COBRA Cable Readies for Action

Laxman Pai
Tuesday, September 3, 2019

The 700MW COBRAcable interconnector linking the Dutch and the Danish grid will be available for the electricity market as of delivery day, 7 September, Dutch high-voltage grid operator TenneT said.

"After three years of construction, including the laying of the submarine cables as well as the construction of two onshore converter stations, and a successful test phase earlier this year, COBRAcable will be available for the electricity market as of the delivery day of 7 September, which is exactly on schedule," it said.

The first direct connection between the electricity markets of Denmark and the Netherlands was jointly realised and is operated by the two TSCNET shareholders Energinet, the Danish transmission system operator (TSO), and TenneT, the Dutch-German TSO.

The interconnector cable runs between Eemshaven (the Netherlands) via Germany and Endrup (Denmark). Two onshore converter stations, one in the Netherlands and one in Denmark, convert alternating current into direct current. This is necessary to transport the electricity without major losses. The converters also convert direct current back into alternating current; electricity grids operate on the basis of alternating current.

Siemens is the main contractor for design and technical equipment of the converter stations in Denmark and in the Netherlands and for the construction of the converter station in Eemshaven. The cables were manufactured and installed by Prysmian.

The Netherlands can import more sustainable electricity via this interconnector cable, mainly wind energy from Denmark. Ensuring security of supply is of great importance to Denmark. The cable makes Dutch capacity available on a structural basis for the Danish electricity grid and vice versa.

Furthermore, the cable connection has been designed in such a way that it will be possible to connect an offshore wind farm at a later stage. In this way, the cable contributes to realizing a sustainable international energy landscape, an important goal of the European Union.

Categories: Subsea Cables Power Generation Connectivity

Related Stories

Russia's Lukoil Takes Up Gunvor’s Offer for Foreign Assets

Sponsored: UAE Breaks Ground on GW-Scale Renewable Energy Hybrid

Pharos Energy Kicks Off Drilling Campaign Offshore Vietnam

Viridien to Shed More Light on Malaysia’s Offshore Oil and Gas Potential

Vietsovpetro Brings BK-24 Oil Platform Online Two Months Early

Propane’s Economic Edge for Ports During Trade Uncertainty

Shell’s Brazil-Bound FPSO Starts Taking Shape

Russia Targets 2028 for Sakhalin-3 Gas Project Start Up

Seatrium Secures ABS Backing for Deepwater FPSO Design

Yinson Production Nets DNV Approval for New FPSO Hull Design

Current News

PTTEP Orders OneSubsea Systems for Two Deepwater Projects off Malaysia

Russia's Lukoil Takes Up Gunvor’s Offer for Foreign Assets

How Hot Is Your Cable? Understanding Subsea Cable Thermal Performance

Sponsored: UAE Breaks Ground on GW-Scale Renewable Energy Hybrid

Pertamina Joins Petronas in Ultra-Deepwater Asset off Indonesia

Malaysia’s Petronas and Oman’s OQEP Strengthen Oil and Gas Ties

Southeast Asia’s 2GW Cross-Border Offshore Wind Scheme Targets 2034 Buildout

Pharos Energy Kicks Off Drilling Campaign Offshore Vietnam

Viridien to Shed More Light on Malaysia’s Offshore Oil and Gas Potential

US Pressure on India Could Propel Russia's Shadow Oil Exports

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com