Carnarvon Faces Another Buffalo Drilling Start-up Delay

Monday, December 13, 2021

Australian oil and gas firm Carnarvon Energy expects to spud its Buffalo-10 well in the Timor Sea in late December and not in mid-December as previously expected.

The company said Monday that the Valaris JU-107 jack-up drilling rig was "still on its current operations, and the handover of the rig to Carnarvon is now expected to be in late December."

"The delays are not related to the performance of the rig or preparation by Carnarvon. The current operator of the rig is undertaking its final operation, after which the rig will be handed over to Carnarvon," the company said.

To remind, Carnarvon in September said it expected to spud the Buffalo-10 well in the Timor Sea in early November.

According to Valaris' October fleet status report, the rig is on a contract with Jadestone. 


The Buffalo project involves the redevelopment of the Buffalo oil field in the Timor Sea. The field resides in only 30 meters of water with a reservoir depth between 3,200 and 3,300 meters below the sea bed. The previous field proved the existence of a very high deliverability reservoir containing high-quality light oil that is expected to sell at a premium to Brent in today’s market, Carnarvon explained.

Carnarvon, as the operator of the project, is preparing to drill a well that will penetrate the existing oil column (because the field was still producing when it was shut-in in 2004), and assess the extent of the revised mapped attic oil column.

Carnarvon’s mid-case recoverable volume estimate is 31 million barrels (gross, 2C contingent resource). With the minimum economic field size estimated to be significantly lower than the mid-case estimate, there is a strong likelihood the Buffalo-10 well will confirm an economic project, Carnarvon said.

Accordingly, Carnarvon’s drilling plans provide for the Buffalo-10 well to be retained as the first production well in the redevelopment program.  

Carnarvon also said it was working with its project partner, Advance Energy Plc, on plans to compress the timeline to first production once the Buffalo-10 well confirms a commercial oil resource. These plans include engaging with the industry for the supply and installation of suitable equipment to produce the oil.
 

Categories: Drilling Activity Australia/NZ Shallow Water

Related Stories

ADES Expects Up to 44% Earnings Rise Despite Regional Tensions Impacting Rigs

Velesto Inks Five-Year Drilling Deal for Jack-Up Rig with Petronas

Velesto Lands Jack-Up Drilling Deal with Jadestone off Malaysia

Seatrium Targets $40M Cost Savings in Continued Divestment Drive

Dolphin Drilling, Vantris Ink Marketing Deal for Blackford Dolphin Semi-Sub

MISC, PTSC Extend Ruby II FPSO Operations Offshore Vietnam

Vantage Drilling’s Ultra-Deepwater Drillship Heads to India Under $260M Contract

Australia and Timor-Leste Push to Advance Greater Sunrise Gas Field

JERA Lifts First LNG Cargo From Barossa Gas Project in Australia

Philippines Makes First Offshore Gas Discovery in Over a Decade

Current News

Eni Exits Consortium for Oil and Gas Exploration Offshore Israel

Big Oil to Reap Billions from Energy Price Surge

UAE Stands Ready to Join Force to Reopen Strait of Hormuz

Asian Buyers Rush for Russian Oil Amid Supply Disruption

Mubadala Energy Secures Southwest Andaman Exploration Block off Indonesia

Strohm to Supply Insulated TCP Jumpers for Malaysia’s Offshore Project

Arabian Drilling Flags Temporary Offshore Rig Suspensions in Persian Gulf

Iran War Sends LNG Prices Soaring, Curbing Asia Demand

Rising Costs of War: Gulf Energy Infrastructure Stares Down $25B Repair Bill

ADES Expects Up to 44% Earnings Rise Despite Regional Tensions Impacting Rigs

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com