Jumbo Completes Work on Bangladesh FLNG Terminal

Posted by Michelle Howard
Friday, May 4, 2018

In 2017 Jumbo was awarded a contract by Geocean for the Moheshkhali Project, which is seeing a floating liquefied natural gas (LNG) import terminal developed off the shores of Moheshkhali Island in the Bay of Bengal, Bangladesh. It will be the country's first LNG import terminal and is expected to help secure the future provision of energy for Bangladesh.

The Moheshkhali floating LNG import terminal will also include a floating storage and regasification unit (FSRU), a subsea buoy system and a subsea pipeline, which will connect the terminal to an onshore pipeline system.

Jumbo was contracted to transport and install the mooring system for the FSRU. This involved installing eight suction piles/anchors, one pipeline end terminal (PLEM) and one pad as well as scouring protection.

Mobilization began in mid-December 2017 with the installation execution going ahead in early January 2018. Works on the project have now been successfully completed by the Jumbo offshore team and all the experienced crew aboard the Jumbo Javelin.

Tom Rijnders, Project Manager Jumbo, said, “Conditions on this project were at times challenging due to strong currents and poor visibility, however, the crew on board managed to perform outstandingly with a lot of ingenuity and persistence to complete the project within specifications.”

Categories: Contracts Ports Offshore LNG Offshore Energy

Related Stories

Iran Outlines Terms for Restoring Hormuz Shipping

BP Moves Indonesia CCUS Project Into Offshore Installation Phase

QatarEnergy Prolongs LNG Force Majeure, Charters Out Tankers

ABL Gets Papua New Guinea FSO Job

Oil Rises 2% as Middle East Hostilities Escalate

LNG Tankers Resume Hormuz Crossings Amid Tensions

Hormuz Standoff Risks Chronic Instability for Gulf Oil Flows

From Fixtures to Values: Where the Jackup Recovery Is Already Being Priced

Ruwais LNG Commitments Top 90% Capacity with New INPEX Deal

Yinson Production Names FSO for Murphy's Lac Da Vang Project off Vietnam

Current News

PTTEP, Petronas Ink 35-Year Malaysia-Thailand Gas Deals

Iran Outlines Terms for Restoring Hormuz Shipping

Technip Energies Nets Engineering Services Job for ADNOC Offshore

Seatrium Nears Dual FPSO Sailaway for Petrobras' Búzios Field

Strait of Hormuz Shipping Marks Slight Rise

China's CNOOC Posts Record First-Half Profit

BP Completes Central Azeri Platform Maintenance, Ramps Up Production

Iran-Oman Talks on Hormuz Reopening Drive Down Oil Prices

Viridien Progresses Hybrid Multi-Client Survey Offshore Malaysia

TGS Extends Work on Indonesia’s Largest Seismic Acquisition Project

Subscribe for AOG Digital E‑News

AOG Digital E-News is the subsea industry's largest circulation and most authoritative ENews Service, delivered to your Email three times per week

https://accounts.newwavemedia.com