Taiwan: Works Resume on Yunlin Offshore Wind Farm Construction

Friday, April 29, 2022

Following the winter break, works have restarted on the construction of the Yunlin offshore wind farm in Taiwan.

The UAE-based National Petroleum Construction Company (NPCC) will bring the heavy lift vessel DLS 4200 as their fleet’s flagship from Abu Dhabi into Taiwanese waters for the work. Havfram will provide additional Project Management and Owners Engineer Services within the foundation (monopile) installation package.

To remind, the previous monopile installation contractor, Malaysian company Sapura Energy in February issued a termination notice to Yunneng Wind Power in relation to a contract for the transportation and installation of monopiles at the Yunlin offshore wind farm in Taiwan, over an alleged breach of contract.

"While the monopile installation is starting up again, the other main subcontractors such as turbine manufacturer Siemens Gamesa Renewable  Energy (SGRE), Seaway 7 as the company responsible for the cable work,  Jumbo as the installation company for the transition pieces (TP) are preparing for the construction activities to continue soon. Boskalis as the contractor for scour protection and the subsea earthworks has already commenced with its works," Yunneng said.

The Yunlin offshore wind project will have 80 turbines of 8 MW each and a  total capacity of 640 megawatts MW when completed. This will produce  2.4 terawatt-hours TWh of electricity per year, which is enough to power 605,000 households. 

"The project makes an important contribution to achieving the Taiwanese government's goal of increasing the share of renewable energy in the energy mix by 2025," Yunneng said.

"During the winter break, Yunneng focused their efforts on completing the remainder of the installation campaign taking into account many challenges encountered which were overcome through the efforts of all parties concerned. This has led to Yunneng’s confidence in seeing steady progress in 2022," said Yunneng’s chairperson Yuni Wang. "Thanks  to our project management team and our reliable partners, we will  successfully bring the Yunlin project towards completion." 


 

Categories: Energy Renewable Energy Industry News Offshore Wind Activity Asia

Related Stories

Indonesia’s Mako Gas Project on Track for First Gas in 2027

UAE Exit Weakens OPEC, Raises Risk of Price War

Technology as Enabler of Energy Security in Offshore Asia

Middle East Conflict Jolts Offshore Drilling Market

Pertamina Unit to Operate Indonesia’s Lavender Block under 30-Year PSC

Metropolitan CCS Cleared to Drill CO2 Storage Wells off Japan

Saipem Bags $400M in Offshore Contracts from Aramco in Saudi Arabia

China Calls for De-Escalation as US Threatens Hormuz Blockade

Oil Surges Over 7% to Above $102 Ahead of US Hormuz Blockade

UK Declines to Support US Hormuz Blockade, PM Starmer Says

Current News

Vessel Sector Deep Dive: WTIVs

Indonesia’s Mako Gas Project on Track for First Gas in 2027

CNOOC’s First Quarter Profit Rises on Higher Oil Prices, Output

UAE Exit Weakens OPEC, Raises Risk of Price War

United Arab Emirates Exits OPEC and OPEC+

Technology as Enabler of Energy Security in Offshore Asia

Saipem Poised for Middle East Repair Work After Iran War

Middle East Conflict Jolts Offshore Drilling Market

Bureau Veritas Expands Offshore Services with New Asia Hub

Valeura Charters Shelf Drilling’s Jack-Up Rig for Gulf of Thailand Ops

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com