Pluto Gas Processing Starts at Australia's North West Shelf, Woodside Says

OEDigital
Thursday, March 31, 2022

Australian oil and gas company Woodside said Wednesday that the processing of gas from the offshore Pluto fields in W. Australia had started ahead of schedule at the North West Shelf Project’s (NWS) Karratha Gas Plant (KGP). 

"This accelerated production of Pluto gas has been enabled by the start-up of the Pluto-KGP Interconnector," Woodside said.

The Interconnector is a 3.2-kilometer pipeline that connects Pluto LNG with KGP, providing access for other resource owners’ gas to be processed at KGP. 

Woodside said that the start-up of the Interconnector supported the accelerated production of gas from the first phase of Pluto’s Pyxis Hub by enabling it to be processed at KGP. Ready for start-up was achieved for the first phase of Pyxis Hub in October 2021. 

KGP is expected to process approximately 2.5 million tonnes of LNG in aggregate and approximately 20 petajoules of domestic gas from Pluto in the period 2022 to 2025. This follows the exercise by Woodside Burrup Pty Ltd of a contract reduction option under the gas processing agreement it entered into with the NWS Project participants in December 2020. 

Woodside CEO Meg O’Neill said:“The start-up of the Pluto-KGP Interconnector provides access to spare capacity at Karratha Gas Plant to process gas owned by other resource owners, both onshore and offshore Western Australia."

“The processing of gas from the offshore Pluto fields through Karratha Gas Plant enables Woodside to deliver additional LNG cargoes into the international gas market. The commercial agreements underpinning third-party gas processing at the North West Shelf reflect the commitment of Woodside and the North West Shelf Project to maximising value from the significant infrastructure on the Burrup Peninsula,” she said. 

The NWS Project partnes are Woodside Energy Ltd (Operator; 16.67%); BHP Petroleum (North West Shelf) Pty Ltd (16.67%); BP Developments Australia Pty Ltd (16.67%); Chevron Australia Pty Ltd (16.67%); Japan Australia LNG (MIMI) Pty Ltd (16.67%) and Shell Australia Pty Ltd (16.67%). Woodside Burrup Pty Ltd holds a 90% interest in Pluto LNG and operates the Pluto LNG facilities. The Pluto-KGP Interconnector pipeline was constructed and is operated by AGI Operations Pty Limited.

Categories: Energy Pipelines Activity Production Gas Australia/NZ

Related Stories

Lloyd’s Register Approves Wison’s Internal Turret FPSO Concept

Gulf Marine Services Profit Plunges After Gulf Vessel Evacuations

Eni Advances Giant Indonesia Gas Discovery after ‘Exceptional’ Well Test

ADNOC Drilling Finalizes MB Petroleum JV, Expands Regional Fleet

Indonesia’s Mako Gas Project on Track for First Gas in 2027

UAE Exit Weakens OPEC, Raises Risk of Price War

United Arab Emirates Exits OPEC and OPEC+

US-Israel War on Iran Creates Biggest Energy Crisis in History

MidEast Energy Output Recovery to Take Two Years, IEA Says

Offshore Vietnam: Energy Imports Rise as Domestic Production Falls

Current News

Lloyd’s Register Approves Wison’s Internal Turret FPSO Concept

Gulf Marine Services Profit Plunges After Gulf Vessel Evacuations

Eni Advances Giant Indonesia Gas Discovery after ‘Exceptional’ Well Test

IEA: Middle East Conflict Reshaping Medium-Term Gas Outlook

ADNOC Drilling Finalizes MB Petroleum JV, Expands Regional Fleet

Brent Near $114 as Middle East Conflict Continues

Thailand Cancels Offshore Energy Exploration Pact with Cambodia

Vessel Sector Deep Dive: WTIVs

Indonesia’s Mako Gas Project on Track for First Gas in 2027

CNOOC’s First Quarter Profit Rises on Higher Oil Prices, Output

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com