TenneT, EnBW, Ørsted Pact on Transmission Concept

Laxman Pai
Monday, September 9, 2019

The European transmission system operator TenneT, German utilities company EnBW and offshore wind specialist Ørsted have formed an alliance with the aim of implementing new connection concept for offshore wind farms and converter platforms in the German North Sea.

The connection concept already planned by TenneT in the Netherlands will also be used in the future as part of selected offshore DC projects in the German North Sea. It eliminates the transformer platform for Ørsted's future offshore wind projects in Junction Cluster 1 and EnBW's future offshore wind project He Dreiht in Cluster 7, both north of Borkum.

The concept envisages a direct connection from the wind turbines via 66 kV connecting cables to the offshore converter platform of the transmission system operator TenneT.

The grid operator TenneT has agreed with the energy companies EnBW and Ørsted, respectively, that they will not connect the selected future offshore wind projects in the North Sea with 155 kV cables, but instead the wind turbines of the offshore wind farms with 66 kV connecting cables directly to the offshore converter platform.

 As a result, the construction of offshore substations (OSS) by the wind farm constructor can be avoided or reduced to the lower requirement of an offshore service platform (OSP). In addition, the export cable for the network operator is omitted.

Volker Malmen, Managing Director of Ørsted in Germany said: "Offshore wind power is still a young industry in Germany, but due to Ørsted's many years of experience, we have been able to significantly advance the cost-effectiveness of offshore wind energy within just a few years. The cost reduction and innovation potential for our industry continues to be very high."

Tim Meyerjürgens, Managing Director of TenneT, said: "This transmission concept leads to an enormous cost reduction in the wind farms and for the grid connection. With the 66 kV direct connection, we have developed a new generation of cost-efficient offshore grid connections for the German North Sea, which will make an important contribution to the energy transition. "

Categories: Wind Power Technology(Energy) Transmission/Gears Offshore Wind

Related Stories

Are North Sea Jack-Ups Set for Flat 2024?

Equinor Pens 15-Year LNG Supply Deal with Indian Firm

Marine Power R&D Insights: Matt Hart, Wabtec Corporation

Valeura Buys Nong Yao Field’s FSO Aurora and Expands Wassana Drilling Campaign

Baron Oil Schedules Site Survey at Timor-Leste Gas Field

Borr Drilling Secures $82M for Three Jack-up Rigs

BW Opal FPSO Starts Taking Final Shape Ahead of Barossa Assignment

China Puts First ‘Home-Made’ Subsea Xmas Tree Into Operation

Nebula Energy Acquires Majority Stake in AG&P LNG for $300M

QatarEnergy Signs 15-year LNG Supply Deal with Excelerate Energy

Current News

SOVs – Analyzing Current, Future Demand Drivers

Decarbonization Offshore O&G: Navigating the Path Forward

Subsea Vessel Market is Full Steam Ahead

China's Imports of Russian Oil Near Record High

TotalEnergies Inks $530M Deal to Acquire Malaysia’s SapuraOMV

Energy Storage on O&G Platforms - A Safety Boost, too?

Malampaya Gas Field Exceeds Export Capacity Amid Grid Demands in Philippines

Timor-Leste: Chuditch-2 Well to be Drilled at New Location Following Site Surveys

Akastor’s Subsidiary Wins $101M Case Against Seatrium's Jurong Shipyard

ONGC Hires Consortium to Deliver FEED Work for Bay of Bengal Oil Field

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com