Jadestone Shutting Down Montara FPSO Output to Fix Tank Issues

OE Staff
Friday, August 12, 2022

Asia Pacific-focused oil and gas company Jadestone has decided to shut production from its Montara field FPSO in the Timor Sea, off Australia, to allow for repairs on a tank that leaked oil back in June through a 30-millimeter crack.

While the incident had led Jadestone to shut down production from the Montara Venture FPSO, production resumed in July following a temporary repair of the leak point in the 2C tank, and Jadestone at the time said it was working on a permanent solution.

In a statement on Friday, Jadestone said that, while preparing for the repair, it found a defect in water ballast tank 4S, which will now also be included in the workscope of repairs, and that it would need to shut production from the FPSO again.

"Over the past several weeks, the permanent repair to tank 2C has been developed, though delayed due to weather, manpower and logistics issues, further complicated while the facility remains in production operations.  This has resulted in an inability to simultaneously accommodate the increased number of inspection and repair crews alongside production operations.  

As a result, the company has taken the decision to temporarily shut-in production from Montara and reorganize offshore manpower on the FPSO, enabling priority and focus on maintenance and inspection crews.  This is the most practical and efficient way to complete tank repairs whilst progressing ongoing inspection and remediation to other tanks in the FPSO and to complete key remaining scheduled inspection and repair activities planned for this year," the company said.

Credit: Jadestone

It is currently anticipated that these inspection and repair activities will result in production being shut-in during the remainder of August and potentially through September 2022.  It is currently anticipated that prioritizing the activity as described by Jadestine will result in incremental costs of US$2-4 million.

Output guidance cut

As a result of the Montara shut-in, and the performance of the wider production portfolio year-to-date, Jadestone now expects that 2022 production will average between 13,000 and 14,000 boe/d. 

This compares to the announcement on June 20, 2022, which signaled that 2022 production would likely be around 15,500 boe/d, being the lower end of the previous guidance range.  

The revised 2022 production guidance reflects the company's assumption that production from its non-operated assets offshore Peninsular Malaysia will now remain shut in for the remainder of 2022, due to ongoing delays in reinstating operations.

"The company is confident that by taking this approach at Montara, the necessary work required to deliver long-term asset integrity can be safely and efficiently completed.  The impact is short-term and there is no reduction in reserves.  As a result, and given its strong balance sheet, the company intends to continue the share buy-back program announced on August 2, 2022," Jadestone said.


Categories: Energy Activity FPSO Production Asia Floating Production Australia/NZ

Related Stories

China’s CNOOC Brings Bohai Sea Oil Field On Stream

Kuwaiti Oil and Gas Firm Exploring More Opportunities in Indonesia's Natuna Sea

BP Greenlights $7B CCUS Scheme Tied to Indonesia LNG Facility

TotalEnergies and Oil India to Jointly Tackle Methane Emissions Issues

Korea's Hanwha Raises Offer for Singapore's Dyna-Mac Takeover

East Timor Eyes Chinese Partners for Stalled Greater Sunrise Gas Development

Nong Yao C Development Bolsters Valeura’s Production Rates Off Thailand

First Oil Starts Flowing at CNOOC’s South China Sea Field

OPEC+ Has Oil Price and Demand Problems. It Should Solve Demand

CNOOC Brings Online Another South China Sea Field

Current News

The Five Trends Driving Offshore Oil & Gas in 2025

China’s CNOOC Brings Bohai Sea Oil Field On Stream

Offshore Service Vessels: What’s in Store in 2025

ABS Approves Hanwha Ocean’s FPSO Design

AI & Offshore Energy: The Higher the Stakes, the More Value AI Creates

Floating LNG Conversion Job Slips Out of Seatrium’s Hands

Transocean’s Drillship to Stay in India Under New $111M Deal

INEOS Picks Up CNOOC’s US Assets in $2B Deal

Sunda Energy, Timor-Leste Gov Plan Accelerated Chuditch Gas Development

RINA to Conduct Pre-FEED Study for Petronas’ CCS Project in Malaysia

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com