Installation and testing of the 67 km control umbilical connecting the Sole gas field with the Orbost Gas Plant has been completed, marking the conclusion of the offshore construction phase of the Sole Gas Project, operator Cooper Energy said in an update on Monday.

The offshore project, which was 93% complete at the end of February, is expected to be fully completed, ready and available to deliver gas from the Gippsland Basin offshore Victoria to APA Group’s Orbost Gas Plant by end-May 2019. The only work remaining on the offshore project is repair of the damaged pipe section which is expected to commence in late April, Cooper said.

Onshore, work to upgrade APA Group's Orbost Gas Plant (previously owned and operated by Santos and known as the Patricia Baleen Gas Plant) is well underway, Cooper said. APA is currently assessing the most likely plant completion date within the September quarter and working closely with Cooper Energy to confirm timing and ensure a safe and reliable start-up for the plant.

Gas supply from Sole to the Orbost Gas Plant is expected to commence prior to plant completion for the commissioning and the subsequent plant performance test.

Once operational, the gas plant and the export pipeline will supply treated gas to meet the growing market demand from the Australian eastern seaboard. The Orbost Gas Plant is expected to deliver 68TJ/day into the network.

Categories: Activity Natural Gas Australia/NZ Engineering Subsea Pipelines

Related Stories

ADNOC Gas Signs $3B LNG Supply Deal with India’s HPCL

Thailand's Gulf Energy Eyes Long-Term LNG Supply

OceanMight Gets Petronas’ Offshore Construction Job in Malaysia

Vantris Energy Lands Petronas Job on Malaysia’s Offshore Fields

DOF Bags Two Deals in Asia-Pacific Region

Eni Expands Asian Footprint with Long-Term LNG Contract in Thailand

Mubadala Energy, PLN Energy Primer Team Up for Andaman Sea Gas Supply

Venture Global, Tokyo Gas Ink 20-Year LNG Supply Deal

How Hot Is Your Cable? Understanding Subsea Cable Thermal Performance

RINA Wins FEED Contract for Petronas’ Flagship CCS Project in Malaysia

Current News

Inpex Moves to Accelerate Indonesia’s Abadi LNG Project

Chevron in Final Talks with Eneos, Glencore on Singapore Assets Sale

Seadrill Firms Up Offshore Drilling Workload with Multi-Region Contract Awards

Turkish Petroleum, Chevron Discuss Joint Oil and Gas Exploration

ADNOC Gas Signs $3B LNG Supply Deal with India’s HPCL

Samos Energy Buys Suksan Salamander FSO from Altera Infrastructure

Philippines Makes First Offshore Gas Discovery in Over a Decade

Woodside to Supply LNG to JERA During Japan's Winter Peak

Fugro, PTSC G&S Extend Partnership for Vietnam's Offshore Wind Push

Thailand's Gulf Energy Eyes Long-Term LNG Supply

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com