Jadestone Shutting Down Montara FPSO Output to Fix Tank Issues

OE Staff
Friday, August 12, 2022

Asia Pacific-focused oil and gas company Jadestone has decided to shut production from its Montara field FPSO in the Timor Sea, off Australia, to allow for repairs on a tank that leaked oil back in June through a 30-millimeter crack.

While the incident had led Jadestone to shut down production from the Montara Venture FPSO, production resumed in July following a temporary repair of the leak point in the 2C tank, and Jadestone at the time said it was working on a permanent solution.

In a statement on Friday, Jadestone said that, while preparing for the repair, it found a defect in water ballast tank 4S, which will now also be included in the workscope of repairs, and that it would need to shut production from the FPSO again.

"Over the past several weeks, the permanent repair to tank 2C has been developed, though delayed due to weather, manpower and logistics issues, further complicated while the facility remains in production operations.  This has resulted in an inability to simultaneously accommodate the increased number of inspection and repair crews alongside production operations.  

As a result, the company has taken the decision to temporarily shut-in production from Montara and reorganize offshore manpower on the FPSO, enabling priority and focus on maintenance and inspection crews.  This is the most practical and efficient way to complete tank repairs whilst progressing ongoing inspection and remediation to other tanks in the FPSO and to complete key remaining scheduled inspection and repair activities planned for this year," the company said.

Credit: Jadestone

It is currently anticipated that these inspection and repair activities will result in production being shut-in during the remainder of August and potentially through September 2022.  It is currently anticipated that prioritizing the activity as described by Jadestine will result in incremental costs of US$2-4 million.

Output guidance cut

As a result of the Montara shut-in, and the performance of the wider production portfolio year-to-date, Jadestone now expects that 2022 production will average between 13,000 and 14,000 boe/d. 

This compares to the announcement on June 20, 2022, which signaled that 2022 production would likely be around 15,500 boe/d, being the lower end of the previous guidance range.  

The revised 2022 production guidance reflects the company's assumption that production from its non-operated assets offshore Peninsular Malaysia will now remain shut in for the remainder of 2022, due to ongoing delays in reinstating operations.

"The company is confident that by taking this approach at Montara, the necessary work required to deliver long-term asset integrity can be safely and efficiently completed.  The impact is short-term and there is no reduction in reserves.  As a result, and given its strong balance sheet, the company intends to continue the share buy-back program announced on August 2, 2022," Jadestone said.


Categories: Energy Activity FPSO Production Asia Floating Production Australia/NZ

Related Stories

Into the Deep: Offshore Production Increasingly Finds Deeper Waters

Sapura Energy Lands $1.8B Petrobras Deal for Six Pipelaying Vessels and Subsea Services

BP Suspends Production at Azerbaijani Platform for Maintenance Works

BP Starts Oil Production at Major New Platform Offshore Azerbaijan

Russian Oil Companies Told to Boost Fuel Supply to Domestic Market

Seatrium Scoops $259M Worth of Repairs and Upgrades Work

Japan’s Mitsubishi Invests in EIG’s LNG Unit MidOcean Energy

CNOOC Finds Oil in South China Sea Deepwater Field

Turkish Oil Terminal Halts Russian Oil Business

Equinor Pens 15-Year LNG Supply Deal with Indian Firm

Current News

Optimizing Cathodic Protection Survey Using Non-contact Sensors

Into the Deep: Offshore Production Increasingly Finds Deeper Waters

Odfjell Technology Boosts Asia Pacific Presence with New Contracts in Malaysia

Sapura Energy Lands $1.8B Petrobras Deal for Six Pipelaying Vessels and Subsea Services

CNOOC Starts Production at Gas Field in Bohai Sea

Shell In Talks to Sell Malaysia Fuel Stations to Saudi Aramco

Unique Group Acquires Subsea Innovation

ConocoPhillips Misses Quarterly Profit Estimates

Taliban Plan Regional Energy Trade Hub with Russian Oil in Mind

Russia Shipping Oil to North Korea Above UN Mandated Levels

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com