Pluto Gas Processing Starts at Australia's North West Shelf, Woodside Says

OEDigital
Thursday, March 31, 2022

Australian oil and gas company Woodside said Wednesday that the processing of gas from the offshore Pluto fields in W. Australia had started ahead of schedule at the North West Shelf Project’s (NWS) Karratha Gas Plant (KGP). 

"This accelerated production of Pluto gas has been enabled by the start-up of the Pluto-KGP Interconnector," Woodside said.

The Interconnector is a 3.2-kilometer pipeline that connects Pluto LNG with KGP, providing access for other resource owners’ gas to be processed at KGP. 

Woodside said that the start-up of the Interconnector supported the accelerated production of gas from the first phase of Pluto’s Pyxis Hub by enabling it to be processed at KGP. Ready for start-up was achieved for the first phase of Pyxis Hub in October 2021. 

KGP is expected to process approximately 2.5 million tonnes of LNG in aggregate and approximately 20 petajoules of domestic gas from Pluto in the period 2022 to 2025. This follows the exercise by Woodside Burrup Pty Ltd of a contract reduction option under the gas processing agreement it entered into with the NWS Project participants in December 2020. 

Woodside CEO Meg O’Neill said:“The start-up of the Pluto-KGP Interconnector provides access to spare capacity at Karratha Gas Plant to process gas owned by other resource owners, both onshore and offshore Western Australia."

“The processing of gas from the offshore Pluto fields through Karratha Gas Plant enables Woodside to deliver additional LNG cargoes into the international gas market. The commercial agreements underpinning third-party gas processing at the North West Shelf reflect the commitment of Woodside and the North West Shelf Project to maximising value from the significant infrastructure on the Burrup Peninsula,” she said. 

The NWS Project partnes are Woodside Energy Ltd (Operator; 16.67%); BHP Petroleum (North West Shelf) Pty Ltd (16.67%); BP Developments Australia Pty Ltd (16.67%); Chevron Australia Pty Ltd (16.67%); Japan Australia LNG (MIMI) Pty Ltd (16.67%) and Shell Australia Pty Ltd (16.67%). Woodside Burrup Pty Ltd holds a 90% interest in Pluto LNG and operates the Pluto LNG facilities. The Pluto-KGP Interconnector pipeline was constructed and is operated by AGI Operations Pty Limited.

Categories: Energy Pipelines Activity Production Gas Australia/NZ

Related Stories

SED Energy’s GHTH Rig Kicks Off Ops for PTTEP

MODEC Forms Dedicated Mooring Solutions Unit

Petrobras’ New FPSO Sets Sail From South Korea to Brazil's Santos Basin

Eneos Warns on Skyrocketing Costs fo Offshore Wind

Mooreast to Assess Feasibility of Floating Renewables Push in Timor-Leste

Malaysia Issues First Offshore CCS Permit to Petronas Subsidiary

Sponsored: Energy and Finance Chiefs Call for Sound Policy, Stable Frameworks at ADIPEC

CNOOC Brings Online Another Oil and Gas Project in South China Sea

Norwegian Oil Investment Will Peak in '25

Saipem Wins FEED Contract For Abadi LNG Project FPSO Module In Indonesia

Current News

Blackford Dolphin Semi-Sub to Keep Drilling Offshore India

Aramco Expands US Partnerships with $30B in New Deals

Pakistan Greenlights TPOC-Led Offshore Exploration in Block-C

TechnipFMC to Supply Subsea Systems for Eni’s Maha Deepwater Project

SED Energy’s GHTH Rig Kicks Off Ops for PTTEP

MODEC Forms Dedicated Mooring Solutions Unit

Seatrium Maintains $12.8B Order Book on Renewables and FPSO Progress

Petrobras’ New FPSO Sets Sail From South Korea to Brazil's Santos Basin

Eneos Warns on Skyrocketing Costs fo Offshore Wind

Mooreast to Assess Feasibility of Floating Renewables Push in Timor-Leste

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com