Jadestone Shutting Down Montara FPSO Output to Fix Tank Issues

OE Staff
Friday, August 12, 2022

Asia Pacific-focused oil and gas company Jadestone has decided to shut production from its Montara field FPSO in the Timor Sea, off Australia, to allow for repairs on a tank that leaked oil back in June through a 30-millimeter crack.

While the incident had led Jadestone to shut down production from the Montara Venture FPSO, production resumed in July following a temporary repair of the leak point in the 2C tank, and Jadestone at the time said it was working on a permanent solution.

In a statement on Friday, Jadestone said that, while preparing for the repair, it found a defect in water ballast tank 4S, which will now also be included in the workscope of repairs, and that it would need to shut production from the FPSO again.

"Over the past several weeks, the permanent repair to tank 2C has been developed, though delayed due to weather, manpower and logistics issues, further complicated while the facility remains in production operations.  This has resulted in an inability to simultaneously accommodate the increased number of inspection and repair crews alongside production operations.  

As a result, the company has taken the decision to temporarily shut-in production from Montara and reorganize offshore manpower on the FPSO, enabling priority and focus on maintenance and inspection crews.  This is the most practical and efficient way to complete tank repairs whilst progressing ongoing inspection and remediation to other tanks in the FPSO and to complete key remaining scheduled inspection and repair activities planned for this year," the company said.

Credit: Jadestone

It is currently anticipated that these inspection and repair activities will result in production being shut-in during the remainder of August and potentially through September 2022.  It is currently anticipated that prioritizing the activity as described by Jadestine will result in incremental costs of US$2-4 million.

Output guidance cut

As a result of the Montara shut-in, and the performance of the wider production portfolio year-to-date, Jadestone now expects that 2022 production will average between 13,000 and 14,000 boe/d. 

This compares to the announcement on June 20, 2022, which signaled that 2022 production would likely be around 15,500 boe/d, being the lower end of the previous guidance range.  

The revised 2022 production guidance reflects the company's assumption that production from its non-operated assets offshore Peninsular Malaysia will now remain shut in for the remainder of 2022, due to ongoing delays in reinstating operations.

"The company is confident that by taking this approach at Montara, the necessary work required to deliver long-term asset integrity can be safely and efficiently completed.  The impact is short-term and there is no reduction in reserves.  As a result, and given its strong balance sheet, the company intends to continue the share buy-back program announced on August 2, 2022," Jadestone said.


Categories: Energy Activity FPSO Production Asia Floating Production Australia/NZ

Related Stories

Oil Up 8% as Middle Eastern War Rages

Seatrium Targets $40M Cost Savings in Continued Divestment Drive

MISC Secures Long-Term Charter for Papua New Guinea's First FSO

Petronas Takes Operatorship of Oman’s Offshore Block 18

Japan’s JERA Agrees Long-Term LNG Supply from Middle East

Australia and Timor-Leste Push to Advance Greater Sunrise Gas Field

Inpex Moves to Accelerate Indonesia’s Abadi LNG Project

ADNOC Gas Signs $3B LNG Supply Deal with India’s HPCL

CNOOC Launches New Offshore Oil Development in Southern China

CNOOC Puts New South China Sea Development Into Production Mode

Current News

Remazel Expands Offshore Services Footprint in Brazil with H Tech Acquisition

Lamprell Secures ONGC Deal for Subsea Pipeline Replacement Project

China’s Five-Year Plan Focuses on Oil Stability, Gas and Reserves Growth

Velesto Gets Shell’s Deepwater Job Offshore Malaysia

Subsea7 Extends Engagement on Türkiye’s Sakarya Field with New Deal

Asia’s Oil Reliance on Middle East Explained

Oil Prices Go Up 3% as Iran Crisis Disrupts Supply

Petronas Picks OceanSTAR Elite FPSO for Asian Oil and Gas Project

Velesto Inks Five-Year Drilling Deal for Jack-Up Rig with Petronas

Arabian Drilling Reactivates Fleet as GCC Offshore Contract Starts

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com