Johan Sverdrup Drilling Platform Installed

Posted by Michelle Howard
Monday, June 4, 2018

The 22,000-tonne topside for the drilling platform was lifted into position in one single lift on the Johan Sverdrup field last weekend. Equinor and the Johan Sverdrup partners are the first users in the world of this ground-breaking technology.

On Thursday, May 31, the topside for the Johan Sverdrup drilling platform sailed from the Aibel yard in Haugesund to Bømlafjorden at Stord.

Here the 22,000-tonne steel structure was transferred from the barge to Pioneering Spirit, the world’s biggest heavy-lift vessel. All set for the 11-hour journey to the jacket waiting for its topside on the Johan Sverdrup field.

After initial preparations, the actual installation job took only three hours. This makes it likely the fastest ever installation of a large, fully completed topside. The second of four platforms in the first development phase of the giant Johan Sverdrup field is thus installed.

“This is an important milestone in the Johan Sverdrup installation campaign. Two of the four Johan Sverdrup platforms are now in place. The power cables to the field were rolled out last week, and so far, the installation of Norway’s biggest oil pipeline has gone very well, so this is definitely moving in the right direction,” says Trond Bokn, senior vice president for Johan Sverdrup at Equinor.

“At the same time, much work remains, and we must maintain extra focus on safety and quality in the execution phase. But we can breathe a bit more easily now that the drilling platform is installed – this is the first ever such operation in the world,” Bokn adds.

Ståle Hanssen, project manager for Johan Sverdrup jackets, installation and commissioning, describes the technology enabling single-lift installation of big platforms as a game changer for the industry.

Up until now big topsides have been modular in design. No crane vessels have been able to lift more than 12,000 tonnes in one lift. The brand new lifting technology on Allseas‘ Pioneering Spirit vessel, however, allows entire topsides of up to 48,000 tonnes to be lifted in one, single lift.

The technology was initially developed for the removal of scrapped platforms. Equinor is the first user of the technology for the installation of big, new topsides. This allows for great savings in the construction and installation phases, both in terms of manhours and costs, and, not least, reduces risks related to health, environment and safety.

“Equinor and the Johan Sverdrup partnership, working closely with Allseas, make a break-through for the industry here. The safety-, schedule- and cost-related benefits are substantial, and we expect that many others will follow suit,” says Hanssen.

“At the same time making the Johan Sverdrup planning puzzle so dependent on a vessel that was in fact at the time not even fully completed was no easy decision. We of course spent much time with the Johan Sverdrup partnership before coming to this conclusion,” he says.

Pioneering Spirit will return to the Johan Sverdrup field in the spring of 2019, to install the two last topside structures in the first phase of the development, for the processing platform and the utility and accommodation platform.

Overall the use of Pioneering Spirit will help cut one million manhours offshore. This enabled the Johan Sverdrup partnership to deliver a Plan for development and operation (PDO) for Phase 1 of the development which included a three-to-six months earlier start-up of the field than would have been possible with the alternative topside installation solution. At the same time this helped cut the estimated costs for the PDO by almost NOK 1 billion.

The drilling platform on stream from the autumn of 2018
The Johan Sverdrup drilling platform is now fully completed and 85 percent fully tested. The last phase - hook-up and testing – starts now. The platform is due to become operational this autumn, and the tie-back to the platform of eight wells pre-drilled by the Deepsea Atlantic semi-submersible in 2016 starts towards the end of the year.

“We look forward to putting the drilling platform on stream, and completing the pre-drilled wells towards the end of the year and next year, preparing for first oil in late 2019,” says Stig Åtland, head of drilling and well for Johan Sverdrup.

Then the drilling platform will start drilling new wells on the field, both for the first and second phase of the Johan Sverdrup development. Overall, as many as 48 wells may be drilled.

Categories: Offshore Energy Technology Energy Offshore

Related Stories

Baker Hughes Sets Up Global Network to Bolster Mature Oil and Gas Fields Production

Big Oil Pockets Near-Record Profits but Spending Restraint Signals Long-Term Doubts

Strohm Nets Ultra-Deepwater Supply Deal for Southeast Asia’s Gas Scheme

Riyadh Attacks Disrupt Oil Majors' Summit Plans

Oil Climbs on US Storm Threat, Saudi Attack Risks

Iran Set to Keep Hormuz Shut Until Seven Demands Are Met

Solstad Maritime Secures APAC Drilling Support Work for AHTS Pair

KKB Unit to Deliver Offshore Structures for Shell’s Malaysian Fields

Oil Goes Down 2% as Saudi Supply Concerns Recede

MODEC, Eld Energy Advance Fuel Cell Power for FPSOs

Current News

Baker Hughes Sets Up Global Network to Bolster Mature Oil and Gas Fields Production

Valaris Secures $600M in New Contracts as Backlog Rises to $4.8B

Production Restart at Australian Offshore Fields Boosts Jadestone's Oil Output

Aramco Targets Hormuz Bypass with East-West Pipeline Expansion

ADES Lands New Offshore Drilling Rig Deals in Angola and Indonesia

Shell to Exit Australia's North West Shelf Project in $1.45B Deal with XRG

Aramco Third Quarter Profit Up 35% Despite War Disruptions

Eni, Petronas JV Brings Indonesian Offshore Gas Field Online

CNOOC Set to Restore Production at Major South China Sea Gas Field

Big Oil Pockets Near-Record Profits but Spending Restraint Signals Long-Term Doubts

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com