The transmission system operator Tennet has moved the first submarine cable from the Dutch wind farm zone "Borssele" to the transformer station.

"TenneT has laid the first sea cable to connect the Alpha platform to the transformer substation in Borssele. In the morning of Friday 12 April, VBNK started withdrawing the sea cable on land and early Saturday morning the cable reached the newly built transformer substation," said a press release.

The cable-laying vessel, Giant 7, then repositioned itself in the Honte and started with the most critical part of the installation: crossing the fairway.

Before crossing the channel, shipping traffic to and from the port of Antwerp was blocked until Sunday afternoon. The crossing went completely according to plan and the traffic got back on track in the course of the evening.

In the coming weeks, preparations will be made to also connect the second sea cable for the Borssele Alpha project to the transformer station.

Categories: Energy Wind Power Transmission/Gears Subsea Cables

Related Stories

Aesen, DOC JV Targets Subsea Cable Logistics

SBM Offshore Starts Construction of FSO for Trion Oil Field off Mexico

Russia Targets 2028 for Sakhalin-3 Gas Project Start Up

Hanwha Ocean's Tidal Action Drillship Starts Maiden Job with Petrobras

Aquaterra Energy Nets Subsea Analysis Contracts with INPEX off Indonesia

Floating Offshore Wind Test Center Planned for Japan

Japan Picks Wood Mackenzie to Assess Trump-Backed Alaska LNG Scheme

Marco Polo Picks Salt Ship Design for Next-Gen Offshore Energy CSOV

SPE Offshore Europe 2025 set to drive transformational change for the energy sector

Norwegian Oil Investment Will Peak in '25

Current News

MODEC Ramps Up Hammerhead FPSO Work After ExxonMobil's Go-Ahead

Aesen, DOC JV Targets Subsea Cable Logistics

Timor Gap Boosts Stake in Finder Energy’s Timor-Leste Oil Fields

SBM Offshore Starts Construction of FSO for Trion Oil Field off Mexico

Russia Targets 2028 for Sakhalin-3 Gas Project Start Up

Seatrium Secures ABS Backing for Deepwater FPSO Design

MDL Secures Cable Laying Job in Asia Pacific

Hibiscus Petroleum Starts Drilling at Teal West Field off UK

Yinson Production Nets DNV Approval for New FPSO Hull Design

Hanwha Ocean's Tidal Action Drillship Starts Maiden Job with Petrobras

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com