We have won. The most important thing for us is to protect our Sea Country," Tipakalippa said in a statement.



Santos, which had agreed to suspend drilling for the project pending the court decision, said it had "engaged with" indigenous representative bodies - the Tiwi Land Council and the Northern Land Council - about the proposed drilling, and the regulator had accepted its efforts to consult with Tiwi islanders.

Santos was on track to start producing gas from Barossa in 2025 to feed its Darwin liquefied natural gas (LNG) plant.

"The drilling activities are not on the critical path for the project and we have headroom in the project cost contingency," Santos said.

Credit Suisse analyst Saul Kavonic said if Santos fails in its appeal and has to submit a new environmental plan, that could impact the overall cost and add months or even more than a year to the project's schedule.

Besides expanding consultations, Kavonic said, there is a risk that the regulator might broaden any review to include other considerations, such as looking at emissions, since the country's carbon emissions targets are tighter now than when the permit was approved. 


 (Reuters - Reporting by Sonali Paul; Editing by Kenneth Maxwell)

Categories: Energy Drilling Industry News Activity Australia/NZ Regulations

Related Stories

MDL Secures Cable Laying Job in Asia Pacific

Petronas to Leverage AI to Expedite Oil and Gas Exploration Activities

PV Drilling Takes Ownership of Noble Corporation’s Stacked Jack-Up Rig

Saipem Wins FEED Contract For Abadi LNG Project FPSO Module In Indonesia

Valeura Makes Progress with Multi-Well Drilling Campaign in Gulf of Thailand

Four Jack-Up Drilling Rig Deals Set to Bring In $129M for Borr Drilling

Woodside and Jera Agree LNG Cargoes Supply for Japan’s Winter Period

Fugro Expands Geotechnical Testing Capabilities in Indonesia

BP Expands Oil and Gas Scope in Azerbaijan with New Projects and Exploration Rights

Valeura Concludes Eight-Well Drilling Campaign in Gulf of Thailand

Current News

MDL Secures Cable Laying Job in Asia Pacific

Hibiscus Petroleum Starts Drilling at Teal West Field off UK

Yinson Production Nets DNV Approval for New FPSO Hull Design

Hanwha Ocean's Tidal Action Drillship Starts Maiden Job with Petrobras

Petronas to Leverage AI to Expedite Oil and Gas Exploration Activities

Brownfield Output Decline Accelerates, says IEA

PV Drilling Takes Ownership of Noble Corporation’s Stacked Jack-Up Rig

Hanwha Ocean Enlists ABB for Singapore’s First Floating LNG Terminal

Aquaterra Energy Nets Subsea Analysis Contracts with INPEX off Indonesia

POSH Set to Tow Nguya FLNG from China to Eni’s Congo Field

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com