Norwegian major Equinor has awarded an engineering, procurement and construction (EPC) contract to domestic services company Aibel for the final bridge on the Johan Sverdrup field.The deal, worth an estimated NOK 200 million, was included as…
South Korean shipbuilder Samsung Heavy Industries (SHI) has successfully completed the processing platform (P1) for Johan Sverdrup Field development and delivered it to Equinor according to the scheduled delivery date stated in the original contract…
Kvaerner and Aker Solutions on Thursday cut the first steel plate for the second phase of the Johan Sverdrup offshore field development, kicking off Norway’s largest industrial project in three decades.The two Norwegian engineering firms have been working in a 50/50 joint venture under a NOK 3…
Denmark-based cable supplier NKT said it has received a letter of award from Norway's Equinor to supply and install a cable system of 200 kilometers of 80 kV high-voltage DC offshore power cables for the second phase of the Johan Sverdrup oil field development project in the Norwegian North Sea…
Norway's Kvaerner announced that it has signed a contract worth approximately $107 million (NOK 900 million) with Equinor for the delivery of a steel substructure for the Johan Sverdrup Phase 2 process platform.“With this contract, Kværner and…
With a flip of the switch, Kjell-Børge Freiberg, Norway's Minister of Petroleum and Energy, opened a new era in offshore oil and gas operations, initiating the 'power-from-shore solution' that will provide the Johan Sverdrup field in the North Sea with electricity for more than 50 years…
The Danish cable manufacturer NKT has received a letter of award by Equinor Energy AS to supply and install a cable system of 200 kilometres of 80 kV high-voltage DC offshore power cables for the second phase of the Johan Sverdrup oil field development project in Norway…
Statoil, on behalf of the Johan Sverdrup partnership, signed a letter of intent with Aibel for the construction of the processing platform topside for phase 2 of the project. A letter of intent for field center modifications is also issued to a joint venture of Aker Solutions and Kværner…
Aker Solutions has won a contract to provide umbilicals for the Statoil-operated Johan Sverdrup, Utgard and Bauge developments offshore Norway. The order entails delivery of a total of more than 40km of subsea umbilicals. 'By combining…
Aibel lifted the final three modules into place for the Johan Sverdrup drilling platform earlier this week. The platform arrived in Haugesund on 5 September, where the facility will remain for hook-up and preparation work, until it is handed over to Statoil in mid-2018…
Phase 1 of the massive Johan Sverdrup project offshore Norway is now close to 60% complete, ahead of schedule and even further under the original estimated budget, says partners Aker BP and Lundin. In statements released this morning…
Statoil successfully installed the largest jacket on the Norwegian Continental Shelf (NCS) at its Johan Sverdrup project, giving the Norwegian giant the first visible sign of the field. The jacket…
Statoil has awarded Ocean Installer a contract for subsea installations and tie-in operations on Johan Sverdrup, Utgard, and Bauge. Normand Vision. Image from Ocean Installer. The…
Statoil and its partners have agreed to move forward with a US$5.92-6.51 billion second phase development of the giant Johan Sverdrup field offshore Norway at a sub-$30/bbl break even price. The cost is half that estimated, when Statoil…
Norway’s Petroleum Safety Authority (PSA) has cleared Statoil for the design engineering of the drilling platform for the Johan Sverdrup field, in addition to giving the Norwegian giant approval to use the Haven jackup at the field. Image of Haven…