First Topside Module Lifted on Coral South FLNG Hull

Wednesday, May 27, 2020

Eni-operated Coral South FLNG project is making progress with the first topside module installed aboard the hull of the under-construction FLNG unit destined to develop offshore gas fields in Area 4 of the Rovuma Basin, Mozambique.

Coral FLNG SA, an Eni-led JV developing the project, said Wednesday that the power generation module had been lifted aboard the hull, marking the start of the integration between the hull, launched in January, and the massive topside (12 process modules of around 70,000 tons), both currently under construction in South Korea.

"The construction of the FLNG facility, which is primarily carried out at Samsung Heavy Industry in South Korea with 7 main operating centers worldwide and a global supply chain, is progressing well aiming towards the commencement of production in 2022," Coral FLNG said.

The Coral South FLNG, a floating facility for the processing, liquefaction, and storage of gas, will be moored approximately 50 kilometers offshore of the Palma bay in the northern province of Cabo Delgado, Mozambique. Partners in the Coral FLNG SA are Eni, ExxonMobil, CNODC, ENH, Galp, and Kogas.

The 432 meters long FLNG unit will have a gas liquefaction capacity of 3.4 million tons per year (MTPA), and it will be the first FLNG ever deployed in deep waters, at a water depth of approximately 2,000 meters. While not the first operational FLNG unit in Africa, the unit will be the first purpose-build FLNG in Africa.

Namely, Cameroon was the first African nation to bring online an FLNG unit (in 2018), however, the vessel was converted from the 1975-built Moss LNG carrier and not purpose-built.

<




Caption; Topside module lifting - Credit: Coral FLNG
Categories: Offshore Energy Activity Production Floating Production

Related Stories

Jereh Group Delivers Oil Separation Systems for Petrobras’ FPSO Units

Low Demand, High Supply Keeps Asia LNG Spot Prices Flat

India Seeks $30B from Reliance, BP Over Gas Shortfall at Offshore Fields

Saipem Nets Multibillion-Dollar Job at World's Largest Offshore Gas Field

ADES Nets $63M Contract for Compact Driller Jack-Up off Brunei

Mubadala Energy, PLN Energy Primer Team Up for Andaman Sea Gas Supply

BP Hires Seatrium to Deliver Tiber FPU in Gulf of America

Major Oil and Gas Projects Drive Strong OSV Demand in the Middle East

Eni-Petronas Gas Joint Venture Up for Launch in 2026

Synergy Marine Group Completes Conversion of LNG Vessel to FSRU

Current News

Jereh Group Delivers Oil Separation Systems for Petrobras’ FPSO Units

Offshore Rig Outlook: As 2025 Challenges Fade, Path Ahead Brightens

Offshore Energy and Boosting the Energy Efficiency of Water Processes

Low Demand, High Supply Keeps Asia LNG Spot Prices Flat

Following Big Loss in 2025, Oil Steadies

Saipem Lands $425M Turkish Gas Contract in Sakarya Expansion

OE’s 2025 Top of the Festive Video Pops: Santa Goes Offshore

India Seeks $30B from Reliance, BP Over Gas Shortfall at Offshore Fields

PV Drilling’s Jack-Up Rig Returns to Asia Ahead of April Drilling Ops

South Korean Firm Buys Into Indonesian Offshore Oil Block

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com