Chevron, Partners to Fork Out for Carbon Offsets for Gorgon LNG Carbon Capture Shortfall

Sonali Paul
Friday, November 12, 2021

Chevron Corp and its partners in the Gorgon liquefied natural gas (LNG) project in Western Australia have agreed to buy carbon credits likely to cost more than $180 million as a penalty for failing to meet a five-year target for carbon capture and storage (CCS).

The costs, which could amount to well over A$250 million ($184 million) based on Reuters calculations, will be shared with its Gorgon LNG partners - Exxon Mobil Corp, Royal Dutch Shell, and Japan's Osaka Gas, Tokyo Gas and JERA.

The A$3.1 billion Gorgon CCS project, the world's largest commercial CCS project, is being penalized by the Western Australian government for injecting far less carbon dioxide than planned since the LNG plant started up five years ago.

Chevron said in a statement that it would invest A$40 million in "lower-carbon projects" and would buy and surrender 5.23 million greenhouse gas offsets to fulfill the Gorgon project's obligations to the state government, ideally by mid-July 2022.

"The package we have announced ... ensures we meet the expectations of the regulator, the community and those we place on ourselves as a leading energy producer in Australia," Chevron Australia Managing Director Mark Hatfield said in a statement.

Gorgon project - Credit: Chevron (File image)

Based on the current price of carbon offsets on the voluntary Australian spot market, which last week hit a record high of A$37 a tonne, 5.23 million offsets would cost at least A$195 million.

Amid short supply of Australian Carbon Credit Units (ACCUs), Chevron is unlikely to meet its obligation just with those offsets and said in a report to the government it would also use other internationally verified carbon units and offsets.

Gorgon CCS was designed to inject up to 4 million tonnes a year of CO2. Since starting injecting CO2 in August 2019, three years later than scheduled, it has injected a total of about 5.5 million tonnes of CO2-equivalent.

The project was delayed by three years due to a range of technical problems.

($1 = 1.3563 Australian dollars) 

(Reporting by Sonali Paul; additional reporting by Sameer Manekar in Bengaluru; Editing by Ramakrishnan M. and Kenneth Maxwell)

Categories: Energy Activity Australia/NZ Decarbonization CCUS CCS

Related Stories

MODEC and Samsung Team Up to Install Carbon Capture Tech on FPSO

Santos Hires Weststar-GAP for Timor-Leste Offshore Helicopter Services

Sunda Energy Starts Environmental Survey for Timor-Leste Oil and Gas Field

Kazakhstan Looks to Improve Oil Production Agreements Terms

China's CNOOC Aims for Record Oil and Gas Production in 2025

CNOOC’s South China Sea Oil Field Goes On Stream

ADES’ Fourth Suspended Jack-Up Rig Gets Work Offshore Thailand

Saipem’s Castorone Vessel on Its Way to Türkiye’s Largest Gas Field

AI & Offshore Energy: The Higher the Stakes, the More Value AI Creates

Floating LNG Conversion Job Slips Out of Seatrium’s Hands

Current News

Mitigate SCC & HE to Keep Offshore Metal Structures Ship Shape

India Stretches Bids Deadline for 13 Offshore Deep-Sea Mineral Blocks

Indonesia Awards Oil and Gas Blocks to Boost Reserves

Sapura Energy Nets $22.6M in Offshore Support Vessel Contracts

CNOOC Puts Into Production New Oil Field in South China Sea

Sunda Energy Starts Environmental Consultation for Chuditch-2 Well Drilling Plans

Pakistan’s OGDC to Start Production at ADNOC’s Offshore Block by 2027

Petrovietnam, Petronas Extend PSC for Offshore Block

Sapura Energy Scoops Close to $9M for O&M Work off Malaysia

Hanwha Ocean Marks Entry into Deepwater Drilling Market with First Drillship

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com