First Topside Module Lifted on Coral South FLNG Hull

Wednesday, May 27, 2020

Eni-operated Coral South FLNG project is making progress with the first topside module installed aboard the hull of the under-construction FLNG unit destined to develop offshore gas fields in Area 4 of the Rovuma Basin, Mozambique.

Coral FLNG SA, an Eni-led JV developing the project, said Wednesday that the power generation module had been lifted aboard the hull, marking the start of the integration between the hull, launched in January, and the massive topside (12 process modules of around 70,000 tons), both currently under construction in South Korea.

"The construction of the FLNG facility, which is primarily carried out at Samsung Heavy Industry in South Korea with 7 main operating centers worldwide and a global supply chain, is progressing well aiming towards the commencement of production in 2022," Coral FLNG said.

The Coral South FLNG, a floating facility for the processing, liquefaction, and storage of gas, will be moored approximately 50 kilometers offshore of the Palma bay in the northern province of Cabo Delgado, Mozambique. Partners in the Coral FLNG SA are Eni, ExxonMobil, CNODC, ENH, Galp, and Kogas.

The 432 meters long FLNG unit will have a gas liquefaction capacity of 3.4 million tons per year (MTPA), and it will be the first FLNG ever deployed in deep waters, at a water depth of approximately 2,000 meters. While not the first operational FLNG unit in Africa, the unit will be the first purpose-build FLNG in Africa.

Namely, Cameroon was the first African nation to bring online an FLNG unit (in 2018), however, the vessel was converted from the 1975-built Moss LNG carrier and not purpose-built.

<




Caption; Topside module lifting - Credit: Coral FLNG
Categories: Offshore Energy Activity Production Floating Production

Related Stories

James Fisher, Aquaterra Launch Global Decommissioning Partnership

Hormuz Standoff Risks Chronic Instability for Gulf Oil Flows

From Fixtures to Values: Where the Jackup Recovery Is Already Being Priced

MODEC Advances Construction of Brazil-Bound Gato do Mato FPSO

TGS Gets Exclusive Rights for Seismic Survey Offshore Brunei

Floating Nuclear: A New Offshore Energy Frontier

Yinson Production Names FSO for Murphy's Lac Da Vang Project off Vietnam

Oman Opens Alternative Hormuz Lanes as Shipping Recovery Continues

Oil Falls as Signs of Hormuz Recovery Weigh on Market

BP Launches Gas Production at Azerbaijan’s Giant ACG Field

Current News

Velesto Terminates NAGA 3 Jack-Up Rig Sale to Indonesian Firm

Noble Gets $136M Brunei Drillship Job

James Fisher, Aquaterra Launch Global Decommissioning Partnership

Tetragon Energy Advances Oil and Gas Exploration Activities off Philippines

Arabian Drilling Set to Resume Ops with Three Offshore Rigs

Oil Jumps 3% on Renewed US-Iran Conflict

Hormuz Traffic Falls to Five-Week Low as Tensions Escalate

Eni Enlists OneSubsea for Deepwater Umbilical Supply off Indonesia

EnQuest Clears Key Hurdle for $833M Malaysia Offshore Deal

ONGC Plans Major New Indian Oil Reserve

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com