Carnarvon Faces Another Buffalo Drilling Start-up Delay

Monday, December 13, 2021

Australian oil and gas firm Carnarvon Energy expects to spud its Buffalo-10 well in the Timor Sea in late December and not in mid-December as previously expected.

The company said Monday that the Valaris JU-107 jack-up drilling rig was "still on its current operations, and the handover of the rig to Carnarvon is now expected to be in late December."

"The delays are not related to the performance of the rig or preparation by Carnarvon. The current operator of the rig is undertaking its final operation, after which the rig will be handed over to Carnarvon," the company said.

To remind, Carnarvon in September said it expected to spud the Buffalo-10 well in the Timor Sea in early November.

According to Valaris' October fleet status report, the rig is on a contract with Jadestone. 


The Buffalo project involves the redevelopment of the Buffalo oil field in the Timor Sea. The field resides in only 30 meters of water with a reservoir depth between 3,200 and 3,300 meters below the sea bed. The previous field proved the existence of a very high deliverability reservoir containing high-quality light oil that is expected to sell at a premium to Brent in today’s market, Carnarvon explained.

Carnarvon, as the operator of the project, is preparing to drill a well that will penetrate the existing oil column (because the field was still producing when it was shut-in in 2004), and assess the extent of the revised mapped attic oil column.

Carnarvon’s mid-case recoverable volume estimate is 31 million barrels (gross, 2C contingent resource). With the minimum economic field size estimated to be significantly lower than the mid-case estimate, there is a strong likelihood the Buffalo-10 well will confirm an economic project, Carnarvon said.

Accordingly, Carnarvon’s drilling plans provide for the Buffalo-10 well to be retained as the first production well in the redevelopment program.  

Carnarvon also said it was working with its project partner, Advance Energy Plc, on plans to compress the timeline to first production once the Buffalo-10 well confirms a commercial oil resource. These plans include engaging with the industry for the supply and installation of suitable equipment to produce the oil.
 

Categories: Drilling Activity Australia/NZ Shallow Water

Related Stories

Major Oil and Gas Projects Drive Strong OSV Demand in the Middle East

Energy Drilling’s EDrill-2 Rig Starts Ops for PTTEP in Gulf of Thailand

Ventura Offshore’s Semi-Sub Rig to Keep Drilling for Eni in Asia

SBM Offshore, SLB to Optimize FPSO Performance Using AI

Timor Gap Boosts Stake in Finder Energy’s Timor-Leste Oil Fields

Hibiscus Petroleum Starts Drilling at Teal West Field off UK

DOF Secures Moorings Hook-Up Job in Asia Pacific

Marco Polo Picks Salt Ship Design for Next-Gen Offshore Energy CSOV

Saipem Wins FEED Contract For Abadi LNG Project FPSO Module In Indonesia

One Shelf Drilling Rig Up for New Job in India, Other for Disposal

Current News

Eneos Warns on Skyrocketing Costs fo Offshore Wind

Mooreast to Assess Feasibility of Floating Renewables Push in Timor-Leste

Malaysia Issues First Offshore CCS Permit to Petronas Subsidiary

Sponsored: Record Deals and Record Attendance Underscore ADIPEC’s Global Impact

Sponsored: Energy and Finance Chiefs Call for Sound Policy, Stable Frameworks at ADIPEC

Sponsored: Energy Sector Urged to Scale AI Adoption at ADIPEC

Sponsored: Policy, AI, and Capital Take Center Stage at ADIPEC 2025

Major Oil and Gas Projects Drive Strong OSV Demand in the Middle East

ABL to Support Platform Installations, Rig Moves for Chevron in Gulf of Thailand

PTTEP Orders OneSubsea Systems for Two Deepwater Projects off Malaysia

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com