Hornsea One Export Cable Installation Completed

Tuesday, December 11, 2018

The installation of export cables at the world's largest offshore wind farm, Hornsea One in the North Sea off the coast of England, has been completed several months ahead of schedule, Danish operator Ørsted announced Tuesday.

With offshore export cables totaling 467km, plus an onshore cable route of 38km connecting each of the three strings to the national grid, it is the longest AC offshore wind export cable system ever to have been installed. The cables were manufactured by NKT at their facilities in Cologne and Karlskrona.

Tideway BV installed the three landfall cable sections using sub-Contractor VBMS and their vessel Ndurance. The remainder of the cable sections were laid using Ocean Yield’s vessel Connector, and later Tideway’s own vessel Living Stone.

The Connector has two large turntables with capacity to hold up to 6,000 and 3,000 metric ton cables, and has laid subsea cables since 2012 in a range of different water depths. For this job, the Connector lay-system was been replaced with a bespoke back deck cable lay spread designed and installed by Tideway for the Hornsea export cable project.

The Living Stone, which came into operational this year, is equipped with a dual-lane cable installation system, consisting out of two cable highways - one for laying the cable and one where the next cable can be simultaneously prepared and have the cable protection system (CPS) installed. This reduces the time needed for preparing the cables, minimizes the manual handling and risk of damaging the cable and increases the vessel’s workability.

The 1.2GW capacity Hornsea One, a 50/50 joint venture between Ørsted A/S and Global Infrastructure Partners, is a record-setting project in more ways than one. When fully operational in 2020, its 174 Siemens 7MW turbines will generate enough clean electricity for well over one million homes. The electricity generated out at sea will pass through one of three offshore substations, before being carried by three high voltage subsea export cables (245kV), via the reactive compensation station, to shore.

“This record-breaking project is a step up in scale from the offshore wind farms we have today,” Duncan Clark, program director for Hornsea Projects One and Two. “It will be the first offshore wind farm in the world with a capacity over 1GW, and at 120km out to sea, we are pioneering new technology and really at the forefront of scaling up clean energy infrastructure with each phase we complete.

“Over 35 vessels were involved in delivering the installation, which was conducted safely and efficiently by all. An incredible feat of logistical coordination, and truly a landmark achievement for both the project and the growing offshore wind industry across the globe.”

Termination and testing is being completed ahead of schedule, and is expected to conclude within the first months of 2019.

In November, Ørsted announced that more than 100 of the 174 foundations have now been installed, and turbine installation is expected to commence in Q1 2019.

Categories: Subsea Activity Construction Renewables Hardware Construction Vessel Energy Offshore Energy Renewable Energy Engineering

Related Stories

MDL Secures Cable Laying Job in Asia Pacific

Chinese Contractor Secures Offshore Oil and Gas ‘Mega Deal’ from QatarEnergy

DOF Secures Moorings Hook-Up Job in Asia Pacific

Floating Offshore Wind Test Center Planned for Japan

Technip Energies Gets FEED Job for Inpex’ Abadi LNG Project in Indonesia

PXGEO Nets First Seismic Survey off Malaysia

Norwegian Oil Investment Will Peak in '25

Seatrium Engages Axess Group to Clear FPSOs for Brazil Deployment

Inpex Picks FEED Contractors for Abadi LNG Onshore Plant

Sapura Energy Rebrands to Vantris Energy

Current News

MODEC Ramps Up Hammerhead FPSO Work After ExxonMobil's Go-Ahead

Aesen, DOC JV Targets Subsea Cable Logistics

Timor Gap Boosts Stake in Finder Energy’s Timor-Leste Oil Fields

SBM Offshore Starts Construction of FSO for Trion Oil Field off Mexico

Russia Targets 2028 for Sakhalin-3 Gas Project Start Up

Seatrium Secures ABS Backing for Deepwater FPSO Design

MDL Secures Cable Laying Job in Asia Pacific

Hibiscus Petroleum Starts Drilling at Teal West Field off UK

Yinson Production Nets DNV Approval for New FPSO Hull Design

Hanwha Ocean's Tidal Action Drillship Starts Maiden Job with Petrobras

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com