The 700MW COBRAcable interconnector linking the Dutch and the Danish grid will be available for the electricity market as of delivery day, 7 September, Dutch high-voltage grid operator TenneT said.

"After three years of construction, including the laying of the submarine cables as well as the construction of two onshore converter stations, and a successful test phase earlier this year, COBRAcable will be available for the electricity market as of the delivery day of 7 September, which is exactly on schedule," it said.

The first direct connection between the electricity markets of Denmark and the Netherlands was jointly realised and is operated by the two TSCNET shareholders Energinet, the Danish transmission system operator (TSO), and TenneT, the Dutch-German TSO.

The interconnector cable runs between Eemshaven (the Netherlands) via Germany and Endrup (Denmark). Two onshore converter stations, one in the Netherlands and one in Denmark, convert alternating current into direct current. This is necessary to transport the electricity without major losses. The converters also convert direct current back into alternating current; electricity grids operate on the basis of alternating current.

Siemens is the main contractor for design and technical equipment of the converter stations in Denmark and in the Netherlands and for the construction of the converter station in Eemshaven. The cables were manufactured and installed by Prysmian.

The Netherlands can import more sustainable electricity via this interconnector cable, mainly wind energy from Denmark. Ensuring security of supply is of great importance to Denmark. The cable makes Dutch capacity available on a structural basis for the Danish electricity grid and vice versa.

Furthermore, the cable connection has been designed in such a way that it will be possible to connect an offshore wind farm at a later stage. In this way, the cable contributes to realizing a sustainable international energy landscape, an important goal of the European Union.

Categories: Subsea Cables Power Generation Connectivity

Related Stories

Lloyd’s Register Approves Wison’s Internal Turret FPSO Concept

Gulf Marine Services Profit Plunges After Gulf Vessel Evacuations

Vessel Sector Deep Dive: WTIVs

Indonesia’s Mako Gas Project on Track for First Gas in 2027

CNOOC’s First Quarter Profit Rises on Higher Oil Prices, Output

Technology as Enabler of Energy Security in Offshore Asia

Saipem Poised for Middle East Repair Work After Iran War

Oil Prices Jump as Ships Come Under Fire in Strait of Hormuz

Saipem Bags $400M in Offshore Contracts from Aramco in Saudi Arabia

Japan to Launch $10B Fund to Help Asia Secure Oil

Current News

Lloyd’s Register Approves Wison’s Internal Turret FPSO Concept

Gulf Marine Services Profit Plunges After Gulf Vessel Evacuations

Eni Advances Giant Indonesia Gas Discovery after ‘Exceptional’ Well Test

IEA: Middle East Conflict Reshaping Medium-Term Gas Outlook

ADNOC Drilling Finalizes MB Petroleum JV, Expands Regional Fleet

Brent Near $114 as Middle East Conflict Continues

Thailand Cancels Offshore Energy Exploration Pact with Cambodia

Vessel Sector Deep Dive: WTIVs

Indonesia’s Mako Gas Project on Track for First Gas in 2027

CNOOC’s First Quarter Profit Rises on Higher Oil Prices, Output

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com