Carnarvon: Buffalo Drilling Rig Tender Nears Completion. Spud Date Set for Q4

Bartolomej Tomic
Tuesday, May 11, 2021

The tender process for an offshore drilling rig to be used for the drilling of Carnarvon Petroleum's and Advance Energy's Buffalo offshore well in the Timor Sea is nearing completion, and the spud date is scheduled for the fourth quarter of 2021, the companies said Tuesday.

Advance Energy recently paid US$20 million to acquire a 50% interest in the Buffalo PSC. The cash will be utilized for the drilling of the shallow water Buffalo-10 well offshore Timor-Leste.  This also means the drilling will be at no cost to Carnarvon unless the well costs more than US$20m.

Carnarvon said Tuesday that Petrofac, the oilfield services company hired to manage the Buffalo well's drilling, had identified the long-lead equipment needed to ensure the Buffalo-10 well can be drilled before the end of 2021.

The procurement of long-lead equipment has started, with orders placed for the supply of conductor pipe, wellhead, liner hanger, and related services. This long-lead equipment is planned to be available before the end of the third quarter of 2021. 

"A tender process for the drilling rig is nearing completion, with the requirement for a suitable jack-up rig to be available in the fourth quarter of this year," Carnarvon said.

Carnarvon has also begun the process of obtaining the requisite government approvals in Timor-Leste for the well drilling.

Carnarvon Managing Director and CEO,  Adrian Cook, said: “I’m pleased to be able to report that the Carnarvon and Petrofac teams are making clear progress in our preparations to drill the Buffalo-10 well this year. 

"A drilling result that meets pre-drill expectations will provide a material value catalyst for Carnarvon and its partner, particularly given the low capital and operating costs per barrel that are expected to arise from production operations." 

"The nature of the field, particularly in terms of it being in shallow water, also enables a development facility to be installed in a timeframe that has the potential to result in the generation of earnings and cash flows well ahead of that arising from our larger Dorado development. The consequence of these outcomes is important in terms of its value generation and strategic optionality for the company.”

Carnarvon recently said it was targeting the FID for Buffalo in 2022 with the first oil targeted for late 2023.

Credit: Carnarvon Petroleum

Buffalo background

Carnarvon was awarded the WA-523-P permit, which included the previously developed Buffalo field, in May 2016 for an initial six-year term. The field was discovered by BHP in 1996 and subsequently developed using four wells drilled from a small, unmanned wellhead platform installed in 25 meters water depth, tied back to an FPSO. 

Production started in December 1999 at production rates up to approximately 50,000 stb/d and terminated in November 2004 after the production of 20.5 MMstb of highly-undersaturated, light oil (53°API) from the Jurassic-age Elang Formation. All existing facilities and wells were decommissioned and removed prior to Carnarvon being awarded the permit.  

Carnarvon initially focused its technical efforts on reprocessing the 3D seismic dataset using full-waveform inversion (FWI) technology. 

"This work supports the interpretation of a significant attic oil accumulation remaining after the original development, based on sub-optimal positioning of early wells using poorly processed seismic data. Reservoir modeling has been conducted using the latest structural interpretation and available well data, including an extensive history-matching effort to calibrate model/well performance to production rates and water-cut development (governed by strong aquifer drive) observed during the original production period," the company said previously.

Per Carnarvon, independently audited volumetric estimates of contingent resources in the Buffalo oil field are 31.1 million barrels (2C) with low estimates of 15.3 million barrels (1C) and high estimates of 47.8 million barrels (3C).

The Buffalo project was originally situated in Australian waters, but in 2018, the Australian and Timor-Leste governments signed a maritime boundary agreement that changed the maritime boundary between the two countries, affecting the WA-523-P permit that contains the Buffalo project.

The WA-523-P exploration permit has been split in two with a portion containing the Buffalo oil field changing from its Australian jurisdiction to being exclusively in the East Timor jurisdiction.

According to Advance Energy's previous statements, Buffalo PSC has the potential to deliver production of 40,000 bopd within three years of the B-10 Appraisal Well depending on the degree of success of the drilling of the well.

This was reiterated Monday by Advance Energy's CEO Leslie Peterkin: "The drilling of this well is transformational to Advance Energy, representing a material value catalyst for the company and our shareholders. In the success case,  there is potential to deliver a gross production rate of around 40,000 barrels per day by the end of 2023, which in this current pricing environment would deliver exceptionally strong cash flow and compelling rates of return." 

 "We are very excited for what the next six months may bring and will continue to provide updates to the market as we approach the various milestones of drilling activity on the Buffalo-10 well." 

Categories: Drilling Industry News Activity Rigs Australia/NZ Shallow Water

Related Stories

CNOOC Makes Ultra-Deep Gas Discovery in China's Bohai Sea

ADES Lands $117M ONGC Drilling Contracts for Two Jack-Ups

Strohm Nets Ultra-Deepwater Supply Deal for Southeast Asia’s Gas Scheme

Oil India Discovers Gas in Shallow Waters of Krishna-Godavari Basin

Masirah Oil Starts Yumna Offshore Drilling Ops After Months of Delays

Inpex-Led Bonaparte CCS Project Gets Australian Offshore Storage Approval

Jack-Up Rig Arrives in Indonesia for Conrad Asia Energy's MOPU Conversion

Murphy Oil Finds More Oil Offshore Vietnam, Côte d'Ivoire

Solstad Maritime Secures APAC Drilling Support Work for AHTS Pair

SBM Offshore Taps Chinese Contractor for FPSO Topside Modules

Current News

China’s COOEC Lands $800M QatarEnergy Subsea Contract

Oil Prices Rise as Houthi Strikes Revive Supply Disruption Fears

COSL Places $1.64B Order for 59 Offshore Support Vessels

When Contractors Collide: Keeping Offshore Energy Projects on Schedule

Floating Production Outlook: Pipeline Looks Huge, But Not All Projects Are Created Equal

Shell Brings Deepwater Gas Fields Onstream off Malaysia

Hanwha Power Secures FSRU Conversion Deal with Energos

Orlen's Termination of Qatar LNG Deal Could Yield $2B in Savings

Oil Heads for Weekly Decline Despite Middle East Supply Threats

Inpex Raises Profit Forecast on Strong Ichthys LNG Production

Magazine

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com