Deutsche Bucht Completes Offshore Wind Foundations

Laxman Pai
Wednesday, January 9, 2019

Northland Deutsche Bucht has completed the installation of all 31 foundations for its offshore wind farm project in the North Sea.

The  Canadian power producer of Northland Power's third offshore wind farm which is  about 95 kilometres to the northwet of the North Sea island of Borkum in Germany’s Exclusive Economic Zone (EEZ), pointed out that this successfully concludes the first phase of construction within the planned timeframe.

Jens Poulsen, Project Director of Northland Deutsche Bucht GmbH, says: “Installation work on the construction site, which is more than 100 kilometers off the coast, is a real challenge in the winter months. But thanks to the flexible and efficient work of our project team and our contract partners, we were able to install all foundations safely and on schedule.”
The next construction phase, inter-array medium-voltage cabling, is set to start this spring.

Reloading of the foundations onto the installation vessel Scylla at the offshore base port in Cuxhaven went off without a hitch. The monopiles, measuring an average of 78 metres in length, were delivered from Rostock as needed and loaded directly onto the installation vessel.

The transition pieces, which measure 26 meters in height and serve as connecting elements to the 8.4 MW wind turbine, were transported to Cuxhaven from their production location in Spain by heavy lift vessel.

They were offloaded for interim storage in Cuxhaven until installation.

Further, two Mono Bucket foundations are to be erected in addition to the 31 monopiles during the second quarter of this year. Deutsche Bucht is the first offshore wind farm worldwide to test this innovative foundation under commercial operating conditions.

After its completion, the 269 MW offshore wind farm is expected to produce 1.1 billion kilowatthours annually, which will serve the energy needs of approximately 328,000 households.

Categories: Wind Power Offshore Energy Offshore Wind Installation

Related Stories

SBM Offshore, SLB to Optimize FPSO Performance Using AI

MODEC Ramps Up Hammerhead FPSO Work After ExxonMobil's Go-Ahead

Aesen, DOC JV Targets Subsea Cable Logistics

SBM Offshore Starts Construction of FSO for Trion Oil Field off Mexico

Russia Targets 2028 for Sakhalin-3 Gas Project Start Up

Yinson Production Nets DNV Approval for New FPSO Hull Design

PV Drilling Takes Ownership of Noble Corporation’s Stacked Jack-Up Rig

Floating Offshore Wind Test Center Planned for Japan

Marco Polo Picks Salt Ship Design for Next-Gen Offshore Energy CSOV

China Rolls Out 17MW Floating Wind Turbine Prototype

Current News

Shell’s Brazil-Bound FPSO Starts Taking Shape

Ventura Offshore’s Semi-Sub Rig to Keep Drilling for Eni in Asia

SBM Offshore, SLB to Optimize FPSO Performance Using AI

MODEC Ramps Up Hammerhead FPSO Work After ExxonMobil's Go-Ahead

Aesen, DOC JV Targets Subsea Cable Logistics

Timor Gap Boosts Stake in Finder Energy’s Timor-Leste Oil Fields

SBM Offshore Starts Construction of FSO for Trion Oil Field off Mexico

Russia Targets 2028 for Sakhalin-3 Gas Project Start Up

Seatrium Secures ABS Backing for Deepwater FPSO Design

MDL Secures Cable Laying Job in Asia Pacific

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com