Carnarvon Faces Another Buffalo Drilling Start-up Delay

Monday, December 13, 2021

Australian oil and gas firm Carnarvon Energy expects to spud its Buffalo-10 well in the Timor Sea in late December and not in mid-December as previously expected.

The company said Monday that the Valaris JU-107 jack-up drilling rig was "still on its current operations, and the handover of the rig to Carnarvon is now expected to be in late December."

"The delays are not related to the performance of the rig or preparation by Carnarvon. The current operator of the rig is undertaking its final operation, after which the rig will be handed over to Carnarvon," the company said.

To remind, Carnarvon in September said it expected to spud the Buffalo-10 well in the Timor Sea in early November.

According to Valaris' October fleet status report, the rig is on a contract with Jadestone. 


The Buffalo project involves the redevelopment of the Buffalo oil field in the Timor Sea. The field resides in only 30 meters of water with a reservoir depth between 3,200 and 3,300 meters below the sea bed. The previous field proved the existence of a very high deliverability reservoir containing high-quality light oil that is expected to sell at a premium to Brent in today’s market, Carnarvon explained.

Carnarvon, as the operator of the project, is preparing to drill a well that will penetrate the existing oil column (because the field was still producing when it was shut-in in 2004), and assess the extent of the revised mapped attic oil column.

Carnarvon’s mid-case recoverable volume estimate is 31 million barrels (gross, 2C contingent resource). With the minimum economic field size estimated to be significantly lower than the mid-case estimate, there is a strong likelihood the Buffalo-10 well will confirm an economic project, Carnarvon said.

Accordingly, Carnarvon’s drilling plans provide for the Buffalo-10 well to be retained as the first production well in the redevelopment program.  

Carnarvon also said it was working with its project partner, Advance Energy Plc, on plans to compress the timeline to first production once the Buffalo-10 well confirms a commercial oil resource. These plans include engaging with the industry for the supply and installation of suitable equipment to produce the oil.
 

Categories: Drilling Activity Australia/NZ Shallow Water

Related Stories

Keppel Reclaiming Control of 13 Rigs to Cash In on Offshore Drilling Market's Growth

Blackford Dolphin Kicks Off Long-Term Drilling Campaign Offshore India

CNOOC Kicks Off Production from Bohai Bay Field

Eni Strengthens LNG Ties with Japan

MCDermott Gets Pipelines and Cables Job at Qatar's Giant Gas Field

India Opts Out of Buying Gas from Russia's Sanctioned Arctic LNG 2 Project

CNOOC Starts Production from Deepwater Gas Project in South China Sea

Santos Pens Mid-Term LNG Supply Deal

Equinor Picks SHI as Preferred Supplier for Korean 750 MW Floating Wind Project

Borr Drilling Scoops $332M in Three Jack-Up Rig Contracts

Current News

Velesto Completes Removal of Wrecked Naga 7 Jack-Up Rig Off Malaysia

BP Greenlights $7B CCUS Scheme Tied to Indonesia LNG Facility

Sapura Scoops Petrobras Contract for Pan-Malaysia Offshore Services

Velesto’s Drilling Rigs Up for Automatization Overhaul Under New Tech Alliance

US Firm Finds Chinese Partner to Deliver Mobile Offshore Drilling Units

TotalEnergies and Oil India to Jointly Tackle Methane Emissions Issues

Keppel Reclaiming Control of 13 Rigs to Cash In on Offshore Drilling Market's Growth

Global Offshore Wind Stumbles to the End of '24

Seatrium Delivers Fifth Jack-Up to Borr Drilling

Malaysia's FPSO Firm Bumi Armada Eyes Merger with MISC’s Offshore Unit

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com